The fields listed in the following tables (Currency, Date, Duration, Enumerated, Indicator, Integer, Outline Code, Percentage and Number, Text, and Yes/No) are grouped by data type, as follows :
Currency fields
Date fields
Duration fields
Enumerated fields
Indicator fields
Integer fields
Outline code fields
Percentage and number fields
Text fields
Yes/No (Boolean) fields
Table B-1 lists all currency and currency rate fields available in Microsoft Project.
Cross-References | For more information about working with costs, see Chapter 8, "Planning Resource and Task Costs," and "Monitoring and Adjusting Costs". For more information about analyzing project information with earned value, see Chapter 13, "Analyzing Project Information." |
Field | Available Categories | OLE DB Provider | Microsoft Project Database | Description |
---|---|---|---|---|
Actual Cost | Assignment | AssignmentActualCost | ASSN_ACT_COST | The actual costs associated with resource work or fixed costs for tasks |
Assignment (Timephased) | AssignmentTimeActualCost | |||
Resource | ResourceActualCost | RES_ACT_COST | ||
Resource (Timephased) | ResourceTimeActualCost | |||
Task | TaskActualCost | TASK_ACT_COST | ||
Task (Timephased) | TaskTimeActualCost | |||
Actual Fixed Cost | Task | TaskTimeActualFixedCost | The actual fixed cost expenses charged over time. | |
Actual Overtime Cost | Assignment | AssignmentActualOvertimeCos | ASSN_ACT_OVT_COST | The actual overtime costs |
Resource | ResourceActualOvertimeCost | RES_ACT_OVT_COST | ||
Task | TaskActualOvertimeCost | TASK_ACT_OVT_COST | ||
ACWP | Assignment | AssignmentACWP | ASSN_ACWP | The earned value actual cost of workperformed (ACWP). |
Assignment (Timephased) | AssignmentTimeACWP | |||
Resource | ResourceACWP | RES_ACWP | ||
Resource (Timephased) | ResourceTimeACWP | |||
Task | TaskACWP | TASK_ACWP | ||
Task (Timephased) | TaskTimeACWP | |||
BAC | Assignment | AssignmentBaselineCost | ASSN_BASE_COST | The earned value Budget At Completion (BAC). Same as the Baseline Cost field. |
Assignment (Timephased) | AssignmentTimeBaselineCost | |||
Resource | ResourceBaselineCost | RES_BASE_COST | ||
Resource(Timephased) | ResourceTimeBaselineCost | |||
Task | TaskBaselineCost | TASK_BASE_COST | ||
Task (Timephased) | TaskTimeBaselineCost | |||
aselineCost | Assignment | AssignmentBaselineCost | ASSN_BASE_COST | The total planned cost for work performed, plus fixed costs. |
Assignment (Timephased) | AssignmentTime-BaselineCost | |||
Resource | ResourceBaselineCost | RES_BASE_COST | ||
Resource | ResourceTimeBaselineCost | |||
Task | TaskBaselineCost | TASK_BASE_COST | ||
Task | TaskTimeBaselineCost | |||
Baseline1-10Cost | Assignment | AssignmentBaseline1Cost10 | The baseline costs for Baseline1through Baseline 10. | |
Assignment (Timephased) | AssignmentTimeBaseline1-Cost-10 | |||
Resource | ResourceBaseline1Cost10 | |||
Resource | ResourceTimeBaseline1Cost-10 | |||
Task | TaskBaseline1Cost-10 | |||
Task | TaskTimeBaseline1- | |||
BCWP | Assignment | AssignmentBCWP | ASSN_BCWP | The earned |
Assignment (Timephased) | AssignmentTimeBCWP | |||
Resource | ResourceBCWP | RES_BCWP | ||
Resource | ResourceTimeBCWP | |||
Task | TaskBCWP | TASK_BCWP | ||
Task | TaskTimeBCWP | |||
BCWS | Assignment | AssignmentBCWS | ASSN_BCWS | The earned |
Assignment (Timephased) | AssignmentTimeBCWS | |||
Resource | ResourceBCWS | RES_BCWS | ||
Resource | ResourceTimeBCWS | |||
Task | TaskBCWS | TASK_BCWS | ||
Task | TaskTimeBCWS | |||
Cost | Assignment | AssignmentCost | ASSN_COST | The total |
Assignment (Timephased) | AssignmentTimeCost | |||
Resource | ResourceCost | RES_COST | ||
Resource | ResourceTimeCost | |||
Task | TaskCost | TASK_COST | ||
Task | TaskTimeCost | |||
Cost Per Use | Resource | ResourceCostPerUse | RES_COST_PER_USE | The cost for each unit of work |
Cost | Assignment | AssignmentCostVariance | The difference between the baseline cost and total scheduled cost. | |
Resource | ResourceCostVariance | |||
Task | TaskCostVariance | |||
Cost1-10 | Assignment | AssignmentCost1-10 | The values for | |
Resource | ResourceCost1-10 | |||
Task | TaskCost1-10 | |||
Cumulative Cost | Assignment (Timephased) | AssignmentTimeCumulativeCost | The cumulative cost for all work | |
Resource | ResourceTimeCumulativeCost | |||
Task | TaskTimeCumulativeCost | |||
CV | Assignment | AssignmentCV | The earned value Cost Variance (CV), | |
Assignment (Timephased) | AssignmentTimeCV | |||
Resource | ResourceCV | |||
Resource | ResourceTimeCV | |||
Task | TaskCV | |||
Task | TaskTimeCV | |||
EAC | Task | TaskEAC | TASK_EAC | The earned value estimate at completion (EAC), which is the expected total cost of a task. |
Fixed Cost | Task | TaskFixedCost | TASK_FIXED_COST | The expense for |
Task | TaskTimeFixedCost | |||
Overtime Cost | Assignment | AssignmentOvertimeCost | ASSN_OVT_COST | The total scheduled overtime cost for |
Resource | ResourceOvertimeCost | RES_OVT_COST | ||
Task | TaskOvertimeCost | TASK_OVT_COST | ||
Overtime Rate | Resource | ResourceOvertimeCost | RES_OVT_COST | The total overtime cost for a resource on all assigned tasks. |
Remaining Cost | Assignment | AssignmentRemainingCost | ASSN_REM_COST | The costs associated with |
Resource | ResourceRemainingCost | RES_REM_COST | ||
Task | TaskRemainingCost | TASK_REM_COST | ||
Remaining Overtime Cost | Resource | ResourceRemainingOvertimeCost | RES_REM_OVT_COST | The remaining overtime costs for a resource. |
Standard Rate | Resource | ResourceStandardRate | RES_STD_RATE | The standard rate for nonovertime work performed by a resource. |
SV | Assignment | AssignmentSV | The earned value schedule variance (SV), which is | |
Assignment (Timephased) | AssignmentTimeSV | |||
Resource | ResourceSV | |||
Resource | ResourceTimeSV | |||
Task | TaskSV | |||
Task | TaskTimeSV | |||
VAC | Assignment | AssignmentVAC | The earned value variance at completion (VAC), which is the difference between BAC and EAC, measured in cost terms. | |
Resource | ResourceVAC | |||
Task | TaskVAC | TASK_VAC |
Table B-2 lists all date fields available in Microsoft Project.
Cross-References | For information about working with the project schedule and associated date fields, see Chapter 9, "Checking and Adjusting the Project Plan," and "Monitoring and Adjusting the Schedule" . |
Field | Available | OLE DB | Microsoft | Description |
---|---|---|---|---|
Actual | Assignment | AssignmentActualFinish | ASSN_ACT_FINISH | The actual date |
Finish | Resource | ResourceActualFinish | RES_ACT_FINISH | |
Task | TaskActualFinish | TASK_ACT_FINISH | ||
Actual Start | Assignment | AssignmentActualStart | ASSN_ACT_START | The actual date |
Resource | ResourceActualStart | RES_ACT_START | ||
Task | TaskActualStart | TASK_ACT_START | ||
Available From | Resource | ResourceAvailableFrom | RES_AVAIL_FROM | The start date that a resource is available to start work on a project. |
Available To | Resource | ResourceAvailableTo | RES_AVAIL_TO | The end date that a resource is no longer available to work on a project. |
Baseline | Assignment | AssignmentBaselineFinish | ASSN_BASE_FINISH | The originally planned completion date for assignments or tasks. |
Resource | ResourceBaselineFinish | RES_BASE_FINISH | ||
Task | TaskBaselineFinish | TASK_BASE_FINISH | ||
Baseline Start | Assignment | AssignmentBaselineStart | ASSN_BASE_START | The planned beginning date for an assignment or task. |
Resource | ResourceBaselineStart | RES_BASE_START | ||
Task | TaskBaselineStart | TASK_BASE_START | ||
Baseline | Assignment | AssignmentBaseline1Finish-10 | The baseline | |
Resource | ResourceBaseline1- | |||
Task | TaskBaseline1Finish-10 | |||
Baseline | Assignment | AssignmentBaseline1Start-10 | The baseline start values for Baseline1Start through Baseline10Start. | |
Resource | ResourceBaseline1- | |||
Task | TaskBaseline1Start-10 | |||
Complete Through | Task | TaskCompleteThrough | The most recent date that actuals have been reported on a task. | |
Constraint Date | Task | TaskConstraintDate | TASK_CONSTRAINT_DATE | The date associated with a task constraint. |
Created | Task | TaskCreated | TASK_CREATION_ | The date and time that a task was first added to this project. |
Date1-10 | Assignment | AssignmentDate1-10 | The values for the custom Date1 through Date10 fields. | |
Resource | ResourceDate1-10 | |||
Task | TaskDate1-10 | |||
Deadline | Task | TaskDeadline | TASK_DEADLINE | The date by which a task must be completed. |
Early Finish | Task | TaskEarlyFinish | TASK_EARLY_FINISH | The earliest date that a task can finish, based on predecessor and successor tasks, constraints, and delays. |
Early Start | Task | TaskEarlyStart | TASK_EARLY_START | The earliest date when a task can start, based on predecessor and successor tasks, constraints, and delays. |
Expected Finish | Task | TaskFinish2 | The expected finish date of a task for PERT Analysis calculations. | |
Expected Start | Task | TaskStart2 | The expected start date of a task for PERT Analysis calculations. | |
Finish | Assignment | AssignmentFinish | ASSN_FINISH | The date that a task is scheduled to be completed. |
Resource | ResourceFinish | RES_FINISH | ||
Task | TaskFinish | TASK_FINISH | ||
Finish1-10 | Assignment | AssignmentBaseline1- | The values for the custom Finish1 through Finish10 fields. | |
Resource | ResourceBaseline1- | |||
Task | TaskBaseline1Finish-10 | |||
Late Finish | Task | TaskLateFinish | TASK_LATE_FINISH | The latest date that a task can finish, based on predecessor and successor tasks, constraints, and delays. |
Late Start | Task | TaskLateStart | TASK_LATE_START | The latest date when a task can start, based on predecessor and successor tasks, constraints, and delays. |
Optimistic Finish | Task | TaskFinish1 | The optimistic finish date of a task for PERT Analysis calculations. | |
Optimistic Start | Task | TaskStart1 | The optimistic start date of a task for PERT Analysis calculations. | |
Pessimistic Finish | Task | TaskFinish3 | The pessimistic finish date of a task for PERT Analysis calculations. | |
Pessimistic Start | Task | TaskStart3 | The pessimistic start date of a task for PERT Analysis calculations. | |
Preleveled Finish | Task | TaskPreleveledFinish | TASK_PRELEVELED_FINISH | The finish date for a task before resource leveling. |
Preleveled Start | Task | TaskPreleveledStart | TASK_PRELEVELED_START | The start date for a task before resource leveling. |
Resume | Task | TaskResume | TASK_RESUME_ | The date when the remaining portion of a split task is scheduled to resume. |
Start | Assignment | AssignmentStart | ASSN_START | The date when a task or assignment is scheduled to begin. |
Resource | ResourceStart | RES_START | ||
Task | TaskStart | TASK_START | ||
Start1-10 | Assignment | AssignmentStart1-10 | The values for the custom Start1 through Start10 fields. | |
Resource | ResourceStart1-10 | |||
Task | TaskStart1-10 | |||
Stop | Task | TaskStop | TASK_STOP | The date when a split task is to temporarily stop. This is associated with a subsequent Resume date field. |
Summary Progress | Task | TaskSummaryProgress | The progress made on a summary task. |
Table B-3 lists all duration fields available in Microsoft Project.
Cross-References | For more information about durations, see "Setting Task Durations". |
Field | Available Categories | OLE DB Provider | Microsoft Project Database | Description |
---|---|---|---|---|
Actual Duration | Task | TaskActualDuration | TASK_ACT_DUR | The amount of time that actual work has been performed on a task, up to the current date. |
Actual Overtime Work | Assignment | Assignment- | ASSN_OVT_WORK | The amount of overtime work already completed by a resource on a task. |
Assignment (Timephased) | AssignmentTime- | |||
Resource | ResourceOvertimeWork | RES_OVT_WORK | ||
Resource (Timephased) | ResourceTime- | |||
Task | TaskOvertimeWork | TASK_OVT_WORK | ||
Task | TaskTimeOvertimeWork | |||
Actual Work | Assignment | Assignment- | ASSN_ACT_WORK | The amount of work already completed by a resource on a task. |
Assignment (Timephased) | AssignmentTime- | |||
Resource | ResourceActualWork | RES_ACT_WORK | ||
Resource (Timephased) | ResourceTime- | |||
Task | TaskActualWork | TASK_ACT_WORK | ||
Task | TaskTimeActualWork | |||
New Actual Overtime Work Protected | Assignment | Assignment- | ASSN_ACT_OVT_ | |
Assignment (Timephased) | AssignmentTimeActualOvertimeWorkProtected | The amount of actual overtime work reported by a resource and retained on Project Server, regardless of whether the project manager changes the amount in the project plan. | ||
Resource | ResourceActualOvertimeWorkProtected | RES_ACT_ OVT_ | ||
New Actual Work Protected | Assignment | AssignmentActualWorkProtected | ASSN_ACT_WORK_ | The amount of actual work reported by a resource and retained on Project Server, regardless of whether the project manager changes the amount in the project plan. |
Assignment (Timephased) | AssignmentTimeActualWorkProtected | |||
Resource | ResourceActualWorkProtected | RES_ACT_WORK_ | ||
Task | TaskActualWorkProtected | TASK_ACT_WORK_ | ||
Assignment Delay | Assignment | AssignmentDelay | ASSN_DELAY | The amount of time between when a resource is assigned work and when a resource begins work |
Baseline Duration | Task | TaskBaselineDuration | TASK_BASE_DUR | The amount of time originally planned to complete a task. |
Baseline Work | Assignment | AssignmentBaselineWork | ASSN_BASE_WORK | The number of work resource hours originally planned for a task |
Assignment (Timephased) | AssignmentTime-BaselineWork | |||
Resource | ResourceBaselineWork | RES_BASE_WORK | ||
Resource (Timephased) | ResourceTime- | |||
Task | TaskBaselineWork | TASK_BASE_WORK | ||
Task | TaskTimeBaselineWork | |||
Baseline1-10 Duration | Task | TaskBaseline1- | The baseline duration values for Baseline1through Baseline 10. | |
Baseline1-10 Work | Assignment | AssignmentBaseline1-Work-10 | The baseline work values | |
Assignment (Timephased) | AssignmentTime- Baseline1Work-10 | |||
Resource | ResourceBaseline1-Work-10 | |||
Resource (Timephased) | ResourceTime- | |||
Task | TaskBaseline1- | |||
Task | TaskTimeBaseline1-Work-10 | |||
Cumulative Work | Assignment (Timephased) | AssignmentTimeCumulativeWork | The amount of work over a period of time. | |
Resource (Timephased) | ResourceTimeCumulativeWork | |||
Task | TaskTimeCumulativeWork | |||
Duration | Task | TaskDuration | TASK_DUR | The amount of working time between a task's start and finish dates. |
Duration Variance | Task | TaskDurationVariance | TASK_DUR_VAR | The difference between a task's baseline duration and total scheduled duration. |
Dura- | Assignment | AssignmentDuration1-10 | The values for the Custom Duration1 through Duration10 fields. | |
Resource | Resource- | |||
Task | TaskDuration1-10 | |||
Finish Slack | Task | TaskFinishSlack | The difference between a task's early start and late finish dates. | |
Finish | Assignment | AssignmentFinishVariance | ASSN_FINISH_VAR | The difference between the baseline start date of a task or assignment and its current finish date. |
Task | TaskFinishVariance | TASK_FINISH_VAR | ||
Free Slack | Task | TaskFreeSlack | TASK_FREE_SLACK | The amount of time that a task can be delayed before it will delay a successor task. |
Leveling Delay | Assignment | Assignment- | ASSN_LEVELING_ | The amount of delay caused by resource |
Resource | ||||
Task | TaskLevelingDelay | TASK_LEVELING_ | ||
Negative Slack | Task | The amount of time that a task is behind schedule. This time must be recovered to prevent delays for successor tasks. | ||
Optimistic Duration | Task | TaskDuration1 | The optimistic task duration for PERT Analysis calculations. | |
Over- | Assignment (Timephased) | The amount of work that exceeds the amount of time a resource is available. | ||
Resource (Timephased) | ResourceTime- | |||
Task | ||||
Overtime Work | Assignment | Assignment- | ASSN_OVT_WORK | The amount of work assigned to a resource that is charged at a resource's overtime rate. |
Assignment (Timephased) | AssignmentTime- | |||
Resource | Resource- | RES_OVT_WORK | ||
Resource (Timephased) | ResourceTime- | |||
Task | TaskOvertimeWork | TASK_OVT_WORK | ||
Task | TaskTime- | |||
Pessimistic Duration | Task | TaskDuration3 | The pessimistic task duration for PERT Analysis calculation. | |
Regular Work | Assignment | Assignment- | ASSN_REG_WORK | The amount of work assigned to a resource that is charged at a resource's standard rate. |
Assignment (Timephased) | AssignmentTime- | |||
Resource | ResourceRegularWork | RES_REG_WORK | ||
Resource (Timephased) | ResourceTime- | |||
Task | TaskRegularWork | TASK_REG_WORK | ||
Task | TaskTimeRegularWork | |||
Remaining Availability | Resource (Timephased) | ResourceTime-Remaining- | The amount of available resource time not currently allocated to any task in a given time period. | |
Remaining Duration | Task | TaskRemaining- | TASK_REM_DUR | The amount of time required to complete a task. |
Remaining Overtime Work | Assignment | AssignmentRemaining-OvertimeWork | ASSN_REM_OVT_ | The amount of scheduled |
Resource | ResourceRemaining-OvertimeWork | RES_REM_OVT_ | ||
Task | TaskRemaining- | TASK_REM_OVT_ | ||
Remaining Work | Assignment | Assignment- | ASSN_REM_WORK | The amount of work remaining on a task. |
Resource | ResourceRemainingWork | RES_REM_WORK | ||
Task | TaskRemainingWork | TASK_REM_WORK | ||
Start Slack | Task | TaskStartSlack | The amount of time that a task can be delayed without affecting a successor task's start date or a project's finish date. Calculated by measuring the difference between a task's early start and late start dates. | |
Start | Assignment Task | AssignmentStart- | ASSN_START_VAR | The difference between the baseline start date and the current scheduled start date. |
TaskStartVariance | TASK_START_VAR | |||
Total Slack | Task | TaskTotalSlack | TASK_TOTAL_SLACK | The amount of time that a task can be delayed without affecting the project's finish date. |
Work | Assignment | AssignmentWork | ASSN_WORK | The total scheduled amount of work assigned to a resource. |
Assignment (Timephased) | AssignmentTimeWork | |||
Resource | Resource | RES_WORK | ||
Resource (Timephased) | ResourceTimeWork | |||
Task | TaskWork | TASK_WORK | ||
Task | TaskTimeWork | |||
Work | Resource (Timephased) | ResourceTimeWorkAvailability | The maximum amount of time that a resource is available to be assigned work during a specified time period. | |
Work | Assignment | AssignmentWork- | The difference between baseline work and scheduled work. | |
Resource | ResourceWork- | |||
Task | TaskWorkVariance |
Table B-4 lists all fields that store enumerated values in Microsoft Project.
Field | Available Categories | OLE DB | Microsoft | Description |
---|---|---|---|---|
Accrue At | Resource | ResourceAccrueAt | RES_ACCRUE_AT | The way in which resource costs are accrued: at the start, at the end, or prorated across the span of the project. |
Base | Resource | ResourceBase- | RES_CAL_UID | The base calendar to be used with a particular resource. The collaboration method used to communicate with resources on a project team |
Resource | ResourceWorkgroup | RES_WORKGROUP_MESSAGING | ||
New Booking Type | Assignment | Assignment- | ASSN_BOOKING_ | The booking type for a resource, either Committed or Proposed. |
Resource | Resource- | RES_BOOKING_ | ||
Constraint Type | Task | TaskConstraintType | TASK_CONSTRAINT_TYPE | The type of constraint applied to a task. |
Cost Rate Table | Assignment | Assignment- | ASSN_COST_RATE_TABLE | The cost rate table used for a particular assignment. |
Earned Value Method | Task | TASK_EVMETHOD | The method (Percent Complete or Physical Percent Complete) used to calculate earned value budgeted cost of work performed (BCWP). | |
Fixed Cost Accrual | Task | TaskFixedCostAccrual | TASK_FIXED_COST_ACCRUAL | The way in which fixed costs are accrued: at the start, at the end, or prorated across the task duration. |
Priority | Task | TaskPriority | TASK_PRIORITY | The relative importance of the task scheduling; used to determine priority for task leveling. |
Resource Type | Assignment | Assignment-ResourceType | ASSN_RES_TYPE | The type of resource (work or material) assigned. |
Status | Task | TaskStatus | The current status of a task: Complete, On Schedule, Late, or Future Task. | |
Task | Task | TaskCalendar | TASK_CAL_UID | The base calendar to be used with a particular task. |
(Resource) Type | Resource | ResourceType | RES_TYPE | The type of resource: either work or material. |
(Task) | Task | TaskType | TASK_TYPE | The type of task: fixed work, fixed units, or fixed duration. |
Work | Assignment | Assignment- | ASSN_WORK_ | The way in which work is distributed over the length of an assignment. |
Table B-5 contains information about indicator fields, which are used to provide additional information about assignments, tasks, and resources, using a simple visual icon.
Field | Available | OLE DB | Microsoft | Description |
---|---|---|---|---|
Indicators | Assignment | Various | Various | Indicators that provide additional information about assignments, tasks, and resources |
Resource | Various | Various | ||
Task | Various | Various | ||
StatusTask | Indicators that provide information about whether a task is complete, on schedule, late, or planned. |
Table B-6 lists all integer fields available in Microsoft Project.
Field | Available | OLE DB | Microsoft | Description |
---|---|---|---|---|
ID | Resource | ResourceID | RES_ID | The position of a task or resource in relation to other tasks or resources. |
Task | TaskID | TASK_ID | ||
Outline Level | Task Level | TaskOutlineLevel | The task's location within the project outline. | |
Predecessors | Task | Task- | The Task ID for a predecessor task. | |
Resource ID | Assignment | The position of the resource within the project, in relation to other resources. | ||
Successors | Task | Task- | The Task ID of a successor task. | |
Task ID | Assignment | The position of the task within the project, in relation to other tasks. | ||
Unique ID | Assignment | Assignment-UniqueID | ASSN_UID | The unique ID of an assignment, resource, or task. |
Resource | Resource-UniqueID | RES_UID | ||
Task | TaskUniqueID | TASK_UID | ||
Unique ID | Task | TaskUniqueID- | The unique ID of a predecessor task. | |
Unique ID | Task | TaskUniqueID-Successors | The unique ID of a successor task. | |
WBS | Task | TaskWBS- | The work breakdown structure code of the predecessor tasks. | |
WBS | Task | TaskWBS- | The work breakdown structure code of the successor tasks. |
Table B-7 lists all outline code fields available in Microsoft Project.
Field | Available | OLE DB | Microsoft Project | Description |
---|---|---|---|---|
Outline | Resource | ResourceOutline-Code1-10 | The values for the custom OutlineCode1 through OutlineCode10 fields. | |
Code 1-10 | Task | TaskOutline- |
Table B-8 lists all percentage and number fields available in Microsoft Project.
Field | Available | OLE DB | Microsoft | Description |
---|---|---|---|---|
Assignment Units | Assignment | AssignmentUnits | ASSN_UNITS | The number of resource units assigned to a task, expressed as a percentage of a resource's total availability. |
CPI | Task | TaskCPI | The earned value cost performance index, which is the ratio of the difference between BCWP and ACWP. | |
Task | ||||
Cumulative Percent | Task | The progress of a task measured as a percentage of the total work required to finish the task, as distributed over time. | ||
CV Percent | Task Task | TaskCVP | The earned value Cost Variance percent (CV%), which is the ratio of CV to BCWP … … …, expressed as a percentage. | |
Max Units | Resource | ResourceMaxUnits | RES_MAX_ | The maximum number of units a resource is available to be assigned to tasks in the project. |
Number1-20 | Assignment | Assignment-Number1-20 | The values for the custom Number1 through Number20 fields. | |
Resource | Resource- | |||
Task | TaskNumber1-20 | |||
Objects | Resource | ResourceObjects | RES_NUM_ | The number of objects, such as an inserted graphic or a linked file, associated with either a task or resource. |
Task | TaskObjects | TASK_NUM_ | ||
Peak | Assignment | AssignmentPeakUnits | The number of units that represents a resource's largest assignment (in units) or the number of units required to complete an assignment | |
Resource | ResourcePeakUnits | RES_PEAK | ||
Peak Units | Assignment (Timephased) | AssignmentTimePeakUnits | The number of units that represents a resource's largest assignment (in units) or the number of units required to complete an assignment, shown for a specific time period. | |
Resource (Timephased) | ResourceTimePeakUnits | |||
Percent | Assignment (Timephased) | AssignmentTimePercentAllocation | The percentage of a resource's total available units compared with assigned units. | |
Resource (Timephased) | ResourceTimePercentAllocation | |||
Percent Complete | Task | TaskPercentComplete | TASK_PCT_ | The ratio of a task's total duration to completed duration. |
Task | ||||
Percent Work | Assignment Resource Task | TaskPercentWork- | TASK_PCT_ | The ratio of a task's total work to completed work. |
Physical | Task | TASK_PHY_ | A percent complete value that can be used as an alternative to regular percent complete for the purposes of calculating BCWP and other earned value fields. | |
SPI | Task | TaskSPI | The earned value schedule performance index (SPI), which is the ratio of BCWP to BCWS. | |
Task | ||||
SV Percent | Task | TaskSVP | The earned value schedule variance (SV%), which is the ratio of SV to BCWS. | |
Task | ||||
Task Outline Number | Assignment | TaskOutlineNumber | TASK_ | Indicates a task's position in the outline. |
TCPI | Task | TaskTCPI | The earned value To Complete Performance Index (TCPI), which is the ratio of remaining work to remaining funds. | |
Unit | Resource (Timephased) | ResourceTimeUnit-Availability | The number of units a resource is available to be assigned work, expressed as a percentage of a resource's total units. |
Table B-9 lists all text fields available in Microsoft Project.
Field | Available | OLE DB | Microsoft | Description |
---|---|---|---|---|
Code | Resource | ResourceCode | The information about a resource entered as a code, abbreviation, or number. | |
Contact | Task | TaskContact | The name of the person responsible for a task. | |
E-mail Address | Resource | ResourceEmailAddress | The e-mail address for a resource. | |
Group | Resource | ResourceGroup | The name of the group that a resource is part of. | |
Hyperlink | Assignment | Assignment- | The title of a hyperlink associated with an assignment, resource, or task. | |
Resource | Resource- | |||
Task | TaskHyperlink | |||
Hyperlink Address | Assignment | Assignment- | The hyperlink address of a hyperlink associated with an assignment, resource, or task. | |
Resource | ResourceHyperlinkAddress | |||
Task | TaskHyperlinkAddress | |||
Hyperlink | Assignment | AssignmentHyperlinkHref | The combination of the Hyperlink Address and the Hyperlink Sub-Address fields. | |
Resource | ResourceHyperlinkHref | |||
Task | TaskHyperlinkHref | |||
Hyperlink SubAddress | Assignment | Assignment-HyperlinkSubAddress | The location within a document associated with the Hyperlink Address field. | |
Resource | ResourceHyperlinkSubAddress | |||
Task | TaskHyperlinkSubAddress | |||
Initials | Resource | ResourceInitials | RES_INITIALS | The abbreviation of a resource's name. |
Material Label | Resource | Resource- | RES_MATERIAL_ | The name of the unit of measurement associated with a material resource. |
Name | Resource | ResourceName | RES_NAME | The name of a resource or task. |
Task | TaskName | TASK_NAME | ||
Notes | Assignment | AssignmentNotes | ASSN_RTF_NOTES | The notes about an assignment, resource, or task. |
Resource | ResourceNotes | RES_RTF_NOTES | ||
Task | TaskNotes | TASK_RTF_NOTES | ||
Outline | Task | TaskOutline- | TASK_OUTLINE_ | The number that identifies a task's position in a project's outline; this number is entered automatically by Microsoft Project. |
Phonetics | Resource | Resource- | RES_PHONETICS | The phonetic information about a resource name; used only in the Japanese version of Microsoft Project. |
Project | Assignment | Projects | The PROJ_NAME field in the MSP_PROJECTS table contains the name of a project. Match the | The name of the project. |
Resource | Projects | |||
Task | Projects | |||
Resource Group | Assignment | ResourceGroup | The name of a group to which a resource belongs. | |
Task | ResourceGroup | |||
Resource | Assignment | ResourceInitials in the Resources table | RES_INITIALS in the MSP_RESOURCES table | The initials of a resource assigned to a task. |
Task | ResourceInitials table | RES_INITIALS in the MSP_RESOURCES table | ||
Resource Names | Assignment | ResourceName in the Resources table | RES_NAME in the MSP_RESOURCES table | The name of a resource assigned to a task. |
Task | ResourceName in the Resources table | RES_NAME in the MSP_RESOURCES table | ||
Subproject File | Task | TaskSubprojectFile | The name of an inserted project, including the path to the project. | |
Task Name | Assignment | TaskName | TASK_NAME | The name of a task. |
Task | Assignment | AssignmentTaskSummary-Name | The name of a summary task. | |
Text1-30 | Assignment | Assignment- | MSP_TEXT_FIELDS | The values for the |
Resource | ResourceText1-30 | MSP_TEXT_FIELDS | ||
Task | TaskText1-30 | MSP_TEXT_FIELDS | ||
WBS | Assignment Task | TaskWBS | TASK_WBS | The work breakdown structure codes used to represent a task's position within the project. |
Windows User Account | Resource | ResourceNT-Account | The Microsoft Windows user name for a work resource. |
Table B-10 lists all Yes/No fields available in Microsoft Project. Yes/No fields, which are set either by the user or by Microsoft Project, indicate the state of a task, resource, or assignment as being on or off or being true or false. Yes/No fields are also referred to as Boolean fields.
Field | Available | OLE DB | Microsoft | Description |
---|---|---|---|---|
Assignment | Assignment | Indicates whether this is an assignment. | ||
Resource | ||||
Task | ||||
Can Level | Resource | ResourceCanLevel | RES_CAN_LEVEL | The setting that specifies whether leveling can be performed on the resource. |
Confirmed | Assignment | AssignmentConfirmed | ASSN_IS_ | The setting that specifies whether a resource has accepted an assignment using an electronic team collaboration method. |
Resource | ResourceConfirmed | |||
Task | TaskConfirmed | |||
Critical | Task | TaskCritical | TASK_IS_CRITICAL | The setting that specifies whether the task is on the critical path. |
Effort Driven | Task | TaskEffortDriven | TASK_IS_EFFORT_DRIVEN | The setting that specifies whether the task is effort-driven. |
Estimated | Task | TaskEstimated | TASK_DUR_IS_ | The setting that specifies whether a task's duration is estimated. |
External Task | Task | TaskExternalTask | TASK_IS_ | The setting that specifies whether the task is an external task. |
Flag1-20 | Assignment | Assignment- | The setting that specifies whether the custom fields Flag1 through Flag20 are on or off. | |
Resource | ResourceFlag1-20 | |||
Task | TaskFlag1-20 | |||
Group By | Resource Task | TaskSummary | TASK_IS_ | The setting that specifies whether a task is a summary task. |
Hide Bar | Task | TaskHideBar | TASK_BAR_IS_ | The setting that specifies whether Gantt and Calendar bars are hidden for a task. |
Ignore Resource | Task | TaskIgnore-ResourceCalendar | TASK_IGNORES_ | The setting that specifies whether a resource's calendar is taken into account in conjunction with a task calendar. |
Inactive | Resource | The setting that specifies whether an enterprise resource has been made inactive. | ||
Level Assignments | Task | TaskLevelAssignments | TASK_LEVELING_ | The setting that specifies whether assignments can be split or delayed to resolve resource overallocations. |
Leveling Can Split | Task | TaskLevelingCanSplit | TASK_LEVELING_ | The setting that specifies whether resource leveling can cause a task split on the remaining work on a task. |
Linked Fields | Assignment | AssignmentLinkedFields | ASSN_HAS_ | The setting that specifies whether an assignment, resource, or task has OLE links to it from within the project, another project, or an external application. |
Resource | ResourceLinkedFields | RES_HAS_ | ||
Task | TaskLinkedFields | TASK_HAS_ | ||
Marked | Task | TaskMarked | TASK_MARKED | The setting that specifies whether a task is identified, or flagged , as requiring further attention. |
Milestone | Task | TaskMilestone | TASK_MILESTONE | The setting that specifies whether a task is a milestone. |
Overallocated | Assignment | AssignmentOverallocated | ASSN_IS_ | The setting that specifies whether resources have been assigned work beyond their work capacity or availability. |
Resource | ResourceOverallocated | RES_IS_ | ||
Task | TaskOverallocated | TASK_IS_ | ||
Recurring | Task | TaskRecurring | TASK_IS_ | The setting that specifies whether a task is recurring. |
Response Pending | Assignment | Assignment-ResponsePending | ASSN_RESPONSE_PENDING | The setting that specifies whether a response to an update has been received through an electronic team collaboration method. |
Resource | Resource- | |||
Task | TaskResponse-Pending | |||
Rollup | Task | TaskRollup | TASK_IS_ | The setting that specifies whether information on the subtask Gantt bar is rolled up to the summary task bar. |
Subproject Read Only | Task | TaskSubprojectReadOnly | The setting that specifies whether a subproject of a task is read-only. | |
Summary | Task | TaskSummary | TASK_IS_ | The setting that specifies whether the task is a |
TeamStatus Pending | Assignment | AssignmentTeamStatusPending | ASSN_TEAM_ | The setting that specifies whether a response to a progress request has been received through an electronic team collaboration method. |
Resource | ResourceTeamStatusPending | |||
Task | TaskTeamStatusPending | |||
Text Above | Task | The setting that specifies whether text appears above or below the summary Gantt bar. | ||
Update Needed | Assignment | AssignmentUpdateNeeded | ASSN_UPDATE_ | The setting that specifies whether an update message should be sent to resources to notify them of updates to their assigned tasks through an electronic team collaboration method. |
Resource | ResourceUpdateNeeded | |||
Task | TaskUpdateNeeded |