Reviewing the Impact of Changes


After you adjust your project plan to bring in your finish date, reduce costs, or balance your workload, check that you've succeeded in hitting your target. Look at the Project Statistics dialog box or review the project summary task, as described earlier in this chapter.

When you're content with one aspect of your project plan, such as your finish date, it's a good idea to see whether you've "broken" any other aspect of your project, such as your costs. Keep an eye on your finish date, total project costs, and resource allocation while always remembering your highest priority of the three. Continue to adjust and balance until all aspects of the project are just the way you want them.