Selecting the Appropriate Task Settings

 < Day Day Up > 

If you don't assign resources to tasks or if you assign only material resources, you do not have to be concerned with selecting the task type or whether the task is effort driven. However, most assignments are for work resources, and for those you need to consider the task type and the effort-driven setting for a task each time you make or change resource assignments for the task.

NOTE

The effort-driven setting and the task types are defined and explained in detail in Chapter 9. Only a summary of the distinctions among the task types is given here. Similarly, the data fields that define a resource are covered in detail in Chapter 8 and are not explained again in detail here.


For detailed explanations of the use of the resource fields, see "Using the Resource Fields," p. 292 .


Setting the Task Type

The work formula is defined in terms of the values for duration, units, and work. When one of these values is changed, Project automatically recalculates the values for either one or both of the other values in order to keep the formula valid. The task type tells Project how you want it to calculate changes in the formula, and therefore changes in task assignments and the task schedule, when you assign resources or change resource assignments.

For more information about task types and the work formula, see "Choosing the Task Type," p. 335 .


The three task types are named Fixed Units, Fixed Work, and Fixed Duration. The default type for new tasks in Microsoft Project is Fixed Units. You can make any one of the three task types the default for new tasks by choosing Tools, Options and selecting the type in the Default Task Type field on the Schedule tab.

To verify or change the task type setting for a task, follow these steps:

  1. Select the task.

  2. graphics/dialogbox_icon.gif

    Click the Task Information tool to display the Task Information dialog box.

  3. Select the Advanced tab.

  4. Set the task type by choosing the list arrow and selecting Fixed Duration, Fixed Units, or Fixed Work (see Figure 10.1).

    Figure 10.1. You can use the Task Information dialog box to access additional fields of information about each task.

    graphics/10fig01.jpg

  5. Click OK.

You can also select the task's type on the Task Form view (see Figure 10.2), which is the view displayed in the bottom pane when you split a full-screen task view. To change the task type settings using the Task Form view, follow these steps:

Figure 10.2. You can access the Task Type field in the Task Form view.

graphics/10fig02.jpg

To display the Task Form view, follow these steps:

  1. If it is not already displayed, choose a task view such as the Gantt Chart view, the Task Sheet view, or the Task Usage view.

  2. Split the view by choosing Window, Split. The bottom pane displays the Task Form view.

  3. Activate the bottom pane. If resource details are not visible, choose Format, Details, and select one of the options that includes resources, such as Resources & Predecessors.

  4. Use the Task Type list box to choose a new task type.

If you know the duration you want, you should replace the default duration before you start assigning resources. Also, you must consider what you want Project to calculate for you and choose the appropriate task type. For example, if you have defined the duration and work that you want for the assignment and you want Project to calculate the units, you have to choose the appropriate task type before assigning the resource.

Table 10.1 provides the guidelines you need to determine which task type is appropriate for each pair of values you might want to define.

Table 10.1. Task Types for Initial Assignment

You Define This:

You Want Project to Calculate This:

Use This Task Type:

Duration and units

Work

Any task type

Duration and work

Units

Fixed Duration

Units and work

Duration

Fixed Units or Fixed Work

If you want Project to just calculate the work, any task type will do. If you want Project to calculate the units that you need to assign, you need to use Fixed Duration. Finally, if you want Project to calculate duration, you can use either Fixed Units or Fixed Work.

If you want to change one of the variables in an existing assignment, you can use the task type to control which variable Project changes. Table 10.2 shows which task type to choose when you want Project to change a specific variable as a result of a change that you make.

Table 10.2. Task Types for Assignment Changes

You Change This:

You Want Project to Change This:

Use This Task Type:

Units

Duration

Fixed Work

Units

Work

Fixed Duration

Work

Duration

Fixed Units

Work

Units

Fixed Duration

Duration

Work

Fixed Units

Duration

Units

Fixed Work

Choosing a Task's Effort-Driven Status

Closely allied to the choice of a task type is the choice of whether a task is effort driven . This choice has importance only when you change the number of work resources assigned to a task. It does not have any effect if you merely change the number of assigned units for an already assigned resource or if you change the material resources assigned to the task.

For more information about effort-driven tasks, see "Understanding Effort-Driven Tasks," p. 338 .


If a task is effort driven, when you add new work resource names to the assignment list, Project reapportions the existing work among all the resources, which results in less work for the preexisting resources and a shorter duration for the task. Conversely, if you remove a named work resource from a task, Project assigns its work to the remaining resources, and the task duration increases .

If a task is not effort driven, Project does not change the workloads of existing resources when you add a new work resource, and the task duration does not change. Total work for the task increases due to the addition of a new work resource.

To verify or change the Effort Driven setting for a task, follow these steps:

  1. Select the task.

  2. graphics/dialogbox_icon.gif

    Click the Task Information tool to display the Task Information dialog box. The Effort Driven field also appears on the Task Form (refer to Figure 10.2).

  3. Select the Advanced tab.

  4. Look at the Effort Driven check box (refer to Figure 10.1). If the check box is filled, the task is effort driven; if it is empty, the task is not effort driven. Click the check box if you want to change the status.

  5. Click OK.

The default status for new tasks in Project is effort driven, but you can change that default on the Options dialog box. Choose Tools, Options and select the Schedule tab on the Options dialog box. Deselect the New Tasks Are Effort Driven check box to change the default setting.

Before you make any change in resource assignments, you should ask yourself these two questions:

  • What do I want Project to leave unchanged when I enter this new information: duration, units, or work? Be sure to select the appropriate task type to force Project to do what you want.

  • Am I changing the number of named work resources that are already assigned to this task, and if so, do I want the total work for the task to remain the same or to be changed? If you want the total work to change, be sure you uncheck the Effort Driven field for the task.

You need to make sure that the task type and the effort-driven status are appropriate for the result you want to see.

 < Day Day Up > 


Special Edition Using Microsoft Office Project 2003
Special Edition Using Microsoft Office Project 2003
ISBN: 0789730723
EAN: 2147483647
Year: 2004
Pages: 283
Authors: Tim Pyron

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net