Working with Progress Lines

     

Progress lines give project managers a quick visual display of the state of the status of each of the tasks in their project. If the vertical line drawn at the date specified diverts to the left for a task, that task has not been updated up to the status date. This section shows you how to insert and format progress lines.

Displaying a Progress Line at the Status Date

graphics/one_icon.jpg Right-click in a blank area of the Gantt Chart view.

graphics/two_icon.jpg Select Progress Lines from the menu.

graphics/three_icon.jpg Check the option Always Display Current Progress Line.

graphics/four_icon.jpg Choose whether the progress line should be drawn at the project status date or the current date.

graphics/five_icon.jpg Click OK to display the progress line.

graphics/11inf27.jpg

Displaying Recurring Progress Lines

graphics/one_icon.jpg Right-click in a blank area of the Gantt Chart view.

graphics/two_icon.jpg Select Progress Lines from the menu.

graphics/three_icon.jpg Select this option to display the recurring progress lines.

graphics/four_icon.jpg Choose the interval for the lines to be displayed.

graphics/five_icon.jpg Define the recurrence pattern.

graphics/six_icon.jpg Click OK to display the recurring progress lines.

graphics/11inf28.jpg


Show Me. Microsoft Office Project 2003
Show Me Microsoft Office Project 2003