Working with Predecessor Data

     

To set predecessor options, open the Task Information dialog box and select the Predecessor tab. This task shows you how to create a task predecessor.

Creating a Task Predecessor

graphics/one_icon.jpg Double-click the task you want to edit.

graphics/two_icon.jpg Select the Predecessors tab on the Task Information dialog.

graphics/three_icon.jpg To create a new link, select the next blank row in the grid and select the task that should be linked from the drop-down list.

graphics/four_icon.jpg Select the Type value here for your link.

graphics/five_icon.jpg Enter a Lag value, if one is necessary.

graphics/six_icon.jpg Click OK to close the dialog and save your changes.

graphics/04inf07.jpg

For Your Information

Make Sure to Save Your Changes

You must click the OK button on this dialog for the edits you have made to take effect. It is important to remember that if you edit a field on one tab, but then move to another tab, make more edits, and then click Cancel, that ALL the edits you have made in the entire dialog will be lost, not just the ones on the last tab you were on.




Show Me. Microsoft Office Project 2003
Show Me Microsoft Office Project 2003
ISBN: 0789730693
EAN: 2147483647
Year: 2003
Pages: 204

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net