Moving Summary TasksI don't understand how to move summary tasks without moving their subtasks . What do I need to do? First, outdent the subtasks so that the summary task becomes a regular task. Then you can move, copy, cut, delete, promote, or demote the task without affecting its former subtasks. Preserving Edited Custom WBS CodesAfter I customize my summary task WBS codes, they seem to disappear when I have Project renumber tasks. What am I doing wrong? If you have edited custom WBS codes for summary tasks and then want Project to renumber the tasks, your edited changes are lost unless you take the following steps:
The entire task list is displayed again. The summary tasks have not lost their edited codes, but all other tasks are renumbered based on their current order in the outline. |