1. | You are the project manager for a project that will develop an in-house software used to monitor computer parts inventory. Your project sponsor asks that you begin working on the WBS. What is a WBS?
|
|
2. | In regard to a WBS, what is a work package?
|
|
3. | What is the 8/80 Rule?
|
|
4. | Why must a project manager and the project team create a WBS?
|
|
5. | You are implementing a small network and would like to create a WBS. Todd, your assistant, does not want to create a WBS for such a small project. Why should you create a WBS for every project?
|
|
6. | You have finished creating the WBS, and the project sponsor asks to see the schedule in a Gantt chart format. What is a Gantt chart?
|
|
7. | Of the following, which two statements are accomplished by creating a WBS?
|
|
8. | When you create a WBS, there are two main methods you can use. What are they? Choose two:
|
|
9. | Of the different methods available to create a WBS, which requires the most logic and structure?
|
|
10. | Of the following, which would not help a project manager determine the phases of a project?
|
|
11. | Of the following, which is a benefit of using Microsoft Project to create the WBS?
|
|
12. | Which one of the following is not needed when creating a WBS?
|
|
13. | You are the IT project manager for a project to install a new mail server. Which of the following best describes the best approach to creating the WBS?
|
|
14. | Why should the project scope be guarded against even simple additions?
|
|
15. | What should signify the end of each phase?
|
|
Answers
1. | B. A WBS is a decomposition of the work required to complete the project. It serves as input to five key processes within a project: cost estimating, cost budgeting, resource planning, risk management planning, and activity definition. |
2. | C. A work package is the smallest decomposed object within the WBS. |
3. | C. The 8/80 Rule is a guide that says a project activity should not be decomposed less than 8 hours or last more than 80 hours. |
4. | C. A WBS is a deliverables-orientated decomposition of the project work. It is a process to ensure that all of the required deliverables are identified and broken down into manageable components so resources and labor may be assigned to complete the project work. |
5. | B. A WBS, even on small projects, ensures that all tasks are complete and whole. It does not necessarily ensure maximum billable hours, nor does it promise work toward a definite deliverable ”these would be accomplished through the project plan. The project manager is responsible for ensuring that Todd performs all of his duties , not the WBS. |
6. | C. A Gantt chart represents the WBS in a visual format. It depicts the start and end of phases and tasks. It does not represent the time involved for each team member. Although a Gantt chart could depict the total time involved for an entire team, that is not its true purpose. Finally, a Gantt chart does not reflect finances committed to the project. |
7. | A, C. A WBS does identify all of the deliverables the project will create. It can help control the project by referencing the WBS for resource planning, cost estimating, risk management planning, and activity definition. |
8. | A, D. The process of creating a WBS uses either top-down or bottom-up methods. Recall that the top-down method uses deductive reasoning and the bottom-up method uses inductive reasoning. |
9. | A. A WBS using the top-down method involves deductive reasoning, which requires logic and structure. |
10. | D. A WBS does not necessarily need to revolve around the number of team members available. Project deliverables, project milestones, and business cycles will have impact on the WBS. |
11. | C. Microsoft Project is an excellent software tool to finalize your WBS. A whiteboard is still ideal to use during the project planning phases. Microsoft Project can be used to prove the sequence of events, but a whiteboard can accomplish the same task in less time. Microsoft Project does not necessarily reduce the overall cost of the project, though it can help organize and streamline the effort to map out the project schedule. |
12. | B. The WBS is not concerned with the order of activities. Activity sequencing and scheduling, however, will be concerned with the order and relationship of activities. |
13. | C. Creating a WBS is not a solo activity. The project manager should work with the project team and any key stakeholders to create a WBS. |
14. | C. Additions to the project scope can have huge impacts on the deliverables of a project. Often additions are tossed into the plans without adequate foresight or care so their consequences can throw a perfect plan off balance. Do not change the scope of an existing project unless it is absolutely required. |
15. | D. Just as each project produces a definite deliverable, so should each phase. A milestone does not necessarily signify a phase has ended, as there can be multiple milestones within each phase. A party for the project team (while always an excellent idea) does not prove that a phase has officially ended. Dates, while targets for completion, do not signify the end of a phase ”the deliverable proves the end of a project phase. |