Review the Basic concepts and definitions of Lean (p. 199). Then:
The choice of tool or method to improve process flow and speed depends on what type of problem(s) you find after completing the value stream map (VSM).
Once you've implemented these improvements, use Visual Process Controls, p. 237, to maintain the gains.
Total Lead Time (also called process cycle time, process lead time, or total cycle time): the time from when a work item (product, order, etc.) enters a process until it exists.
Things-in-Process (TIP) or Work-In-Process (WIP): Any work item that has entered the process and not yet exited. The "work" can be anything: materials, orders, customers, assemblies, emails, etc.
Average Completion Rate (Exit Rate or Throughput): The output of a process over a defined period of time.
Capacity: The maximum amount of product or service (output) a process can deliver over a continuous period of time.
Take Rate (customer demand rate): The amount of product or service required by customers over a continuous period of time. Processes should be timed to produce at the takt rate. Any lower and you will be disappointing customers; any higher and you will be producing output that cannot be used.
Time Trap: Any process step (activity) that inserts delay time into a process.
Capacity Constraint: An activity in the process that is unable to produce at the completion (exit) rate required to meet customer demand (takt rate).
Value-add (VA) time: any process step or activity that transforms the form, fit, or function of the product or service for which the customer is willing to pay
Non-value-add (NVA) cost: Waste in a process. Customers would be willing to buy a product or service that did not have these costs if it meant a lower price.
See also p. 49 for more on value-add and non-value-add concepts, and the next section for metrics associated with Lean.
The purpose of the tools in this chapter is to improve how time and energy are spent in a process. The three metrics described here can help you identify the sources and impact of inefficiency.
1 Process Cycle Efficiency (PCE)
The best measure of overall process health is Process Cycle Efficiency (PCE), the percentage of value-add time (work that changes the form, fit, or function as desired by the customer).
You can either measure total lead time directly by measuring the time it takes "things in process" to transit the process, or use Little's Law (see next page) to determine an average.
2 Little's Law
One component of PCE is Total Lead Time, which can be described by Little's Law:
This shows how lead time is related to the number of things in process (TIP, also known as WIP) and the completion (exit) rate of the process.
To improve Total Lead Time, and in turn PCE, either increase capacity (average completion rate) and/or reduce TIP or WIP.
3 Workstation Turnover Time
Workstation Turnover Time (WTT) for a given process step or workstation is the amount of time needed to set up and complete one cycle of work on all the different "things" (work items, SKUs) at that step. WTT is important in improvement efforts because it helps highlight which process step (time trap) to work on first.
Calculating WTT for a process step
WTTk=Σ[(Setup Timei) + (Process Timei * Batch Sizei)]
Capacity: The maximum output a process can deliver over a continuous period of time
Capacity Constraint: An activity in a process that is unable to produce at the exit rate required to meet customer demand
Time Trap: Any process step that inserts delay into a process
Focus on identifying time traps if the goal of your project is to improve efficiencies (in inventory, lead time, output rates, etc.). Work on the time trap that is injecting the most amount of delay into your process first.
Focus on identifying capacity constraints if the goal of your project is to increase output to meet real customer demand.
To quantify how much time delay each step or activity introduces into the process
The basis of capacity constraint identification is takt rate (customer demand rate) analysis, which compares the task time of each process (or process step) to:
Step 1: Gather needed data
Determine:
Step 2: Calculate takt rate (customer demand)
Takt rate = (number of units to process)/(net operating time available)
Takt time = inverse of takt rate (net operating time available)/(number of units to process)
Step 3: Analyze the figures
To determine which process step is the biggest time trap, simply calculate WTT for each step in the process. Here's the WTT equation from p. 201:
WTTk=Σ[(Setup Timei) + (Process Timei * Batch Sizei)]
The step with the longest WTT is the time trap that is injecting the most amount of delay into the process.
Taking action
Examine the data you plugged into the WTT equation for the Time Trap. If the problem lies in setup time, use the Four Step Rapid Setup Method (p. 223); for Process Time, use 5S (see below) and other flow-improvement tools. Review Batch Sizing principles on p. 222 if that is the problem. Once improvements have been made, find the new "biggest" time trap and continue until you've reached your improvement goals.
To create and maintain an organized, clean, safe, and high-performance workplace.
Sort: Clearly distinguish needed items from unneeded items and eliminate the latter
Set in order (also known as Simplify): Keep needed items in the correct place to allow for easy and immediate retrieval
Shine (also known as Sweep): Keep the work area swept and clean
Standardize: Standardized cleanup (the first three S's)
Sustain (also known as Self-Discipline): Make a habit of maintaining established procedures
Goal: Remove all items from the workplace that are not needed for current production or tasks.
Put a red tag on any item that is not essential to doing the work and move it to a holding area. (An example tag is shown below.)
RED TAG |
|||
---|---|---|---|
Red Tag No. |
|||
Date Tagged |
|||
Department |
|||
Category |
1 |
Inventory |
|
2 |
Machines and Other Equipment |
||
3 |
Dies, jigs, and fixtures |
||
4 |
Tools and supplies |
||
5 |
Other (Explain) |
||
Item |
|||
Description |
|||
Qty. |
|||
Total Value $ |
|||
Desposition/Evaluation |
Date |
||
a |
Moved to Red Tag Location |
||
b |
Disposed of |
||
c |
Moved to More Suitable Location |
||
d |
Left Exactly Where It Was |
After one week in a holding area, tagged items should be:
Set in order means to arrange needed items in the area and to identify or label them so that anyone can find them or put them away.
GOAL: To arrange all needed work items in line with the physical workflow, and make them easy to locate and use
1 Draw a current-state map
Show the location of all materials, supplies, forms, etc., needed in this workspace.
2 Draw a future-state map
Draw a picture of how you think the workspace could be laid out for better efficiency and effectiveness. Make the map large enough so people can post improvement ideas on "5S tags." The new map should…
3 Visually organize the workplace
Shine emphasizes removing the dirt, grime, and dust from the work area. This is a program of keeping the work area swept area swept and clean of debris.
1 Determine the shine targets
Think about…
2 Set a housekeeping schedule and assign responsibilities
List responsibilities in detail, including which areas to be cleaned, at which times of the day, and what "cleaning" involves. Assign responsibility for completing housekeeping chores.
IT Dept Housekeeping Assignments Week Ending ___/___/___ |
|||||||
---|---|---|---|---|---|---|---|
Task |
Assigned To |
Mon |
Tue |
Wed |
Thu |
Fri |
Comments |
IT Request Inbox |
Daily |
||||||
Computers in Setup |
Daily |
||||||
Supply Table |
Weekly |
||||||
Repairs/Swaps |
Weekly |
||||||
Swap Cabinet |
Weekly |
||||||
Consumables: |
Daily |
||||||
Paper for Printer |
Daily |
||||||
Printer Cartridge |
Daily |
||||||
Blank CDs |
Daily |
||||||
Floppy Diskc |
Daily |
||||||
Office Furniture |
Weekly |
||||||
Priority Board |
Daily |
||||||
Archive (Equip List) |
Daily |
||||||
3 Create procedures for continued daily shine processes
Create a table that shows which housekeeping tasks must be performed, how often, and by whom.
4 Set periodic inspection and targets for machinery, equipment, computers, furnishings, etc.
Standardize mean creating a consistent way of implementing the tasks performed daily, including Sort, Set in order, and Shine. It means doing "the right things the right way, every time."
Tips for standardize
Elements of a 5S agreement
Sustain means that the 5S program has a discipline that ensures its continued success.
5S audit sheet
A. |
Sort |
0 |
1 |
2 |
3 |
4 |
5 |
|
---|---|---|---|---|---|---|---|---|
1> |
Are there unnecessary items (peripherals, supplies) on the setup desk |
X |
||||||
2> |
Are there scrap supplies in the supply bins |
X |
||||||
3> |
ARE there old computers (off lease) in the swap cabinet |
X |
||||||
4> |
Is there more furniture than necessary in the office |
X |
||||||
Score |
0 |
0 |
0 |
0 |
0 |
20 |
B. |
Set in Order |
0 |
1 |
2 |
3 |
4 |
5 |
|
---|---|---|---|---|---|---|---|---|
5> |
Is the supply table arranged per drawing/layout |
X |
||||||
6> |
Is setup desk arranged per layout (incl. a single computer) |
X |
||||||
7> |
Is swap cabinet arranged per layout |
X |
||||||
8> |
Can ANYONE determine normal from abnormal |
X |
||||||
Score |
0 |
0 |
0 |
0 |
0 |
20 |
C. |
Shine |
0 |
1 |
2 |
3 |
4 |
5 |
|
---|---|---|---|---|---|---|---|---|
9> |
Is the desk clean and maintained or is there clutter (unnecessary supplies, etc.) |
X |
||||||
10> |
Is Supply Table/Bins clean and organized |
X |
||||||
11> |
Has the shine check sheet been updated (assignments been worked) |
X |
||||||
12> |
Is dust filter clean |
X |
||||||
Score |
0 |
0 |
0 |
0 |
0 |
20 |
D |
Standardize |
0 |
1 |
2 |
3 |
4 |
5 |
|
---|---|---|---|---|---|---|---|---|
13> |
Is the IT Dept Process Handbook in plain view |
X |
||||||
14> |
Is the IT Dept Process Handbook updated |
X |
||||||
15> |
ARE all supply bin, swap cabinet, and software shelf labels intact |
X |
||||||
16> |
Have all setups gone accordingly to instructions this week |
X |
||||||
Score |
0 |
0 |
0 |
0 |
0 |
20 |
E. |
Sustain score |
0 |
1 |
2 |
3 |
4 |
5 |
|
---|---|---|---|---|---|---|---|---|
17> |
Was the last audit less than two weeks ago |
X |
||||||
18> |
Was the last departmental audit less than one month ago |
X |
||||||
19> |
Is the 5S board up to date (pics, metrics, shine, etc.) |
X |
||||||
20> |
Has anyone complemented the area on its cleanliness & organization |
X |
||||||
Score |
0 |
0 |
0 |
0 |
0 |
20 |
||
Area: |
||||||||
Auditor(s): |
Section |
A |
B |
C |
D |
E |
||
Date: |
Sub-total Score |
20 |
20 |
20 |
20 |
20 |
To place a limit, or cap, on the maximum number of things or work in process (TIP or WIP), so that the lead time is known and predictable (see Little's Law, p. 201). You can then apply improvement tools to reduce TIP or WIP by eliminating the effects of variation and batch size.
Whenever lead times are critical to satisfy customers and when non-value-add cost is significant compared to value-add cost.
Part 1: Determine the WIP Cap
(maximum amount of work or things that should be in process at any given time)
(See p. 201 for more on PCE)
<< low end, multiply current PCE by 10 (one order of magnitude improvement) for use as target PCE < low end, use low-end figure as target PCE = or > low end, use high end as target PCE >> high end, move towards one-piece flow
Application |
Typical (low end) |
World-Class (high end) |
---|---|---|
Machining |
1% |
20% |
Fabrication |
10% |
25% |
Continuous Manufacturing |
5% |
30% |
Business Processes (Service) |
10% |
50% |
Business Processes (Creative/Cognitive) |
5% |
25% |
Determine the maximum WIP allowed within the process at any time.
Part 2: Releasing work into the system
Typically the current WIP level will be significantly greater than the WIP Cap level. Therefore, you need a plan to reduce current WIP and to release work into the system to match the exit rate.
Caution |
as the PCE of a process approaches world-class levels, the effects of variation are magnified. Be careful not to reduce the TIP or WIP too much before addressing issues with variability, or a process step could be "starved" for work, creating a constraint! |
Ex: When people complete a work item, have them send an alert card or email to the "control" person (such as Kanban cards you often find in manufacturing)
To eliminate shortages or overstocking of supplies by creating a system where items are automatically replaced as they are used up.
Use a replenishment pull system for in-process or end-item products, supplies, consumables (or any other item for which shortages and stockouts are not acceptable), which meet the following criteria:
A replenishment pull system should never be installed without a Generic Pull System already in place.
Warning |
historical usage may not reflect coming changes in the business (product or service mix, volume increases, etc.) So often a combination of factors should be considered. |
Handling seasonality
There are many ways to calculate safety stock. This method is based on empirical computations and experience.
Safety Stock = σ*service level*(LT)β
Where.&
Other useful formulas
Maximum inventory in the pull system loop
Minimum expected BOH inventory in the pull system loop
Defining whether or not to order
Order quantity if necessary (ROUND UP to nearest recommended multiple order quantity)
Average On Hand inventory
Where: BOH = Balance on Hand, the quantity of inventory in the strategic buffer
Where: OOQ = the number of items on order at any given time
A 2-Bin Replenishment Pull System is a simplified version of a standard replenishment pull system that uses just two bins of the stock item being replenished.
Bin Quantity = max (LT, OI) * DMD + SS/2
Option 1: Line-Side replenishment
Option 2: Point-of-use stocking
2-Bin POU stocking is used when restocking is not an issue
Note on Management Policy: the batch size is often set by management based on the EOQ formula or the demand for a fixed time period (a month's worth, a week's worth, etc.). Both methods result in lead times and inventory levels that are generally 30% to 80% larger than the process requires.
To have a Lean system operating at peak efficiency with lowest cost, you should compute the minimum safe batch size from the formula shown here.
Assumption: all products have the same demand and process parameters.
There is a more sophisticated version of the equation (protected by U.S. patents) that you can find in Lean Six Sigma, McGraw-Hill, 2001.
The above formulas do not account for variation in demand, which is addressed two ways:
Where ñ = % capacity at which servers are operating
[*]This formula assumes an exponential distribution of arrivals and service times which is adequate to guide the improvement process.
Document all the setup activities and identify them as either:
Tool # 1: Setup documentation worksheet
MACHINE: |
DOCUMENTOR: |
||||
---|---|---|---|---|---|
DATE: |
Page 1 of_ |
||||
SEQ# |
START TIME |
EVENT |
ELAPSED TIME |
INT |
EXT |
1 |
0 |
Shut down machine |
:30 |
:30 |
|
2 |
0:30 |
Get change parts |
3:00 |
3:00 |
|
3 |
3:30 |
Remove change parts from machine |
3:30 |
3:30 |
|
4 |
7:00 |
Place new change parts on machine |
3:30 |
3:30 |
|
5 |
10:30 |
Return change parts to storage |
3:00 |
3:00 |
|
6 |
13:30 |
Load material onto machine |
1:0 |
1:00 |
|
7 |
14:30 |
Generate test piece |
:30 |
:30 |
|
8 |
15:00 |
Measure and inspect |
2:00 |
2:00 |
|
9 |
17:00 |
Adjust dies |
1:00 |
1:00 |
|
10 |
18:00 |
Generate test piece |
:30 |
:30 |
|
11 |
18:30 |
Measure and inspect |
1:30 |
1:30 |
|
12 |
20:00 |
Generate first good piece |
1:00 |
1:00 |
|
TOTAL TIME THIS PAGE: |
21:00 |
||||
TOTAL TIME ALL PAGES: |
21:00 |
Tool # 2: Area Layout
Tip |
You may discover inefficiencies in layout that can be solved with a 5S effort (see p. 206) |
Tool # 3: The "before" timeline
Used to graphically show each event within the setup an highlight which take the longest. Leave room for the "after". See the end of this section for an example that includes both before and after data.
Tool # 4: Improvements worksheet
SEQ# |
IMPROVEMENT |
STEP 1 |
STEPS 2, 3, & 4 |
---|---|---|---|
1 |
Moving "get change parts" to external |
3:00 |
|
2 |
Moving "return change parts" to external |
3:00 |
|
SETUP REDUCTION BY STEP |
6:00 |
||
TOTAL SETUP REDUCTION (STEP 1 and 2, 3, & 4) |
|||
(BST) BEGINNING SETUP TIME |
|||
% SETUP REDUCTION |
(TSR/BST) 100 |
Look for ways to make any setup that must be done by the process operator more efficient.
Highlight conversion to external setup
Before/After chart
(See p. 223 for background on setup reduction)
The underlying principle is the same for reducing setup in transactional processes as it is for manufacturing processes: you want to reduce interruptions to value-add work. The language is a bit different, however.
Step 1. Document and differentiate serial from parallel setup activities
Serial events are activities that cannot (or should not) be performed while any other task is being completed
Ex: All activities by a Teller when dealing with a customer face to face or over the phone (don't want to make customers wait)
Parallel events are activities that could be performed while another task is being completed
Ex: Loading software programs, processing data
Step 2. Convert serial setup activities to parallel setup activities
3. Streamline remaining serial activities
Ex: Moving printers/copiers vs. walking to pick up hard outputs
Ex: Barcoding vs. typing/writing, electronic notepads (that can be hooked into master databases) vs. handwritten notes
Ex: Computing equipment to sort disparate requirements offline (see Lean Six Sigma for Service, McGraw-Hill, 2003)
4. Eliminate adjustments/standardize work
Ex: if people need to look up information, have it available through linked databases and keyword searches
To reduce scheduled and unscheduled downtime from typical levels of 30% to below 5%.
Preventive Maintenance: maintenance that occurs at regular intervals determined by time (Ex: every month) or usage (Ex: every 1000 units)
Predictive Maintenance: maintenance performed on equipment based on signals or diagnostic techniques that indicate deterioration in equipment
Both are common sense approaches for proactively maintaining equipment, eliminating unscheduled downtime, and improving the level of cooperation between Operations and Maintenance.
Prework: Assess current operating conditions
Availability
Performance
Quality
Solution Phase #1: Return equipment to reliable condition
Inspect and clean machine, identify needed repairs, and tag defects that need attention.
Solution Phase #2: Eliminate breakdowns
Solution Phase #3: Develop TPM information database
Solution Phase #4: Eliminate defects
As with any process, metrics are needed to both monitor process performance and understand gains made from the TPM effort
OEE = Availability Level × Operating Level × Quality Level
Mistake prevention is the ability to stop mistakes before they occur.
Mistake proofing is making it impossible for errors to be passed to the next step in the process.
Use when rework to correct errors or process delays downstream (perhaps caused by a lack of material or information) are hurting Process Cycle Efficiency.
If overall lead time suffers because work is improperly balanced (see takt time chart on p. 53), use these principles to help you identify improvements.
To reduce the time needed to complete a task or set of tasks and eliminate opportunity for mistakes.
Whenever you have inefficient workflow (too much movement of people or materials).
You will never get the design perfect the first time around—get it in place, then use operator feedback and process performance to tweak the layout/design,
Phase 1: Prework
Phase 2: Redesign a work cell
U cell
T Line
Z cell
Visual controls include a variety of displays and visual markers in the workplace that help you:
Takt Board: Order Entry Department |
||||
---|---|---|---|---|
Yesterday: 443 Orders 1.61 Orders/Hr |
||||
Today 440 Orders 1.66 Units/Hr |
||||
Hour |
Scheduled |
Actual +− |
Diff |
Comments |
7-8 AM |
60 |
53 |
−7 |
System down f/5 min |
8-9 AM |
60 |
59 |
−8 |
|
9-10 AM |
45 |
48 |
−5 |
|
10-11 AM |
60 |
61 |
−4 |
|
11-12 PM |
30 |
34 |
0 |
Took late lunch |
12-1 PM |
60 |
59 |
−1 |
|
1-2 PM |
50 |
50 |
−1 |
|
2-3 PM |
40 |
41 |
0 |
|
3-4 PM |
35 |
35 |
0 |
Over 7 min: Software issue |
Totals |
440 |
440 |
Issue boards are used to communicate information about the improvement project or ongoing process management.
Process summary
Lists information relevant to your workplace:
Dashboard Metrics
A posted board that lists individuals and summarizes their status with respect to desired training. Can help set priorities for training and help staff know whom to consult with a particular question.
Displays status of 5S Project
The Lean Six Sigma Pocket Toolbook A Quick Reference Guide to Nearly 100 Tools for Improving Process Quality, Speed, and Complexity