The project buffer as a diagnostic

During the critical chain planning process a project buffer is created at the end of the project and feed buffers are created to separate critical tasks from non-critical ones. During the project the current state of these buffers is an easily understandable shorthand for the status of the project. It is to be expected that projects will often use some of the buffer (after all, the original task duration estimates were only 50% likely times), but managers should take action if it seems likely that all the buffer will be used, since this means that the project will be late overall.

The danger level of buffer usage depends on how much work there is still to be done: 40% buffer usage would be a serious warning sign on a project which is only 15% complete, but is probably not a problem on a project which is 85% complete (see Figure A.9). As a rule of thumb, a project manager should

Figure A.9. Buffer usage and project status


  • plan recovery actions if the buffer usage exceeds one-third of the progress-adjusted buffer (this is the total buffer scaled by the proportion of work remaining to be done); and

  • enact the recovery plan if progress-adjusted buffer usage is greater than two-thirds.

Top of Page



Definitive Guide to Project Management. The Fast Track to Getting the Job Done on Time and on Budget
The Definitive Guide to Project Management: The fast track to getting the job done on time and on budget (2nd Edition)
ISBN: 0273710974
EAN: 2147483647
Year: 2007
Pages: 217
Authors: Sebastian Nokes
BUY ON AMAZON

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net