As a first step in the development of the product deliverable's Installation Rollout Plan, ensure that the Core Team conducts a review of the interdependencies that might exist among the hardware, software, and networking facilities intended to be used by the system. Finalize the sequence in which these hardware, software, and networking facilities will be installed at each specific site. Provide a detailed estimate of the time it should take to install each of them, along with the expected delivery and installation dates.
Special care should be given to subtle dependencies that might exist, such as the following:
Hardware-to-hardware dependencies
Software-to-software dependencies
Network-to-network dependencies
Hardware-to-software dependencies