The project plan is a suite of documents that the producer uses to estimate costs, track progress, maintain the schedule, and estimate profitability.
Manpower plan. This is a spreadsheet that lists when all the internal people connected to the project come on board, and when they finish up. Here is a drastically simplified version:
Resource plan. This spreadsheet lists all the external costs of the project and when they will be incurred. The external costs appropriate to the preceding manpower plan might look something like this:
‚ | January | February | March | April | May | June | Total |
---|---|---|---|---|---|---|---|
3 DevKits | 10000 | 10000 | 10000 | ‚ | ‚ | ‚ | 30000 |
2 Debug Kits | ‚ | ‚ | 1000 | 1000 | ‚ | ‚ | 2000 |
Art Tool #1 (2) | ‚ | 5000 | 5000 | ‚ | ‚ | ‚ | 10000 |
Art Tool #2 (4) | ‚ | 1000 | 1000 | ‚ | ‚ | ‚ | 2000 |
Bug Tracking Tool | ‚ | ‚ | 5000 | 150 | ‚ | ‚ | 5150 |
‚ | ‚ | ‚ | ‚ | ‚ | ‚ | ‚ |
|
Composer | ‚ | ‚ | ‚ | ‚ | 5000 | ‚ | 5000 |
Voice | ‚ | ‚ | ‚ | 5000 | 5000 | ‚ | 10000 |
‚ | ‚ | ‚ | ‚ | ‚ | ‚ | ‚ | ‚ |
Total Ext Costs | 10000 | 16000 | 22000 | 6150 | 10000 |
| 54150 |
Project tracking doc. This is usually a Gantt chart generated by the producer using project management software. Each department head supplies a list of tasks, along with the people assigned to them and how long they think the tasks will take. With this information, the producer can see if the project is on schedule, what the critical path to completion is, which resources are overloaded, etc.
Budget. This is a spreadsheet of all the costs associated with the project. Line items will include the following.
Internal personnel costs (salaries of people applied to the project)
Hardware costs
Software licenses
External contractor fees
Engine royalties
IP acquisition costs (license fee)
Marketing & PR costs
An overhead multiplier that applies fixed costs (building rent, utilities, travel, personnel benefits, etc.) to the project
Profit-and-Loss (P&L) statement. This is another spreadsheet that the publisher uses to estimate the profitability of each project. The projected lifecycle sales estimates from the sales team are compared to the costs from the preceding budget to determine if the game will make enough money to justify the investment.
Development schedule. This table breaks out the stages of development, with significant events along the way:
Event | Date |
---|---|
Concept phase | 00/00/00 - 00/00/00 |
Start preproduction | 00/00/00 |
Start development | 00/00/00 |
Milestone #1 | 00/00/00 |
Milestone #2 | 00/00/00 |
‚ (Additional milestones) ‚ | 00/00/00 |
Alpha | 00/00/00 |
Beta | 00/00/00 |
Localization deliverable #1 | 00/00/00 |
Pre-submission (console only) | 00/00/00 |
First submission (console only) | 00/00/00 |
Second submission (console only) | 00/00/00 |
Code freeze | 00/00/00 |
Release to manufacture (RTM) | 00/00/00 |
Shelf date | 00/00/00 |
Milestone definitions. Here, the deliverable for each milestone is specified in detail, along with the date it's due.
Milestone | Date |
---|---|
Milestone #1. General description
| ‚ |
‚ | 00/00/00 |
Milestone #2. General description
| ‚ |
‚ | 00/00/00 |
Milestone #3. General description
| ‚ |
‚ | 00/00/00 |
Etc. | Etc. |