AKA | Work Breakdown Diagram |
Classification | Planning/Presenting (PP) |
A work breakdown structure (WBS) is a necessary division of the overall project into major categories of work. Major categories, in turn, are broken down into more defined, specific elements, and then finally down to a work package level. This process provides project management the ability to schedule, assign resources, and report work package completion status.
To break down a total project's work into definable, manageable, and reportable work packages.
To reduce the complexity of a project so that interrelated activities and work elements can be clearly understood.
To identify work packages and resource requirements, and to schedule for completing project activities.
→ | Select and define problem or opportunity |
→ | Identify and analyze causes or potential change |
→ | Develop and plan possible solutions or change |
Implement and evaluate solution or change | |
Measure and report solution or change results | |
Recognize and reward team efforts |
Research/statistics | |
Creativity/innovation | |
2 | Engineering |
1 | Project management |
Manufacturing | |
Marketing/sales | |
Administration/documentation | |
Servicing/support | |
Customer/quality metrics | |
3 | Change management |
before
Comparison Matrix
Project Prioritization Matrix
Action Plan
Objectives Matrix
Responsibility Matrix
after
Trend Analysis
Gantt Chart
Activity Network Diagram
Program Evaluation and Review Technique (PERT)
Major Program Status
A WBS typically consists of five or more levels of breakdown to reduce a project's scope and complexity:
Level | Description | Designation Example |
1 | Project | 10 |
2 | Category | 10.1 |
3 | Subcategory | 10.1.1 |
4 | Work element | 10.1.1.1 |
5 | Work package | 10.1.1.1.1 |
6 | Deliverables | 10.1.1.1.1.1 |
STEP 1 The first step for a project manager's team is to identify the major categories of work to be completed. See example WBS for Adding an Assembly Line.
STEP 2 A designation or accounting schema is then established to be able to account for or schedule work. The numbering system used is arbitrary—see example shown.
STEP 3 All work categories are broken down into a lower level of detail. This process continues down to the basic work package level. Typically, five or more levels are diagrammed.
STEP 4 The final WBS diagram should reflect all required work and is used as a resource document for the planning and scheduling of the overall project.