| < Day Day Up > |
Identifying Resource Overallocations
Project alerts you when resources are overallocated by highlighting them in any view that displays a resource table. For example, the Resource Sheet, Resource Usage, and Resource Allocation views all highlight overallocated resource
Figure 11.1. Views that display resource tables highlight the names of overallocated resources in red (shown here in bold).
NOTE
By default Project uses red text to highlight overallocated resources. Because that
NOTE You can modify the format for overallocated resources in any resource table by choosing Format, Text Styles to display the Text Styles dialog box. In the Item to Change box, select Overallocated Resources from the drop-down list. Use the other controls in the dialog box to create the style you want. When you're finished, click OK to implement the change.
Recall from Table 11.2 that in this example, the overallocation is due to more work being scheduled in a given time period than the resource is allowed to work (based on the availability defined by the maximum available units for the given time period and the working hours on the resource calendar). The cause of the
Figure 11.1 shows the Resource Sheet view with both the Peak and Overallocated fields displayed to the right of the Max Units field. The Max Units field displays the maximum units for the current date and is taken from the Units column of the Resource Availability table in the Resource Information dialog box.
TIP
The current date is normally determined by the computer's internal clock, but you can set the current date to any date. To do so,
The column for Peak in Figure 11.1 shows the peak units for the life of the project; the value displayed is the largest amount of simultaneously assigned units (the peak resource requirement) at any time in the project. Thus, the peak of 300% for Scott Adams means that at some point during the project, Scott's simultaneous assignments total 300% units. Mary Logan, on the other hand, is never required to provide more than 40% units at any time during the project. Three of the first four resources in Figure 11.1 are flagged as being overallocated because the Peak value exceeds the Max Units value. If the Overallocated field were not displayed, you would still know that these resources were overallocated because of the highlight used for the overallocated resources.
NOTE Sometimes you might find that a resource appears in red even though its max units value is greater than its peak. The peak value (and the overallocation) occurs at a different time period from the current date, at a time when the maximum units value is lower than the peak units.
In most cases, you need to reconcile overallocations because the schedule indicates that the resource can't possibly do what he or she is scheduled to do. You
Sometimes you can regard overallocation as a mere technicality that's simply a product of the way Project calculates schedules. For example, suppose a regular
To help you focus only on overallocation cases that you think really
You can choose the sensitivity setting for Project to use when evaluating overallocations in the Resource Leveling dialog box. Choose Tools, Level Resources, and select the setting in the box labeled Look for Overallocations on a Basis. The choices are Minute by Minute, Hour by Hour, Day by Day, Week by Week, and Month by Month. If you choose the Hour by Hour sensitivity setting (which means assigned work must be completed within the assigned hour), Project displays the Leveling indicator that you see in Figure 11.1. But if you choose the Day by Day setting, there is no indicator because the work will be completed within the assigned day. Table 11.2 shows an example where Scott Adams is overallocated for the day on a Thursday, but his workload for the week is fine. If you are content to let Scott manage the conflict by pushing back his Task C work until Friday, after he has finished Task B, the sensitivity setting can be defined as Week by Week, and there would be no Leveling indicator. All resources with any overallocation appear highlighted in resource tables, but if you don't see the Leveling indicator, the overallocation is acceptable within the boundaries of the leveling sensitivity setting.
TIP You can rest the mouse pointer over the Leveling indicator to see the time period covered by the current sensitivity setting. This is quicker than opening the Resource Leveling dialog box, where the leveling sensitivity is defined.
NOTE If a worker reschedules a critical task (that is, a task whose delay will delay the completion of the project), there are consequences to the finish date of the project. For this reason, you do not want to select an overly long sensitivity setting.
In Figure 11.1 the resource names Scott Adams, Mel Lloyd, and Howard Thompson are highlighted, to
Figure 11.2 shows the same resources in the Resource Usage view. In Figure 11.2 you can see the ScreenTip for the Leveling indicator
Figure 11.2. The Leveling indicator appears in the Indicators column in resource views that have tables, such as the Resource Usage view shown here.
Instead of emphasizing the resource definition fields, the Resource Usage view emphasizes a
Mel Lloyd is overallocated because his max units value for the period shown is 100% and he is assigned for 200% units on Tuesday. He does not have a Leveling indicator because the leveling sensitivity setting is Week by Week, and Mel has fewer than 40 hours of assigned work for the week. Although Mel is overallocated on Tuesday, his assignment does not need leveling because he can do the weekly work he has been assigned. Howard Thompson, on the other hand, has far more than 40 hours of work assigned during the week; therefore, on a Week by Week basis, his assignments need to be leveled. Viewing Resource Overallocations
To identify all the overallocated resources by name, you need to use one of the three resource views that display a table: the Resource Sheet view, the Resource Usage view, or the Resource Allocation view. Figure 11.1 shows the Resource Sheet view, and Figure 11.2 shows the Resource Usage view. The Resource Allocation view includes the Resource Usage view and is discussed more in later sections of this chapter. If a resource is overallocated during any period in the life of the project, the resource
Filtering Overallocated Resources
If a resource list is
Figure 11.3. Applying the Overallocated Resources filter
|
|
|
To apply the Overallocated filter, select the top pane view if you are in a combination view, and choose Overallocated Resources from the Filter tool drop-down list. Or, you can choose Project, Filtered For, Overallocated Resources. Filters can be applied only in the top pane because the bottom pane is already filtered to show details for the selection in the top pane. |
NOTE
In a combination view, the bottom pane always displays a subset of the selected tasks or resources that are highlighted in the upper view.
TIP
If you correct the overallocation problem for a resource that is displayed by a filter, the resource remains in the display until the filter is applied again. This is because the display of filters is not automatically refreshed. You can press Ctrl+F3 to refresh the filtered list.
To remove a filter, choose Project, Filtered For, All Resources, or press the F3 function key.
You must use a resource view with a timescale if you want to see assignment data for each time period or to see exactly when a resource overallocation occurs. The Resource Usage view is a standard view that can display a wealth of assignment information, including timephased details for each time period displayed in the timescale. In addition to listing all the resources and highlighting those that are overallocated, you can display rows indented under each resource for all the resource's assignments (see Figure 11.4). Furthermore, you can display multiple timephased assignment field values for each of the assignments, and you can edit some of the fields directly in the cells of the timescale grid. In Figure 11.4, both the Peak Units and the Work values are displayed for each assignment and summarized for each resource. The
|
|
If you experience problems identifying the specific fields that are displayed in the Resource Usage View,
|
The Resource Usage view in Figure 11.4 shows the individual assignments for Mel Lloyd and Scott Adams. You can click the outline symbol that appears to the left of a resource name to hide or display the assignments for that resource. If some assignments are not displayed, the outline symbol is a plus sign (for example, Howard Thompson and Bill Kirk in Figure 11.4). If the assignments are displayed, the outline symbol is a minus sign (for example, Mel Lloyd and Scott Adams in Figure 11.4). If a resource has no assignments, an outline symbol does not appear next to the resource's name.
|
|
You can also use the Hide Assignments tool on the Formatting toolbar to hide or display the assignments for one or more resources that you have selected. To hide or display all assignments, select one of the column headings (such as Resource Name) to select all the resources and then click the Hide Assignments tool. |
{% if main.adsdop %}{% include 'adsenceinline.tpl' %}{% endif %}
TIP
If you apply a filter (for example, the Overallocated Resources filter) in the Resource Usage view, you can see the assignments for other resources by clicking on the plus symbol that appears to the left of the resource name, in the Resource Name column. If the symbol is a minus symbol, try clicking on it anyway. If it changes to a plus symbol with the first click, you need to click the symbol again to display the assignments for that resource.
For each assignment row in the Resource Usage view, the default display in the cells in the timescale grid is the timephased work for the time period
If any assignment value in a cell in the grid is itself greater than the resource availability for the time period, the assignment value is highlighted (typically in red). For example, if you assigned 200% units of a resource with only 100% max units for that time period, the values in the assignment timephased cells for that assignment would all appear highlighted.
The cells in the rows for the resource name contain the sums of the values in the assignment rows
TIP
|
|
If you see a highlighted value in a cell and want to know exactly when during the period spanned by the cell the overallocation occurred, you can drill down by using the Zoom In tool to view shorter and shorter time periods, until you find the exact time when the overallocation occurred. If there is an overallocation at any time during the period spanned by a cell, Project highlights text in that time period's cells in red, no matter how far you may zoom out to compress the timescale. |
|
|
If you are in the Resource Usage view and have displayed the Resource Management toolbar (choose View, Toolbars, Resource Management), you can use the Go to Next Overallocation tool to find the next time period in which a resource has an overallocation (refer to Figure 11.4). The timescale automatically
|
If you use the Go to Next Overallocation tool in a view that has a task list, such as the Gantt Chart view or the Task Sheet view, the task list scrolls to the first task associated with an overallocation and selects that task. Successive use of the Go to Next Overallocation tool selects other tasks assigned to overallocated resources during the same time period. When all tasks associated with overallocations for that time period have been identified, the Go to Next Overallocation tool identifies the next time period that has an overallocated resource and selects the first associated task for that time period.
If you want to be able to view the overload graphically, you can split the screen and display a combination view with the Resource Graph view in the bottom pane. You do this by going to the Window menu and selecting Split. By default, this displays the Resource Form view in the lower view. To change this, select the lower view to make it the active view and then go to the View menu and select Resource Graph (or select it from the View bar). This allows you to see (by default) peak units for the selected resource highlighted in the upper view (see Figure 11.5). To view other values such as work, right-click over the Resource Graph view and choose an option from the pop-up menu that appears.
The Resource Usage view displays rows for all resources, with their assignments indented beneath them. You can choose different timephased field values to display in the timescale grid. Each timephased field you choose to display has its own rows in the displayone for each resource and one for each resource assignment. For example, if you choose to display four timephased field values, each resource has four summary rows and each assignment has four detail rows. The default timephased value displayed is the Work field, which shows the total hours of assigned work per unit of time.
The display of the timephased details is governed by the Detail Styles and the Details commands on the Format menu. The Details command is a short selection menu of timephased fields to display or remove from the display. All fields that are currently displayed are listed on the Details menu, with a check mark next to each field name. You can click the field to remove it from the display. The Details menu also contains a standard list of fields that you can add to the display by clicking. The list of fields to be included in this standard list is governed by the Detail Styles dialog box.
To remove a timephased field from the display, or to display one of the fields on the standard selection menu, choose Format, Details and click the field you want to add to or remove from the display. Or, you can just right-click over the timescale grid to display the Details shortcut menu, which includes the selection list as well as the command to open the Detail Styles dialog box (see Figure 11.6).
If you need to manage the timescale units,
see
"Formatting Timescales,"
p. 785
.
Microsoft Project 2003 includes SmartTags to explain project scheduling engine calculations and
Resource assignment
Edits to start and finish dates
Edits to work, units, or duration
Deletions in the Name column
You can
When you are editing fields in the Resource Usage grid, the scheduling behavior is largely dictated by whether the task type is Fixed Units, Fixed Work, or Fixed Duration and also whether the task is effort-driven and whether there are multiple resources or a single resource assigned to a task.
For a more detailed explanation of task types and effort-driven scheduling,
see
Chapter 9, "Understanding Resource Scheduling,"
p. 321
.
To display the Detail Styles dialog box, you choose Format, Detail Styles (see Figure 11.8). You can also right-click over the timephased grid and choose Detail Styles from the shortcut menu.
The Usage Details tab of the Detail Styles dialog box contains a full list of all the timephased assignment fields that can be displayed in the view. If the fields are already displayed in the view, they are listed in the Show These Fields list on the right; otherwise, they appear in the Available Fields list on the left. You can select a field from either list to define its formatting or to assign it a place on the Details menu.
The list of timephased fields includes a wide range of actual, baseline, and scheduled values for work and for cost, as well as availability and assigned values for units and work. Here is a list of the different fields:
The cost fields include Actual Cost, Baseline Cost, (scheduled) Cost, Cumulative (scheduled) Cost, and the earned value fields (ACWP, BCWP, BCWS, CV, SV, CPI, SPI, SVP, CVP), plus the Custom Baseline Cost fields 1 through 10.
The work fields include Actual Work, Actual Overtime Work, Baseline Work, (scheduled) Work, (scheduled) Regular Work, (scheduled) Overtime Work, Cumulative (scheduled) Work, Work Availability, Remaining Availability, Overallocation, and Percent Allocation (that is, the percentage of available work that is assigned already), plus all the Custom Baseline Work fields 1 through to 10.
Units fields include Peak Units and Unit Availability.
Other fields include Percent Complete and Cumulative Percent Complete.
The list of fields also includes the entries All Resource Rows and All Assignment Rows. These are not fields, but they are included so that you can define separate formatting for the resource rows and assignment rows in the grid.
To add a timephased field to the standard selection list displayed by the Format Details command, select the field (whether it's in the Available Fields list or in the Show These Fields list) and click the Show in Menu check box. Note that this does not display the field; it just adds the field to the standard list in the Details menu.
To display a field that is not currently in the Show These Fields list, select the field in the Available Fields list and click the Show button. The field is added to the Details selection menu until you choose not to display it in the timescale grid (unless its Show in Menu check box has been filled, in which case it remains on the Details menu).
To move a field that is currently in the Show These Fields list back to the Available Fields list, select the field and click the Hide button.
The order of the fields listed in the Show These Fields list is the order in which their rows appear in the grid. You can change the order by using the Move arrows: You select a field name and move it up or down in the list with the arrows.
You can define distinguishing formats for individual timephased fields in the resource summary rows, but the format you choose is not applied to a field's rows for assignments. To change the display characteristics of a resource field row, click the field (in whichever list it appears) and click the Change Font button to select a different font. Select the Cell Background drop-down list to change the color of the row of cells or the Pattern drop-down box to change the fill pattern for the cells in that row. The selected format remains defined for the field, no matter which list it appears in.
TIP
If you design special formats for the Resource Usage view and want to use those format settings for all projects, you can use the Organizer to copy the view into other projects and into the Global template for all new projects.
You can assign distinct formats to all resource rows or to all assignment rows. Assignment rows can have a different background to distinguish them from the resource rows in the grid. To define a general font or background for the assignment rows or for the resource rows, select the All Assignment Rows entry or the All Resource Rows entry (in whichever list it appears) and use the Change Font button, the Cell Background drop-down list, or the Pattern drop-down list to define the format. To apply the format, you move the All Assignment Rows or the All Resource Rows entry to the Show These Fields list. If you apply a special format to All Resource Rows, it
If you want individual fields to retain their own formatting, you need to remove the All Assignment Rows entry from the right-hand list in the dialog box. Using the same mechanism, you can have all resource rows adopt the same formatting by adding the All Resource Rows option to the list on the right-hand side of the dialog box.
The Usage Properties tab of the Detail Styles dialog box controls the display of row titles in the grid and the alignment of data within the cells (see Figure 11.9). In this tab you can do the following:
Use the Align Details Data drop-down list to select Right, Left, or Center alignment of timephased data within the grid cells.
Select Yes or No in the Display Details Header Column list box to display row headers for each assignment field row. Without these headers, you cannot tell what the value display represents.
|
|
If the headers don't appear on your screen for the detail rows in the timephased data, see "Displaying Detail Headers" in the "Troubleshooting" section at the end of this chapter. |
Select the Repeat Details Header on All Assignment Rows check box to display the headers on every row in the display, for resource and assignment rows alike. Leave the check box empty if you want the row headers to appear next to the resource rows but not for each assignment row.
Select the Display Short Detail Header Names check box to use shorter names for the detail headers. Leave the check box empty to use the long names.
| < Day Day Up > |