Entering Task Names

 < Day Day Up > 

Entering Task Names

You can create task names by typing into the Task Name field of the Gantt Chart view or by pasting names that you have copied from elsewhere. The most common method is undoubtedly the old-fashioned methodtypingbut both methods are described in the following sections.

Typing Task Names

When you type text into the Task Name field on a blank row, you create a new task. You can use any combination of keyboard characters and spaces, and the name can contain up to 255 characters . You complete the cell entry by pressing Enter, by clicking the green check mark in the Entry bar, or by selecting another cell. You can cancel the cell entry before entering it by pressing the Esc key or by clicking the red X in the Entry bar. In that case, the field reverts to its former contents.

TIP

If you make an entry in any field on a blank row of the task table, you create a task, even if it has no task name yet. If you accidentally create a task this way, you can remove it by selecting the ID number and pressing the Delete key.


graphics/tip_icon.jpg

It is a good practice in building projects to name activities in a verb-noun format, such as Install Computers, Write Design Specifications, or Move Warehouse. By using this concise call-to-action naming convention, it is easy to define the tasks and clearly communicate what work needs to be done in the project. It also makes it easy to estimate task durations by simply asking, "How long does it take to?"


NOTE

By default Microsoft Office's AutoCorrect feature is enabled in Project. Common errors are corrected as soon as you press the spacebar or type a punctuation mark. Note also that the list of spelling corrections is shared with all Office applications. You can manage the AutoCorrect feature (including disabling it altogether) by choosing Tools, AutoCorrect.


As soon as you press Enter or move to another cell, Project supplies the default duration 1 day? for the new task, and it supplies a default start and finish date for the task. It also displays a taskbar that starts at the project start date under the timescale in the Gantt Chart view, to the right. Then it moves the selection to the next row so that you can enter the next task.

TIP

If you don't want the selection to change when you press Enter, you can disable that feature. Choose Tools, Options and select the Edit tab. Clear the check box for Move Selection After Enter and click OK.


CAUTION

One more time : You should usually avoid changing the start or finish dates in the date columns . They are intended to be calculated by Project, based on the links between tasks that you'll create in Chapter 6. If you enter dates here, a constraint is created that might limit Project's ability to reschedule the task as needed.


If you really want to create a constraint for a task, see "Entering Task Constraints," p. 206 .


If you have created a task constraint that you want to remove, see "Removing Task Constraints," p. 216 .


NOTE

You can also use the mouse to create tasks by drawing bars on the Gantt Chart view where there is no task in the table on the left. Although this feature is easy to use, it has drawbacks. You still must go to the table to name the task, and you usually need to adjust the duration of tasks when they are created this way. Also, the task automatically has either a constrained start or finish. If you drag from the start to the finish when creating the bar, the task is constrained to start no earlier than the date where the taskbar starts. If you drag from the finish to the start, the task is constrained to finish no earlier than the finish date. You should rarely create a task by using the mouse.


Copying Task Names from Another Application

If task names have already been entered into another application such as a word processor, spreadsheet, or database, you can copy the list to the Windows Clipboard and paste it into Project.

NOTE

If there is additional information for each task that you want to copy into Project, the process is rather complicated because special data types such as dates and duration must be pasted into the correct columns. See "Exchanging Selected Parts of a Project with Other Formats," p. xxx . (Ch 17)


To copy a list of task names from another application into Project, follow these steps:

  1. Open both Project and the other application.

  2. In the other application, select the list of names you want to copy. Note these requirements for the source list:

    • If the source is a word processing document or presentation document (such as Microsoft Word or Microsoft PowerPoint), each task name must be on a separate row of text.

    • If the source is a spreadsheet (such as Microsoft Excel), each task name must be in a separate cell in a column of entries, and all the names you want to copy must be adjacent to each other.

    • If the source is a database (such as Microsoft Access), the task names must be in a single field of the database. Select the cells in that field only; do not select the records because that would select other fields also, and Project wouldn't know what to do with the other fields.

  3. Use the Copy command to copy the list to the Clipboard.

  4. Select the cell in the Task Name field in Project where you want to place the first name in the list, and then use the Paste command.

Displaying Long Task Names

If a task name is too long to see in the Task Name column, you can adjust the width of the column by using the mouse. Drag the right border of the cell that contains the column title to the right or left to change the column width. The pointer changes into a double-headed right and left arrow when it's in position to change the column width. If you double-click instead of drag, Project adjusts the column's width automatically to the longest entry it finds in the column.

If you don't place the mouse pointer directly on the title cell's borderline, the pointer does not change into a double-headed arrow, and double-clicking the mouse opens the Column Definition dialog box (shown in Figure 5.5). If that happens, you can still adjust the column width to the widest entry by clicking the Best Fit button.

Figure 5.5. You use the Column Definition dialog box for, among other things, adjusting the column width.

graphics/05fig05.gif

Adjusting the Height of Task Rows

Initially, each row in a table displays a single line of text. In this case, the row height is said to be 1. But you can adjust any or all rows to display variable numbers of text lines. The maximum row height is 20 (that is, 20 lines of text). Project automatically wraps text if extra lines are available and if the text entry is longer than the column width can display. Figure 5.6 shows wrapped task names.

Figure 5.6. You can use more than one row to display each task in the Gantt Chart view; this enables long task names to word-wrap.

graphics/05fig06.jpg

To adjust the height of a row, you drag the bottom (not the top) of the cell that contains the row number down to display more lines or up to display fewer lines. Note that row height is not infinitely variable. It can only be changed in increments of lines of text from 1 to 20.

NOTE

Unlike with adjusting column widths, you cannot double-click the line dividing row numbers to automatically set the best fit.


You can also change the heights of multiple rows at once. Select the row numbers that you want to change. Use Ctrl+click to select nonadjacent rows. To select all rows, click the Select All buttonthe blank column header above the row numbers. Drag the bottom of any row number cell to adjust all selected rows to the same height.

For information about setting specific row heights for a table, see "Using and Creating Tables," p. 840 .


 < Day Day Up > 


Special Edition Using Microsoft Office Project 2003
Special Edition Using Microsoft Office Project 2003
ISBN: 0789730723
EAN: 2147483647
Year: 2004
Pages: 283
Authors: Tim Pyron

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net