Flylib.com
List of Figures
Previous page
Table of content
Next page
Chapter 1: Starting an Advanced Project Successfully
Figure 1.1: Business plan production schedule
Figure 1.2: Work agreement
Chapter 2: Building the Macro Plan
Figure 2.1: Interview template
Figure 2.2: Target plan creation
Figure 2.3: Distributing the costs
Figure 2.4(a) Contingency calculation
Figure 2.4(b) Contingency weight attribution
Figure 2.5: Macro plan
Figure 2.6: WBS first pass
Figure 2.7: Gradual work ramp-up in all areas
Figure 2.8: Life cycle related to tasks
Figure 2.9: Work package resource levels
Figure 2.10: WBS outline
Figure 2.11: Work package detailed description
Chapter 3: Building the Detailed Project Plan
Figure 3.1: High-level requirement derivation from work packages
Figure 3.2: High-level requirement number scheme
Figure 3.3: HLRs related to DLRs
Figure 3.4: HLRs and life cycles
Figure 3.5: Requirements gathering form
Figure 3.6: DLR gathering form
Figure 3.7: Change control form
Figure 3.8: Identification of Gantt chart components
Figure 3.9(a) Finish to start
Figure 3.9(b) Start to start
Figure 3.9(c) Finish to finish
Figure 3.10(a) Finish to start with lag
Figure 3.10(b) Start to start with lag
Figure 3.11: Gantt chart with inter-dependencies and float
Figure 3.12: Gantt chart with contingency
Chapter 4: Building the Project Team
Figure 4.1: Project organization chart
Figure 4.2: Team member task agreement form
Chapter 5: How to Run the Project on a Day-to-Day Basis
Figure 5.1: Fixed price contract equation
Figure 5.2: Royalty equation
Figure 5.3: Royalty equation graph
Figure 5.4: Supplier risk
Figure 5.5: Waterfall model
Figure 5.6: Time box
Figure 5.7: Rolling wave
Figure 5.8: Standards introduction
Figure 5.9: Organization swinging between approaches
Chapter 6: Monitoring and Controlling the Project
Figure 6.1: Spectrum of projects
Figure 6.2: Management flexibility needed
Figure 6.3: Uncertainty funnel
Figure 6.4: DLR volumes
Figure 6.5: Rate of change
Figure 6.6: Value analysis
Figure 6.7: Value analysis boundaries
Figure 6.8: Cascade reporting
Figure 6.9: Scope reduction
Figure 6.10: Cumulative change requests
Figure 6.11: WBS outline
Figure 6.12: Cost reporting
Figure 6.13: Cost reporting tolerance zones
Figure 6.14: Management summary report
Figure 6-15: High-level schedule hiding problems underneath
Chapter 7: Successfully Shutting Down the Project
Figure 7.1: Maintenance of deliverables
Previous page
Table of content
Next page
Advanced Project Management: A Complete Guide to the Key Processes, Models and Techniques
ISBN: 0749449837
EAN: 2147483647
Year: 2007
Pages: 69
Authors:
Alan D. Orr
BUY ON AMAZON
CISSP Exam Cram 2
Introduction
Network Models and Standards
Network Equipment
Fax Control
Exam Prep Questions
MySQL Clustering
Before You Begin with MySQL Cluster
Backup and Recovery
MySQL Cluster Performance
Displaying the Status of the Cluster/Controlling Nodes
Logging Commands
Information Dashboard Design: The Effective Visual Communication of Data
Arranging the Data Poorly
Gestalt Principles of Visual Perception
Organize the Information to Support Its Meaning and Use
Maintain Consistency for Quick and Accurate Interpretation
Sample Marketing Analysis Dashboard
Microsoft WSH and VBScript Programming for the Absolute Beginner
VBScript Basics
Constants, Variables, and Arrays
Conditional Logic
Processing Collections of Data
Appendix A WSH Administrative Scripting
Oracle SQL*Plus: The Definitive Guide (Definitive Guides)
Executing Scripts
Unions
Validating and Parsing User Input
Using EXPLAIN PLAN
Section B.1. Formatting Numbers
Special Edition Using FileMaker 8
Assigning Field Options
Multiwindow Interfaces
Accessing FileMaker Data Using ODBC and JDBC
FileMaker Extra: Publishing Related Data
FileMaker Extra: Soliant Development Standards
flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net
Privacy policy
This website uses cookies. Click
here
to find out more.
Accept cookies