Questions from Chapter Fifteen


1.

Project risk is the uncertainty that an event or condition that affects ________ will be realized.

A.

Project performance as measured by the functional managers

B.

Project impact on the organization

C.

Opportunities the project could realize

D.

At least one of the project objectives such as cost, scope, time, or quality


2.

True or False? Risks may have one or more causes and one or more impacts.

3.

Risk Management Planning should be completed ________ in the project planning phase.

A.

Sometime

B.

Late

C.

Early

D.

Never


4.

What is a Risk Breakdown Structure (RBS)?

A.

Flowchart of risks

B.

Risk impacts on the organization

C.

List or diagram of risks by category

D.

Risk management activities that are on the schedule


5.

Which of the following would be used to describe the significance of the negative impact of threats or the positive impact of opportunities?

A.

Cost, time, scope, and quality

B.

Sources of the risk events

C.

Types of risk responses

D.

Very Low, Low, Moderate, High


6.

According to Table 15-2, the impact of a risk to the project schedule will be classified as ________ if the delay to the project (as a result of the risk event) will be one week to a 20-week project schedule.

A.

Low

B.

High

C.

Very Low

D.

Moderate


7.

________ usually follows the Risk Identification process, but sometimes ________ directly follows the Risk Identification process when an experienced risk manager is involved.

A.

Risk Management Planning, Quantitative Risk Analysis

B.

Qualitative Risk Analysis, Quantitative Risk Analysis

C.

Quantitative Risk Analysis, Qualitative Risk Analysis

D.

Risk Monitoring and Control, Risk Response Planning


8.

The inputs to Risk Identification are similar to the inputs to the Risk Management Planning process with the addition of the ________.

A.

Scope Statement

B.

Risk Management Plan

C.

Risk Identification method

D.

WBS


9.

Which of the following is NOT an information gathering technique for risk management?

A.

Interviews

B.

Probability and Impact Matrix

C.

Delphi technique

D.

Root cause analysis


10.

The Risk Register consists of:

A.

Qualitative Risk Analysis, Quantitative Risk Analysis, and Risk Management Plan

B.

Qualitative Risk Analysis, Risk Response Plan, list of identified risks

C.

List of identified risks, potential responses, root causes, and updated risk categories

D.

Risk Responses, Risk Categories, Risk Management Plan


11.

________ and ________ are assessed for each identified risk in the Qualitative Risk Analysis process.

A.

Probability, impact

B.

Impact, priority

C.

Probability, costs

D.

None of the above


12.

The ________ section of the Risk Register can be used to ensure that some risk events are not overlooked during the project life cycle.

A.

Priority

B.

Watch List

C.

Qualitative Risk Analysis

D.

None of the above


13.

The Risk Register is updated periodically throughout the project life cycle. The Risk Register is initiated during ________ and further updated based on the information developed in the ________.

A.

Risk Management Planning, Qualitative Risk Analysis

B.

Risk Identification, Quantitative Risk Analysis

C.

Risk Identification, Qualitative Risk Analysis

D.

Risk Management Planning, Risk Identification


14.

The inputs to the Quantitative Risk Analysis process are the Project Management Plan, Risk Register, Risk Management Plan, ________, and ________.

A.

Organizational Process Assets, Project Scope Statement

B.

Impact and Probability Matrix, Project Scope Management Plan

C.

Risk Probability, Impact Assessment

D.

Project Scope Management Plan, Organizational Process Assets


15.

Name the two tools and techniques of the Quantitative Analysis that are most subjective, i.e., based on opinions.

A.

Interviewing, Decision Tree Analysis.

B.

Probability distributions

C.

Expert judgment, Interviewing

D.

Expert judgment, Sensitivity Analysis


16.

What parts of the Risk Register are added during Quantitative Risk Analysis?

A.

Trends in Quantitative Risk Analysis results

B.

Probabilities of achieving project objectives

C.

Estimates of cost and schedule outcomes

D.

B and C

E.

A and B


17.

Name the strategies for negative risks.

A.

Avoid, Mitigate, Transfer, Contingency, Accept

B.

Avoid, Transfer, Mitigate

C.

Avoid, Transfer, Accept, Mitigate

D.

None of the above


18.

True or False? Mitigation as a response strategy will always add time and/or money to the project.



Passing the PMP Exam. How to Take It and Pass It
Passing the PMP Exam: How to Take It and Pass It: How to Take It and Pass It
ISBN: 0131860070
EAN: 2147483647
Year: 2003
Pages: 167
Authors: Rudd McGary

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net