There is no single method that applies to all projects. Estimating is very domain specific. Construction, software,
The objectives of performing an estimate are twofold: to
Most estimating fits into one of four models as
Top-down
value
Similar-to judgments from either side of the project balance sheet, but most often from the business side
Bottom-up facts-driven estimates of actual work effort from the project side of the project balance sheet conveyed to the project sponsor
Parametric calculations from a cost-history model, developed by the project team, and conveyed to the project sponsor
Figure 3-8:
Estimating Concepts.
Naturally, it is rare that a project would depend only on one estimating technique; therefore, it is not unusual that any specific project team will use all the estimating methods available to it that fit the project context. However, let us consider them one by one.
Top-down estimates could be made by
Working with top-down estimates requires the steps shown in Table 3-3.
Project risks are greatest in this estimating methodology,
and
overall cost estimates are usually
|
Step |
Description |
|---|---|
|
Receive estimates from the business |
Estimates from the business reflect a judgment on the investment available given the intended scope and value to the business. |
|
Interview business
|
Scope is the common understanding between the business and the project. Interviews provide the opportunity to exchange information
|
|
Verify assumptions and validate sources, if any |
The business judgment on investment and value is based on certain assumptions of the business managers and may also include
|
|
Develop WBS from scope |
WBS must contain all the scope, but only the scope required by the business sponsors. |
|
Allocate top-down resources to WBS |
Allocation is a means of distributing the investment made possible by the business to the elements of scope on the WBS. |
|
Cost account managers identify risks and gaps |
Cost account managers have responsibility for elements of the WBS. They must assess the risk of performance based on the allocation of investment to the WBS made by the project manager. |
|
Negotiate to minimize risks and gaps |
Once the risks are quantified and
|
|
Top-down estimate to the business side of project balance sheet |
The business makes the judgment on how much investment to make. This investment goes on the business side of the project balance sheet. |
|
Expected value estimate and risks to project side of balance sheet |
Once the allocation is made to the WBS, there is opportunity for the project manager to develop the risks to performance, the expected value, and the confidence of meeting the sponsor's objectives. |
A common application of the top-down methodology is in competitive bidding to win a project opportunity as a contractor to the project sponsor. In this scenario, the top-down estimate usually comes from a marketing or sales assessment of what the market will bear, what the competition is bidding, and in effect
"what it will take to win."
If the top-down estimate is the figure offered to the customer as the price, then the project manager is left with the task of estimating the risk of performance and developing the risk management plan to contain performance cost within the
Top-down offer to do business = Independently estimated cost of performance offered + Risk to close gap with top-down offer
From the steps in Table 3-3, we see that the project manager must allocate the top-down budget to the WBS. Doing so involves the following quantitative steps:
Develop the WBS from the scope statement, disregarding cost.
By judgment, experience, prototyping, or other means, determine or identify the deliverable of least likely cost, or the deliverable that represents the smallest "standard unit of work." Give that deliverable a numerical cost weight of 1 and call it the "baseline" deliverable, B. This procedure normalizes all costs in the WBS to the cost of the least costly
Estimate the normalized cost of all other deliverables,
D
, as
Sum all deliverable weights and divide the sum into the available funds to determine an absolute baseline cost of the least costly deliverable.
($Top-down budget)/( ∑ M i ) = Allocated cost of baseline task B
A "
Total cost bias in WBS = n * O
Complete the allocation of all top-down budgets to the deliverables in the WBS according to their weights.
It is helpful at this point to simplify the disparate deliverables on the WBS to an average deliverable and its statistics. We know from the Central Limit Theorem that the average deliverable will be Normal distributed, so the attributes of the Normal distribution will be helpful to the project manager:
Average deliverable cost = α d = (1/n) * ∑ [ D i + ( M i * O )]
σ 2 of average deliverable = (1/n) * ∑ [( D i + O ) - α d ] 2 , and
σ of average deliverable = √ (1/n) * ∑ [( D i + O ) - α d ] 2
It is easier to calculate these figures than it probably appears from looking at the formulas. Table 3-4 provides a numerical example. In this example, a $30,000 top-down budget is applied to a WBS of seven deliverables. An offset is estimated at 23% of the allocated cost. Immediately, it appears that there may be a $6,900 risk to manage (23% of $30,000). However, we see from the calculations
|
WBS Element |
Weight, M i |
Allocated Budget, D i |
Allocated Budget + ( M i * O) |
Distance 2 (d - average d ) 2 |
|---|---|---|---|---|
|
a |
b |
c |
d |
e |
|
1 |
||||
|
1.1.1 |
8 |
$10,435 |
$12,835 |
57,204,324 |
|
1.1.2 |
5 |
$6,522 |
$8,022 |
7,564,208 |
|
1.1.3 |
1 |
$1,304 |
$1,604 |
13,447,481 |
|
1.2.1 |
2 |
$2,609 |
$3,209 |
4,254,867 |
|
1.2.2 |
2.5 |
$3,260 |
$4,010 |
1,591,202 |
|
1.3.1 |
1.5 |
$1,957 |
$2,407 |
8,207,691 |
|
1.3.2 |
3 |
$3,913 |
$4,813 |
210,117 |
|
Totals: |
23 |
$30,000 |
$36,900 |
92,479,890 |
|
Given: Top-down budget = $30,000 Evaluated least costly baseline deliverable, B = $1,304.35 Estimated independent cost of B = $1,604.35 Calculated baseline offset, O, = $300 = $1,604.35 - $1,304.35 |
||||
|
n = 7 ∑ M i = 23 ∑ D i = ∑ ( M i * B) = $30,000 Average deliverable, average d , with offset = $36,900/7 = $5,271 Variance, σ 2 = 92,479,890/7 = 13,211,413 Standard deviation, σ = $3,635 |
||||
|
Confidence calculations: Total standard deviation of WBS = √ 7* σ 2 = √ 92,479,890 = $9,616 24% confidence: WBS total ≤ $30,000 [*] 50% confidence: WBS total ≤ $36,900 68% confidence: WBS total ≤ $36,900 + $9,616 = $46,516 |
||||
|
[*] From lookup on single-tail standard Normal table for probability of outcome = ($36,900 -$30,000)/$9,616 = 0.71 σ below the mean value. Assumes summation of WBS is approximately Normal with mean = $36,900 and a = $9,616. |
||||
Once the risks are calculated, all the computed figures can be moved to the right side of the project balance sheet. Let us recap what we have so far. On the business side of the project balance sheet, we have the top-down budget from the project sponsors. This is a value judgment about the amount of investment that can be afforded for the deliverables desired. On the right side of the balance sheet, the project manager has the following
The estimated "fixed" bias between the cost to perform and the available budget. In the example, the bias is $6,900.
The average WBS for this project and the statistical standard deviation of the average WBS. In this example, the average WBS is $36,900 (equal to the budget + bias) and the standard deviation is $9,616.
And, of course, the available budget, $30,000.
As was done in the example, confidences are calculated and the overall confidence of the project is negotiated with the project sponsor until the project risks are within the risk tolerance of the business.
"Similar-to" estimates have many of the features of the top-down estimate except that there is a model or previous project with similar characteristics and a cost history to guide estimating. However, the starting point is the same. The business declares the new project "similar to" another completed project and provides the budget to the new project team based on the cost history of the completed project. Of course, some adjustments are often needed to correct for the escalation of labor and material costs from an earlier time frame to the present, and there may be a need to adjust for scope difference. In most cases, the "similar-to" estimate is very much like a top-down estimate except that there is usually cost history at the WBS deliverable level available to the project manager that can be used by the project estimating team to narrow the offsets. In this manner, the offsets are not uniformly proportional as they were in the top-down model, but rather they are adjusted for each deliverable to the extent that relevant cost history is available.
The quantitative methods applied to the WBS are not really any different from those we employed in the top-down case except for the individual treatment of the offsets. Table 3-5 provides an example. We assume cost history can improve the offset estimates (or provide the business with a more realistic figure to start with). If so, the confidence in budget developed by the business as a "similar to" is
|
WBS Element |
Allocated Budget from Cost History, D i |
Offset |
Allocated Budget + ( M i * O) |
Distance 2 (d - average d ) 2 |
|---|---|---|---|---|
|
a |
b |
c |
d |
e |
|
1 |
||||
|
1.1.1 |
$10,435 |
$200 |
$10,635 |
39,813,357 |
|
1.1.2 |
$6,522 |
-$100 |
$6,422 |
4,396,315 |
|
1.1.3 |
$1,304 |
$300 |
$1,604 |
7,401,948 |
|
1.2.1 |
$2,608 |
$50 |
$2,658 |
2,778,889 |
|
1.2.2 |
$3,261 |
-$75 |
$3,186 |
1,297,618 |
|
1.3.1 |
$1,957 |
$100 |
$2,057 |
5,145,994 |
|
1.3.2 |
$3,913 |
-$200 |
$3,713 |
374,491 |
|
Totals: |
$30,000 |
$275 |
$30,275 |
61,208,612 |
|
Given: Top-down budget = $30,000 Evaluated least costly baseline deliverable, B = $1 ,304 |
||||
|
N = 7 ∑ M i = 23 ∑ D i = ∑ ( M i * B) = $30,000 Average deliverable, average d , with offset = $30,275/7 = $4,325 Variance, σ 2 = (1/7) * (61,208,612) = 8,744,087 Standard deviation, σ = $2,957 |
||||
|
Confidence calculations: Total standard deviation of WBS = √ 61, 208,612 = $7,823 46% confidence: WBS total ≤ $30,000 [*] 50% confidence: WBS total ≤ $30,275 68% confidence: WBS total ≤ $30,275 + $7,823 = $38,098 |
||||
|
[*] From lookup on single-tail standard Normal table for probability of outcome = ($30,275 - $30,000)/$2,957 = 0.09 σ below the mean value. Assumes summation of WBS is approximately Normal with mean = $30,275 and σ = $2,957. |
||||
So far we have seen that the project side of the balance sheet is usually a higher estimate than the figure given by the business. Although there is no business rule or project management practice that makes this so in every case, it does happen more often than not. That trend toward a higher project estimate continues in bottom-up estimating.
Bottom-up estimating, in its purest form, is an independent estimate by the project management team of the activities in the WBS. The estimating team may actually be several teams working in parallel on the same estimating problem. Such an arrangement is called the Delphi method. The Delphi method is an approach to bottom-up estimating whereby independent teams evaluate the same data, each team comes to an estimate, and then the project manager synthesizes a final estimate from the inputs from all
The starting point for the estimating team(s) is the scope statement provided by the business. A budget from the business is provided as information and guidance. Parametric data developed from cost history are assumed to be unavailable. In practice, parametric data in some form are usually available, but we will discuss parametric data
Best practice in bottom-up estimating employs the "n-point" estimate rather than a single deterministic number. The number of points is commonly taken to be three: most likely, most pessimistic, and most optimistic (thus the expression "three-point estimates"). A distribution must be selected to go with the three-point estimate. The Normal, BETA, and Triangular are the distributions of choice by project managers. The BETA and Triangular are used for individual activities and deliverables; the Normal is a consequence of the interaction of many BETA or Triangular distributions in the same WBS. However, if there are deliverables with symmetrical optimistic and pessimistic values, then the Normal is used in those cases.
Table 3-6 provides a numerical example of bottom-up estimating using the BETA distribution. Recall that the Triangular distribution will give more pessimistic statistics than the BETA. Although individual deliverables are estimated with somewhat wide swings in optimistic and pessimistic range, overall the confidence of hitting a lower number with greater
|
WBS Element |
Most Likely Estimate |
Most Pessimistic Offset |
Most Optimistic Offset |
BETA Expected Value |
BETA Variance |
|---|---|---|---|---|---|
|
1 |
|||||
|
1.1.1 |
$11,000 |
$3,000 |
-$1,000 |
$11,333 |
444,444 |
|
1.1.2 |
$6,800 |
$4,000 |
-$700 |
$7,350 |
613,611 |
|
1.1.3 |
$1,500 |
$800 |
-$300 |
$1,583 |
33,611 |
|
1.2.1 |
$3,000 |
$2,000 |
-$500 |
$3,250 |
173,611 |
|
1.2.2 |
$3,100 |
$1,800 |
-$750 |
$3,275 |
180,625 |
|
1.3.1 |
$1,800 |
$800 |
-$300 |
$1,883 |
33,611 |
|
1.3.2 |
$3,700 |
$1,900 |
-$600 |
$3,917 |
173,611 |
|
Totals: |
$32,591 |
1,653,124 |
|||
|
Business desires project outcome = $30,000 |
|||||
|
Average deliverable from BETA = $32,591/7 = $4,656 Variance, σ 2 = 1,653, 124/7 = 236,161 Standard deviation, σ = $486 |
|||||
|
Confidence calculations: Total standard deviation of WBS = √ 1, 653,124 = $1,286 50% confidence: WBS total ≤ $32,591 [*] 68% confidence: WBS total ≤ $32,591 + $1,286 = $33,877 |
|||||
|
[*] Assumes approximately Normal distribution of WBS summation with mean = $32,594 and σ = $1,286. |
|||||
Parametric estimating is also called model estimating. Parametric estimating depends on cost history and an estimate of similarity between that project history available to the model and the project being estimated. Parametric estimating is employed widely in many industries, and
|
Estimating Application |
Model Identification |
Key Model Parameters and Calibration Factors |
Model Outcome |
|---|---|---|---|
|
Construction |
PACES 2001 |
Covers new construction, renovation, and alteration
Covers
Regression model based on cost history in military construction
Input parameters (abridged list):
Media/waste type: cleanup facilities and methods |
Specific cost estimates (not averages) of specified construction according to model Project costs Life cycle costs |
|
Environmental |
RACER |
Handles natural attenuation, free product removal, passive water treatment, minor field installation, O&M, and phytoremediation Technical enhancements to over 20 technologies
Ability to use either system costs or
Professional labor template that creates task percentage template |
Programming and budgetary estimates for remedial environmental projects |
|
Hardware |
Price H |
Key parameters: weight, size, and manufacturing complexity
Input parameters:
|
Cost estimates
Other parameter
|
|
SEER H |
WBS oriented Six knowledge bases support the WBS elements: application, platform, optional description, acquisition category, standards, class Cost estimates are produced for development and production cost activities (18) and labor categories (14), as well as "other" categories (4) |
Production cost estimates, schedules, and risks associated with hardware development and acquisition |
|
|
NAFCOM (NASA Air Force Cost Model) Available to qualified government contractors and agencies |
WBS oriented Subsystem oriented within the WBS Labor rate inputs, overhead, and G&A costs Integration point inputs Test hardware and quantity Production rates Complexity factors Test throughput factors Integrates with some commercial estimating models |
Estimates design, development, test, and evaluation (DDT&E) flight unit, production, and total (DDT&E + production) costs |
|
|
Software |
COCOMO 81 (waterfall methodology) |
Development environment: detached, embedded, organic Model complexity: basic, intermediate, detailed Parameters used to calibrate outcome (abridged list): estimated delivered source lines of code, product attributes, computer attributes, personnel attributes, project attributes (with breakdown of attributes, about 63 parameters altogether) |
Effort and duration in staff hours or months Other parametric reports |
|
COCOMO II (object oriented) |
Development stages: applications composition, early design, post architecture (modified COCOMO 81) Parameters used to calibrate outcome (abridged list): estimated source lines of code, function points, COCOMO 81 parameters (with some modification), productivity rating (Stage 1) |
Effort and duration in staff hours or months Other parametric reports |
|
|
Price S |
Nine categories for attributes: project magnitude, program application, productivity factor, design inventory, utilization, customer specification and reliability, development environment, difficulty, and development process |
Effort and duration in staff hours or months Other parametric reports |
|
|
SEER-SEM |
Three categories for attributes: size, knowledge base, input Input is further subdivided into 15 parameter types very similar to the other models discussed |
Effort and duration in staff hours or months Other parametric reports |
Most parametric models are "regression models." We will discuss regression analysis in Chapter 8. Regression models require data sets from past performance in order that a regression formula can be derived. The regression formula is used to predict or forecast future performance. Thus, to
Once a calibrated model is in hand, to obtain estimates of deliverable costs the model is fed with parameter data of the project being estimated. Model parameters are also set or adjusted to account for similarity or dissimilarity between the project being estimated and the project history. Parameter data could be the estimated number of lines of software code to be written and their appropriate attributes, such as degree of difficulty or complexity. Usually, a methodology is incorporated into the model. That is to say, if the methodology for developing software involves requirements development, prototyping, code and unit test, and system tests, then the model takes this methodology into account. Some models also allow for specification of risk factors as well as the severity of those risks.
Outcomes of the model are applied directly to the deliverables on the WBS. At this point, outcomes are no different than bottom-up estimates. Ordinarily, these
Table 3-8 provides a numerical example of parametric estimating practices in the WBS.
|
WBS Element |
Deliverable |
Units |
Quantity |
Parametric Cost |
Model Expected Value |
Model Standard Deviation, σ |
Calculated Variance, σ 2 |
|---|---|---|---|---|---|---|---|
|
1 |
|||||||
|
1.1.1 |
Software code |
Lines of code |
5,000 |
$25 |
$125,000 |
$25,000 |
625,000,000 |
|
1.1.2 |
Software test plans |
Pages |
500 |
$400 |
$200,000 |
$10,000 |
100,000,000 |
|
1.1.3 |
Software requirements |
Numbered items |
800 |
$100 |
$80,000 |
$12,000 |
144,000,000 |
|
1.2.1 |
Tested module |
Unit tests |
2,000 |
$100 |
$200,000 |
$30,000 |
900,000,000 |
|
1.2.2 |
Integrated module |
Integration points |
1,800 |
$50 |
$90,000 |
$3,500 |
12,250,000 |
|
1.3.1 |
Training manuals |
Pages |
800 |
$400 |
$320,000 |
$4,000 |
16,000,000 |
|
1.3.2 |
Training delivery |
Students |
900 |
$500 |
$450,000 |
$5,000 |
25,000,000 |
|
Totals: |
$1,465,000 |
1,822,250,000 |
|||||
|
Average deliverable from model = $1,465,000/7 = $209,286 Variance, σ 2 = 1,822,250,000/7 = 260,321,429 Standard deviation, σ = √ 260.321 ,429 = $16,134 |
|||||||
|
Confidence calculations: Standard deviation of total expected value = √ (1 ,822,250,000) = $42,687 50% confidence: WBS total ≤ $1 ,465,000 [*] 68% confidence: WBS total ≤ $1,465,000 + $42,687 = $1,507,687 |
|||||||
|
[*] Assumes approximately Normal distribution of WBS summation with mean = $1 ,465,000 and σ = $42,687. |
|||||||
[12] A current listing of some of the prominent sources of information about parametric estimating can be found in "Appendix E, Listing of WEB Sites for Professional Societies, Educational Institutions, and Supplementary Information," of the Joint Industry/Government "Parametric Estimating Handbook," Second Edition, 1999, sponsored by the Department of Defense. Among the listings found in Appendix E are those for the American Society of Professional Estimators, International Society of Parametric Analysis, and the Society of Cost Estimating and Analysis.