| 1. | You define the end of the project by defining the: 
| A. | Scope Statement | 
| B. | Charter | 
| C. | Final deliverable | 
| D. | Schedule |
|
| 2. | The phase in which you define the final deliverable is: 
| A. | Planning | 
| B. | Execution | 
| C. | Closing | 
| D. | Control |
|
| 3. | The person who has the responsibility for keeping the final deliverable clear to all stakeholders is the: 
| A. | Sponsor | 
| B. | Technical lead | 
| C. | Team member | 
| D. | Project manager |
|
| 4. | Administrative Closure should occur: 
| A. | Only at the end of a project | 
| B. | Every week | 
| C. | At the end of each phase | 
| D. | On Thursdays |
|
| 5. | Information needs to go to: 
| A. | Everyone on the team | 
| B. | The sponsors | 
| C. | The stakeholders | 
| D. | Everyone in the communication plan |
|
| 6. | As you make approved changes to the original scope, you should: 
| A. | Save the old versions | 
| B. | Shred the old versions | 
| C. | Amend the SOW | 
| D. | Do a completely new WBS |
|
| 7. | If your project comes in 20% ahead of schedule and 25% under budget you should: 
| A. | Reward yourself | 
| B. | Demand a raise and throw a party | 
| C. | Be proud | 
| D. | Find out why there was such a variance from the original plan |
|
| 8. | A complete set of indexed project records is called: 
| A. | Project history | 
| B. | Project archives | 
| C. | The index | 
| D. | The SOW |
|
| 9. | Acceptance of the product of the project should be: 
| A. | Formal | 
| B. | Fast | 
| C. | Consistent | 
| D. | Personal |
|
| 10. | Formal acceptance includes: 
| A. | High praise | 
| B. | Written acceptance | 
| C. | Dialectic | 
| D. | Verbal acceptance |
|
| 11. | The ________ is the person/organization that gives project acceptance. 
| A. | Sponsor | 
| B. | Project team | 
| C. | Delivering organization | 
| D. | Customer |
|
| 12. | The project manager must comply with the requirements of both the customer and: 
| A. | His own organization | 
| B. | The functional managers | 
| C. | The line manager | 
| D. | Executive management |
|
| 13. | A ________ must be written in order to require Contract Closeout. 
| A. | WBS | 
| B. | Formal contract | 
| C. | SOW | 
| D. | Scope Statement |
|
| 14. | A(n) ________ performs the procurement audit. 
| A. | Project manager | 
| B. | Project team | 
| C. | Sponsor | 
| D. | Outside individual/organization |
|
| 15. | What information goes into lessons learned? 
| A. | Everything that happens | 
| B. | Only major concerns | 
| C. | Only minor concerns | 
| D. | Information that will help future project managers |
|
| 16. | When do you discuss lessons learned? 
| A. | Once a month | 
| B. | At a formal meeting after the project | 
| C. | At regular status meetings | 
| D. | At the New Year's party |
|
| 17. | Lessons learned should be: 
| A. | Written down | 
| B. | Carried around in the project team's head | 
| C. | Chiseled in stone | 
| D. | Only done at the end of the project |
|
| 18. | Lessons learned are valuable to: 
| A. | Project managers | 
| B. | Project teams | 
| C. | Stakeholders | 
| D. | All of the above |
|
| 19. | Who is responsible for keeping a lessons learned log? 
| A. | The project manager | 
| B. | The sponsor | 
| C. | Team members | 
| D. | Stakeholders |
|
| 20. | The contract file consists of ________ records. 
| A. | All | 
| B. | Good | 
| C. | Indexed | 
| D. | Accounting |
|
| 21. | Before the main vendor is paid, be sure that ________ are paid. 
| A. | Employees | 
| B. | Sub-contractors | 
| C. | Sponsors | 
| D. | Developers |
|