AKA | Planning Schedule |
Classification | Planning/Presenting (PP) |
A milestones chart displays all activities (milestones) and their corresponding start and completion dates. It is used to manage and monitor a project and can serve as a supporting document when attached to a project status report.
To plan and schedule project activities.
To track and monitor the progress of a project.
To aid project status reporting.
Select and define problem or opportunity | |
Identify and analyze causes or potential change | |
→ | Develop and plan possible solutions or change |
→ | Implement and evaluate solution or change |
Measure and report solution or change results | |
Recognize and reward team efforts |
Research/statistics | |
Creativity/innovation | |
Engineering | |
1 | Project management |
Manufacturing | |
Marketing/sales | |
3 | Administration/documentation |
Servicing/support | |
Customer/quality metrics | |
2 | Change management |
before
Deployment Chart (Down-Across)
Action Plan
Countermeasures Matrix
Project Planning Log
Activity analysis
after
Major Program Status
Monthly Assessment Schedule
Objectives Matrix (OMAX)
What-If Analysis
Presentation
Legend: complete
incomplete
Optional: Include a column to provide space for listing who or which team has responsibility for completing each activity.
STEP 1 The team first identifies all major activities of the project to be scheduled.
STEP 2 The team constructs a milestones chart and lists all identified activities in the order of completion. See example Poster Development Process.
STEP 3 The team estimates the time required to complete each activity and assigns a completion date to each.
STEP 4 Next, the team draws a horizontal bar for each activity, placing the bar in accordance with start and completion dates in sequential order along the milestones chart, as shown in the example.
STEP 5 The team then checks all information and dates the chart.