RBS (resource breakdown structure), 429, 431
Record Macro dialog box, 366
recording macros, xxxviii, 365–69
recurring tasks, xxviii, 148–52, 492
Relationship Diagram view, 228
relationships, 44, 492. See also task relationships
remaining costs, 191
Remove button, 75
removing
deadlines from tasks, 147
filters, xxxi, 210
text formatting, 98
replacing resources for cost reductions, xxxvii, 332–33
reports
communicating with stakeholders via, 223
customizing headers and footers, xxiv, 102–4
defined, 21, 30, 492
editing Task, 236
inserting logos on, 103
macros for publishing, 365–69
Overbudget Resources, 316
predefined, 22
previewing, xix, 21–23, 99–100, 238
printing, xxxiii, 85, 99–104, 234–37
project summary, 259–64
setting page options for, xxxii, 226–27
stoplight view, 317–21, 456–60
viewing multiple pages, 101–2
Reports dialog box, 2, 99, 234
rescheduling
duration, 140–44
incomplete work, xxxv, 295–99
split tasks and, 296, 298
resizing row height, 217
Resource Allocation view, 181
resource breakdown structure (RBS), 429, 431
resource calendars. See also calendars
adjusting, 66–68
defined, 492
importing Outlook appointments and events for, 442
resource costs, working with, 316
Resource Form, 399
Resource Graph view, 180, 185
Resource Information dialog box, 60–61, 68, 157, 400–401
resource leveling
defined, 184–85, 492
exercise in, 186–90
slack, 187
split tasks and, 137
Resource Leveling dialog box, 185, 186–90
resource manager, 492
resource notes, xxii, 69
resource outline codes, 429
resource pools, 63, 392–97. See also sharer plans
about, 392–93, 416
advantages of, 393
clearing assignments for deleted sharer plans, 409
creating, xl, 393–96
defined, 392, 492
designating project plans as, 397
editing calendars in, 416
enterprise, 424
linking project plans to, xli, 404–6
naming, 394
options for opening, 404
saving changes to resource details, 408
updating, xl–xli, 400–401, 403, 406–9
viewing assignment details in, xl, 397–99
Resource Sheet view, 16, 198–99, 201, 332, 394
Resource Substitution Wizard, xlii, 429–36, 439
Resource Usage view, 16, 175, 179, 195, 428
resources, 55–69. See also generic resources; material resources; resource pools; work resources
adjusting resource calendar, 66–68
allocating tasks to category of workers, 59
allocating throughout project, 173–80
applying different cost rates for, xxix, 166–67, 170
applying pay rates at different times, xxviii, 157–59
assigning material resources to tasks, 82–83
collecting actuals from, 295
comparing work and materials, 63
consumption rates for material, xxix, 167–70
creating, 61
creating issues, xliv, 467–69
customizing availability of, xxviii–xxix, 159–61, 167, 170
defined, 475, 492
delaying start of assignments, xxix, 161–62, 170
displaying overbudget, xxxvi, 312–13, 320–21
editing assignments, 182–83
entering pay rates for, xxii, 64–65
equipment, 60–62
evaluating costs, 313–16
fully allocated, 173, 392, 488
getting accurate cost information for, 65
grades of, 480
grouping data about, xxxi, 202–6, 218
handling actuals submitted from, xliv, 450–55
importing information from address book, 57
leveling overallocated, xxx, 184–90
manually resolving overallocations, xxx, 180–84
material, xxi–xxii, 62–63, 69
maximum units, 58–60, 61–62, 174, 195
multiple pay rates for, xxviii, 155–57
notes for, xxii, 69
overallocating, 71, 83, 174
overview, 55
resources (continued)
permanently renumbering, 199, 315
replacing, xxxvii, 332–33, 429–36
setting up sharer plans for, 395–96
shortening assignments for, 330–34
sorting, xxxvi, 314–16
staffing enterprise project with, 427–36
underallocated, 173, 392, 495
updating task status without updating, 295
work, xxi, 55–60
risks, 39
associating with project plan, xliv, 464–66
defined, 464, 492
issues vs., 464, 472
types of associations for, 464, 472
viewing status and owner, 466
rolling down values, 283, 299
rolling up
baselines, 281
project information, 409
values, 283
running macros, xxxviii, 368–69