The Budget at Completion (BAC) is the sum of the budget for each phase of your project. This is the estimated grand total of your project. If a project manager breaks down a project into phases, and she should, then each phase can be reflected with a dollar amount that needs to be allotted to that phase. The benefit of this approach is that a company does not need to allot all of the BAC at the project s conception , but rather the initial amount required to set the project in motion, and an amount as each phase is completed.
The primary advantage of this approach is that an entity can continue to use the capital earmarked for the project until the next phase of the project is ready to proceed. A secondary advantage of the BAC is that it allows everyone involved in the project to examine the costs of each phase of the project and then its grand total. So rather than seeing Server upgrade costs: $25,128, management sees this:
Phase 1 | Start Date | Costs |
---|---|---|
Server 1 | November 3 | $4578 |
Server 2 | November 3 | $4578 |
Phase 1 total | $9156 | |
Phase 2 | Start Date | Costs |
Initiate clustering servers | November 10 | $6526 |
Install switch | November 12 | $1592 |
Phase 2 Total | $8118 | |
Phase 3 | Start Date | Costs |
Add RAID 5 tower | November 17 | $7854 |
Test and document | November 19 | $0 |
Phase 3 Total | $7854 | |
Phase 4 | Start Date | Costs |
Migrate data from old servers to new (performed at night) | November 21 |
|
Put servers into production | November 22 |
|
Phase 4 Total |
| |
Budget at Completion | $25,128 |
As you can see, this approach to budgeting allows all parties to get a sense of what each phase will cost, when the monies will need to be allocated (in advance of the implementation date, of course), and the total cost of the project. This cash flow approach to project management creates a cooperation between the project manager, the project customer, and management. The project manager should include phases that do not require any outlay of cash. In some situations, you may be required to add the number of hours estimated to complete each phase of the project to factor in the cost of an employee s or a consultant s time. The preceding sample only shows the hardware expense.