Section 11.1. Introduction


11.1. Introduction

In Chapter 10, we discussed how to manage your project once work gets underway. Monitoring and measuring project performance can be a challenge, especially if you use percent complete or other less technical measurements. We've all been involved in at least one project where everything seemed to be rolling along in the "green" zone and a week or two before project completion, all hell broke loose and the project suddenly was in the "red" zone. How do these things happen? Depending on whether you're in an optimistic or pessimistic mood, your assessment of the percent complete can change in part because percent complete is a judgement call. In this chapter, we're going to review a few more technical approaches to measuring project progress. Even if you don't plan on using them, you might find it useful to read through the material. You might be surprised to find that these are measurements you understand and could easily implement. If you choose not to read through the more technical measurements, skip to the middle of the chapter and pick up reading where we discuss common project problems and their solutions. Understanding and resolving project problems is part of keeping your project on track so you'll find helpful information in this section. It's not meant to be the definitive list of potential project problemsevery project is unique (by its very definition) and every project will encounter different problems. However, there are commonly occurring themes and these tend to crop up frequently. Being prepared for the common problems can be seen as part of your risk management strategy. Plan for the common problems and respond to the uncommon problems. You'll sleep better at night having some of these strategies in your back pocket.

As in previous chapters, let's look at where we are in our IT project management process. Figure 11.1 shows tracking as the last step before project close-out, discussed in Chapter 12.

Figure 11-1. IT Project Management Process Overview


Before we head into the chapter material, let's define new terms you'll encounter in this chapter.

  • Actual Cost The actual cost of all the work you completed.

  • Cost Performance Index (CPI) The ratio of the cost of work accomplished compared to the cost of work planned. A positive value indicates the project is under budget, a zero value indicates the project is on budget, a negative value indicates the project is over budget.

  • Critical Ratio The critical ratio (CR) is found by multiplying the schedule performance index (SPI) by the cost performance index (CPI). If the project is proceeding according to plan, the CR should be at or near 1. Any number above 1 indicates the project is making better than planned progress. Any number below one indicates the project is falling behind.

  • Earned Value The planned cost of all work you have completed.

  • Earned Value Analysis The analysis of the earned value of a project to indicate current project status and to forecast future project status.

  • Planned Value The planned cost of all work you expected to complete.

  • Schedule Performance Index (SPI) The ratio of work accomplished compared to the work planned. A positive value indicates the project is ahead of schedule, a zero value indicates the project is on schedule, a negative value indicates the project is behind schedule.

Tracking the project to maintain control, taking corrective action based on tracking data, and resolving common project problems are all part of managing the IT project, but are discussed separately in this chapter in order to clearly focus on these aspects of IT project management. For some IT projects, using a simple percent complete or variance reporting will be sufficient; for other IT projects, more detailed tracking and analysis is required and we'll cover these techniques in this chapter.

Figure 11.2 shows the inputs, actions, checkpoints, and outputs from this stage of the project lifecycle. It is the same diagram used in Chapter 10 since the tracking and control steps occur during the management phase of the project.

Figure 11-2. Inputs, Actions, and Outputs for Project Management Step


The discrete steps are delineated in Chapter 10, but it is important to note the project management process includes implementing the project, monitoring and tracking the results, and taking appropriate corrective action in an iterative manner until all project work has been successfully completed. In this chapter, we'll look at steps involved in tracking and controlling the project as well as the steps for preparing for final project deliverables and close-out.




How to Cheat at IT Project Management
How to Cheat at IT Project Management
ISBN: 1597490377
EAN: 2147483647
Year: 2005
Pages: 166

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net