SUMMARY

4.4 SUMMARY

The basic goal of effort estimation is to generate reasonable estimates that will work most of the time. The following are key lessons from the estimation and scheduling approaches used at Infosys:

         Use past data to estimate. Prefer data from similar projects to general process capability data. Use a model to estimate, but allow flexibility for adjusting estimates to accommodate project-specific factors.

         Employ different models in different situations. Bottom-up estimation is effective when project details are known. Use the top-down approach if you can estimate the size and productivity, and the use case approach when using a use-case-based development approach.

Table 4.9. Portion of the Detailed Schedule for the ACIC Project

Module

Program

Activity Code

Task

Duration (days)

Effort (days)

Start Date

End Date

% Complete

Resource Initials

PRS

Requirements

8.89 days

1.33 days

7/10/00 8:00

7/21/00 17:00

100%

BB, BJ

PDDRV

Design review

1 day

0.9 days

7/11/00 8:00

7/12/00 9:00

100%

BB, BJ, SB

PDDRW

Rework after design review

1 day

0.8 days

7/12/00 8:00

7/13/00 9:00

100%

BJ, SB

History

UC17

PCD

View history of party details, UC17

2.67 days

1.87 days

7/10/00 8:00

7/12/00 17:00

100%

HP

History

UC7

PCDRV

Code walkthrough, UC17

0.89 days

0.27 days

7/14/00 8:00

7/14/00 17:00

100%

BJ, DD

History

UC19

PCDRV

Code walkthrough, UC19

0.89 days

0.27 days

7/14/00 8:00

7/14/00 17:00

100%

BJ, DD

PCDRW

Rework after code walkthrough

0.89 days

2.49 days

7/17/00 8:00

7/17/00 17:00

100%

DD, SB, HP, BJ

PUTRW

Rework after testing

0.89 days

0.71 days

7/18/00 8:00

7/18/00 17:00

100%

BJ, SB, DD, HP

History

UC17

PUT

Test, UC 17

0.89 days

0.62 days

7/18/00 8:00

7/18/00 17:00

100%

SB

History

UC19

PUT

Test, UC 19

0.89 days

0.62 days

7/18/00 8:00

7/18/00 17:00

100%

HP

Configuration

PCM

Reconciliation

0.89 days

2.49 days

7/19/00 8:00

7/19/00 17:00

100%

BJ, DD, SB, HP

Management

PPMPT

Scheduling and tracking

7.11 days

2.13 days

7/10/00 8:00

7/19/00 17:00

100%

BB

Quality

PPMPT

Milestone analysis

0.89 days

0.62 days

7/19/00 8:00

7/19/00 17:00

100%

BB

         For the overall schedule and the high-level milestones, use the existing flexibility to meet proposed dates. Once the overall schedule and milestones are fixed, determine the resource requirement for each phase from the phase-wise effort estimate.

         Detailed scheduling is a dynamic task; take into account people issues while assigning tasks. It is not necessary to completely refine the schedule at the start. You can develop details for the tasks in the overall schedule as the need arises.

         The detailed schedule forms the planned activity list for the project. Capture all activities planned in the project in this document and use it later to track activities.

From the CMM standpoint, a proper effort and schedule estimation method is a requirement for the Software Project Planning KPA at level 2. At level 4, the use of past data for estimation is expected to increase, and the goals of the Quantitative Process Management KPA cannot be satisfied unless a good estimation procedure is in place. The Integrated Software Management KPA at level 3 also assumes that good estimation methods are available to projects for planning. The requirements related to estimation in these KPAs are satisfied by methods discussed in this chapter.

 



Software Project Management in Practice
Linux Annoyances for Geeks: Getting the Most Flexible System in the World Just the Way You Want It
ISBN: 0596008015
EAN: 2147483647
Year: 2005
Pages: 83
Authors: Michael Jang

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net