Appendix N: Checklists for Pilot Projects


The following is an example process template that, although textual, is written very to-the-point. For more information, see Chapter 16.

Requirements Management Process

Action

Responsibility

Obtain work request from the customer

SM, PM

Review work request

PM

Create initial budget/estimates/schedule

PM

Initial planning

PM, project team

High-level requirements

PM, project team, customer

Risk identification and documentation

PM

Requirements spec draft

PM, project team

Technical review

PM, project team, QA

Customer review

Customer

Refine requirements

PM, project team, customer

Create requirements traceability matrix (RTM)

PM, project team

Review requirements and RTM

PM, customer, project team, QA

Review/update risks

PM

Update estimates and schedules

PM

Review requirements and schedules and estimates

PM, project team, QA, customer

Requirements spec final

PM, analysts

Approvals and sign-offs

Customer, QA, PM, SM, EPG

Baseline requirements spec

PM, CCB, EPG

Assess, track, and incorporate changes

PM, CCB, QA, EPG, customer, project team




Interpreting the CMMI(c) A Process Improvement Approach
Interpreting the CMMI (R): A Process Improvement Approach, Second Edition
ISBN: 142006052X
EAN: 2147483647
Year: 2005
Pages: 205

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net