The goal of this activity is to provide experience in brainstorming activities and in breaking them down and organizing them into a logical work structure.
Handout 11-5: Project Case Study (already distributed)
Post-It notes
flipchart paper.
for the two-day version of the workshop, 20 minutes; for the one-day version, approximately seven or eight minutes
For the two-day version of the workshop, teams should be expected to break down the case study into at least 20 activities. Using Post-It notes and flipchart paper, they should arrange the activities either by project phase or by major component.
For the one-day class, ask the teams to create a WBS either for one of the project phases or for just one of the components , depending on their choice of approach.
Have each team explain its approach and quickly enumerate the activities making up their WBS.