Flylib.com

Books Software

 
 
 

Troubleshooting

 <  Day Day Up  >  

Troubleshooting

Attaching to a Taskbar

graphics/note_icon.jpg

My drawing won't stay with the taskbar I want it associated with. What should I do?

Choose Format, Drawing, Properties to attach the drawing to the task instead of to a date on the timeline.

Missing Taskbar

The taskbars are hidden by the drawing and I can't see them. What should I do?

You need to select the drawing and use the shortcut menu to move the drawing back to a lower drawing layer. This will draw the object behind the taskbars.

If an object seems to disappear after you attach it to a taskbar, open the Format Drawing dialog box again and change the horizontal and vertical offset values to zero. Then the object appears right next to the taskbar, and you can reposition it with the mouse.

Linking Lines and the Task Dependency Box

If I double-click a linking line in the Network Diagram view, the Task Dependency dialog box doesn't display the relationship between the two tasks I'm interested in. What should I do?

Linking lines in the Network Diagram view (and also the Gantt Chart view) are sometimes drawn on top of other linking connections, which makes it hard to pinpoint the pair of tasks you want. Your best bet is to open the Task Information dialog box for the successor task in the pair. Then you can make changes to the linking relationship on the Predecessors tab of the dialog box.

 <  Day Day Up  >  
 <  Day Day Up  >  

Part III: Assigning Resources and Costs

 

8 Defining Resources and Costs

 

9 Understanding Resource Scheduling

 

10 Assigning Resources and Costs to Tasks

 

11 Resolving Resource Assignment Problems

 <  Day Day Up  >  
 <  Day Day Up  >  

Chapter 8. Defining Resources and Costs

In this chapter

Understanding How Project Uses Resources and Costs

Understanding Resources and Costs

Defining the Resource Pool

Using the Resource Fields

Setting the Automatically Add New Resources and Tasks Option

Sorting Resources

Grouping Resources

Filtering Resources

Troubleshooting

 <  Day Day Up  >  
 <  Day Day Up  >  

Understanding How Project Uses Resources and Costs

This chapter focuses on resources and costs ”understanding what resources are, how to create a resource pool, and how resource costs are calculated in Microsoft Project. You will learn how to define resources and their costs and how to define costs that are not associated with a particular resource. With this foundation, you will then be ready in ensuing chapters to assign resources and costs to tasks , modify those assignments, and resolve conflicts that arise with overallocated resources.

Although you can create a schedule in Microsoft Project without assigning resources to the tasks, such a schedule is based on the assumption that you will have all the necessary resources on hand whenever you need them ”and that assumption is rarely realistic. People take vacations , have sick leave, or have unique work schedules. Machinery and equipment need downtime for maintenance. Employees leave the organization and new ones arrive . New facilities are not ready for occupancy until midway through a project. All these are examples of situations in which a resource that is necessary to complete a task might not be available when Project schedules the task. You can make a project schedule more realistic by defining and assigning resources to tasks. At the very least, you should assign to each task the name of the person who is responsible for seeing it through to completion.

There are several major benefits of including resources in a project file:

  • If you provide the working time information for each resource, Project automatically schedules tasks only during those times.

  • After you assign resources to all the tasks, Project can help you see how many units of each resource you will need to complete the project.

  • Every project manager needs to know how much the project will cost. If you include the cost information for each resource, Project automatically calculates the cost of each resource assignment to individual tasks, and sums those costs to show the total cost of each task and the overall cost of the project. You can use these cost calculations in estimating the budget for the project.

You can define a comprehensive list of resources at the outset, including resource cost rates and availability information. Later, you will assign these resources to tasks. Alternatively, you can define the resources as you create the tasks, while you are thinking about how the work will be done. When you assign new resource names to a task, Project adds these names to the list of resources (see Figure 8.1). If you create resources on-the-fly , you must remember to go back later and enter the resource cost rates and availability information.

Figure 8.1. The list of resources includes information about the availability and cost of using the resources.

graphics/08fig01.jpg

NOTE

The Automatically Add New Resources and Tasks option (which is available on the General tab of the Options dialog box) determines how Project treats undefined resources that you assign to tasks. See the section "Setting the Automatically Add New Resources and Tasks Option," later in this chapter, to learn about the hazards of using this option.


 <  Day Day Up  >