Chapter 6. Risk Management

Chapter 6. Risk Management

A software project is a complex undertaking. Unforeseen events may have an adverse impact on a project's cost, schedule, or quality. Risk management is an attempt to minimize the chances of failure caused by unplanned events. The aim of risk management is not to avoid getting into projects that have risks but rather to minimize the impact of risks in the projects that are undertaken. In words of N.R. Narayana Murthy, CEO of Infosys, "Anything worth doing has risks. The challenge for a leader is not to avoid them but effectively manage them through de-risking strategies." Improper risk management, the result mainly of the common disease of optimism, is the source of many project failures.

Vasu was designated as the project manager of a large project undertaken by a prestigious multinational corporation. The project was to build parts of an integrated system for worldwide human resource management. For the final system, the software Vasu's team was to develop had to be integrated with a system that was being developed by another vendor. For use in the project, the customer provided proprietary tools whose new version was to be released shortly. Vasu's team of 35 people had a little more than a year to deliver the software. Although the project employed a good team and the project manager made reasonable estimates, the system was commissioned six months late, with Infosys footing the bill for the 50% effort escalation in the project.

Why did this project fail? There are two clear reasons. First, the software being developed by the other vendor was not delivered on time, and the interfaces provided to Vasu's team kept changing. Second, a new version of the customer's tools was released during development, requiring the software to be ported to this new version.

Both of these events are clear instances of risks that were not managed properly. These risks were evident at the start, although, as with any risk, it was not certain that they would materialize. When the project started, the project manager, his business manager, and the customer hoped that the other vendor would deliver its software on time and that the new version of the tools would not affect the project.

In hindsight, Vasu thinks that if a steering team comprising the project managers of the two projects and a customer representative had been set up to ensure proper coordination between the two projects and their deliveries, delays could have been minimized. For the second risk, he thinks that the software should have been developed first with the earlier version of the tools. Then it should have been migrated to the new versions later through a separate project. The first solution would have required minimal extra effort, and the cost implications are minor. The second one has clear cost implications for the customer. Perhaps to avoid displeasing the customer, this risk was not highlighted and its mitigation not planned.

This chapter discusses the general concept of risks and risk management before turning to Infosys's approach for risk assessment and risk control the two major steps in risk management.

 



Software Project Management in Practice
Linux Annoyances for Geeks: Getting the Most Flexible System in the World Just the Way You Want It
ISBN: 0596008015
EAN: 2147483647
Year: 2005
Pages: 83
Authors: Michael Jang

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net