THE ACIC MEASUREMENT AND TRACKING PLAN

7.4 THE ACIC MEASUREMENT AND TRACKING PLAN

In the ACIC project the standard metrics of size, effort, defect, and schedule were measured. The plan was to use line counters for size, the WAR system for effort, a defect control system called BugsBunny for defects, and MSP for schedule.

The project manager planned to use MSP for activity tracking and to have regular meetings to monitor the status of the various activities. The issues were classified into onsite, customer, business manager, and support services and tracked separately. Customer feedback complaints as well as compliments was logged.

Status reports were sent weekly to the business manager as well as the customer. The deviation limits for the first five milestones were set to 10% for effort and schedule and 20% for defects. For the rest of the milestones, the limits were set to 5% for effort and schedule and 20% for defects. Milestone reports were also sent to the business manager and the customer.

The final outcome of tracking and measurement planning is included in the project management plan of the ACIC project, given in Chapter 8.

 



Software Project Management in Practice
Linux Annoyances for Geeks: Getting the Most Flexible System in the World Just the Way You Want It
ISBN: 0596008015
EAN: 2147483647
Year: 2005
Pages: 83
Authors: Michael Jang

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net