| < Day Day Up > |
TroubleshootingAttaching to a TaskbarMy drawing won't stay with the taskbar I want it associated with. What should I do? Choose Format, Drawing, Properties to attach the drawing to the task instead of to a date on the timeline. Missing TaskbarThe taskbars are hidden by the drawing and I can't see them. What should I do? You need to select the drawing and use the shortcut menu to move the drawing back to a lower drawing layer. This will draw the object behind the taskbars.
If an object seems to disappear after you attach it to a taskbar,
Linking Lines and the Task Dependency Box
If I double-click a linking line in the Network Diagram view, the Task Dependency dialog box doesn't display the relationship between the two
Linking lines in the Network Diagram view (and also the Gantt Chart view) are sometimes drawn on top of other linking connections, which makes it hard to pinpoint the pair of tasks you want. Your best bet is to open the Task Information dialog box for the successor task in the pair. Then you can make changes to the linking relationship on the Predecessors tab of the dialog box. |
| < Day Day Up > |
| < Day Day Up > |
Part III: Assigning Resources and Costs
|
| < Day Day Up > |
| < Day Day Up > |
Chapter 8. Defining Resources and CostsIn this chapter
|
| < Day Day Up > |
| < Day Day Up > |
Understanding How Project Uses Resources and Costs
This chapter focuses on resources and costs ”understanding what resources are, how to create a resource pool, and how resource costs are calculated in Microsoft Project. You will learn how to define resources and their costs and how to define costs that are not associated with a particular resource. With this foundation, you will then be ready in ensuing chapters to assign resources and costs to
Although you can create a schedule in Microsoft Project without assigning resources to the tasks, such a schedule is based on the assumption that you will have all the necessary resources on hand whenever you need them ”and that assumption is rarely realistic. People take
There are several major benefits of including resources in a project file:
You can define a comprehensive list of resources at the outset, including resource cost rates and availability information. Later, you will assign these resources to tasks. Alternatively, you can define the resources as you create the tasks, while you are thinking about how the work will be done. When you assign new resource names to a task, Project adds these
Figure 8.1. The list of resources includes information about the availability and cost of using the resources.
NOTE The Automatically Add New Resources and Tasks option (which is available on the General tab of the Options dialog box) determines how Project treats undefined resources that you assign to tasks. See the section "Setting the Automatically Add New Resources and Tasks Option," later in this chapter, to learn about the hazards of using this option. |
| < Day Day Up > |