The solution to Exercise 3b is as follows :

Term

Value

Budget at Completion

$550,000.00

Percent Complete

40%

Planned Value

$220,000.00

Actual Costs

$225,000.00

Earned Value

$220,000.00

Cost Variance

$ (5,000.00)

Schedule Variance

$ -

Cost Performance Index

0.98

Schedule Performance Index

1.00

Estimate at Completion

$562,500.00

Estimate to Complete

$337,500.00

To Complete Performance Index

0.98




IT Project Management
IT Project Management: On Track from Start to Finish, Third Edition
ISBN: 0071700439
EAN: 2147483647
Year: 2004
Pages: 195

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net