The solution to Exercise 1 can be found in the file Completed Exercise One, which appears on the CD-ROM in the CH8 folder.
The solution to Exercise 2 can be found in the file Completed Exercise Two, which appears on the CD-ROM in the CH8 folder.
The solution to Exercise 3a can be found in the file Completed Exercise Three, which appears on the CD-ROM in the CH8 folder.
The solution to Exercise 3b is as follows :
Term | Value |
---|---|
Budget at Completion | $550,000.00 |
Percent Complete | 40% |
Planned Value | $220,000.00 |
Actual Costs | $225,000.00 |
Earned Value | $220,000.00 |
Cost Variance | $ (5,000.00) |
Schedule Variance | $ - |
Cost Performance Index | 0.98 |
Schedule Performance Index | 1.00 |
Estimate at Completion | $562,500.00 |
Estimate to Complete | $337,500.00 |
To Complete Performance Index | 0.98 |