Objective 6: Improve Future Project Performance Through Lessons Learned

Objective 6: Improve Future Project Performance Through Lessons Learned

At the end of each project, it is advisable to spend some time analyzing and documenting what worked well and what didn't. What refinements would you recommend for your process or development environment? What are other lessons learned? This is often done in a post-mortem assessment. Based on the results, you update your RUP development case and improve your development environment to reflect the lessons learned.

You should also determine whether any work can be reused for other projects. If so, make sure to remove any sensitive data and store the reusable assets in such a way that they can easily be found and used by other teams .