Description : It is very important to redo Phase III after the supplier has delivered and set up the machine in your plant. This will give you a chance to make sure that the machine is set up the same as at the supplier's shop and that it is set up correctly.
Objectives:
Confirm correct machine setup.
Reconfirm Phase III conclusions with supplier still in the plant.
Final-step participants include the
Machine acceptance team
Supplier of the machine
Production operator of the machine
Production engineers
Repeat Phase III study: If Phase III results are not replicated (i.e., C pk >1.33), have supplier find out why the machine is not set up correctly.