Updating Task Status

     

Updating your project with your resources' status is one of the most important things you can do to keep track of how your project is really going. This can be as simple as updating the Percent Complete field, or as complex as getting a day-by-day breakdown of the actual work for each task assignment from your resources and entering it into the Resource Usage view. Either way, what you're really doing is updating your plan so that it stays consistent with reality. A plan is just that ”a plan. Once the project starts, however, you need to update your plan to account for reality's effects on your original idea. Without this updating for reality, your plan becomes a paper boat anchor, useless before you even get a chance to really use it. If you do not update your project, you end up with an old understanding of what needs to be done. A few tasks slip, and then the tasks that depend on those tasks slip, and so on. If you do not update the plan, it becomes very difficult to let your resources know what their new task start dates really are. Updating is essential and should not be overlooked.

Updating Tasks Using Percent Complete

graphics/one_icon.jpg Click the View, Table, Tracking menu item to apply the tracking table.

graphics/two_icon.jpg For the task to be updated, enter the date when the task actually started in the Actual Start field.

graphics/three_icon.jpg Enter the percent complete in the Percent Complete field.

graphics/four_icon.jpg If the task is finished, enter the Actual Finish date (if the date the task was completed is different from the date that Project entered in the Actual Finish field).

graphics/five_icon.jpg Repeat this process for each task that needs to be updated.

graphics/11inf17.jpg

Using the Tracking Toolbar Buttons

graphics/one_icon.jpg Right-click on any toolbar.

graphics/two_icon.jpg Select Tracking from the list of toolbars .

graphics/three_icon.jpg Select the task or tasks you want to update.

graphics/four_icon.jpg Click on the toolbar button that represents the level of progress for the selected tasks (0, 25, 50, 75, or 100 percent).

graphics/five_icon.jpg The tasks are updated.

graphics/11inf18.jpg


Show Me. Microsoft Office Project 2003
Show Me Microsoft Office Project 2003
ISBN: 0789730693
EAN: 2147483647
Year: 2003
Pages: 204

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net