F

 < Day Day Up > 



Fast Tracking

Doing activities in parallel that are normally done sequentially.

Feedback

A response, question for clarification, or other confirmation of having received a sent message.

Finish No Earlier Than (FNET)

This somewhat unusual constraint requires the activity to be in motion up until the predetermined date.

Finish No Later Than (FNLT)

This constraint requires the project or activity to finish by a predetermined date.

Finish-to-Finish

This relationship means Task A must complete before Task B can complete. Ideally, two tasks must finish at exactly the same time, but this is not always the case.

Finish-to-Start

This relationship means Task A must complete before Task B can begin. This is the most common relationship.

Fixed-price contracts

Fixed-Price Contracts are also known as Firm-Fixed-Price and Lump-Sum contracts. These contracts have a pre-set price that the vendor is obligated to perform the work or provide materials for the agreed price

Float

The amount of time a task can be delayed without delaying the project completion. Technically, there are three different types of float: Free float is the total time a single activity can be delayed without delaying the early start of any successor activities. Total float is the total time an activity can be delayed without delaying project completion. Project float is the total time the project can be delayed without passing the customer's expected completion date.

Flowchart

A chart that illustrates how the parts of a system occur in sequence.

Force majeure

A powerful and unexpected event, such as a hurricane or other disaster.

Forcing

A conflict resolution method where one person dominates or forces their point of view or solution to a conflict.

Forecasting

An educated estimate of how long the project will take to complete. Can also refer to how much the project may cost to complete.

Formal power

The type of power where the project manager has been assigned by senior management to be in charge of the project.

Fragnets (also called subnets)

Portions of a network diagram that branch off the project and are not on the critical path.

Free float

The total time a single activity can be delayed without delaying the early start of any successor activities.

Functional structure

An organizational structure that groups staff members according to their area of expertise (sales, marketing, construction, and so on). Functional structures require the project team members to report directly to the functional manager. In this type of structure, the project manager's authority and decision-making ability is less than the functional manager's.

Future value

A formula to calculate the future value of present money.



 < Day Day Up > 



PMP Project Management Professional Study Guide
PMP Project Management Professional Study Guide, Third Edition (Certification Press)
ISBN: 0071626735
EAN: 2147483647
Year: 2004
Pages: 209

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net