Like the Task Information dialog covered earlier, the main place to edit and view detailed resource information is the Resource Information dialog. You get to this dialog by double-clicking on a resource in the Resource Sheet view. This dialog allows users to edit resource calendars, availability data, costs and rates, and resource- related custom fields.
Double-click on the resource you want to edit.
Choose the tab you want to edit.
For Your Information
Extra Fields in Project Professional
If you are using Project Professional, the General tab of the Resource information dialog will contain several more fields not shown here. These fields deal with how Project Server handles resources. The online help covers these fields in detail.