Tool 87: Gantt Chart


AKA

Gantt Planning

Classification

Planning/Presenting (pp)

Tool description

A Gantt chart effectively documents the schedule of planned activities, milestone dates, and the assigned responsibility for completing the activities. Used as a project management tool, it tracks and monitors completion of goals, possible delays, and time left to target achievement. Critical milestone dates are placed on horizontal activity bars to enable the comparison of planned to actual performance. It is used as supporting data in a project status report.

Typical application

  • To schedule and monitor sequenced project activities.

  • To determine resource requirements, task responsibility, and time duration of the overall schedule of the project.

  • To manage the completion of a project.

Problem-solving phase

Select and define problem or opportunity

Identify and analyze causes or potential change

Develop and plan possible solutions or change

Implement and evaluate solution or change

Measure and report solution or change results

Recognize and reward team efforts

Typically used by

Research/statistics

Creativity/innovation

Engineering

1

Project management

Manufacturing

Marketing/sales

Administration/documentation

Servicing/support

3

Customer/quality metrics

2

Change management

start sidebar
links to other tools

before

  • Resource Histogram

  • Responsibility Matrix

  • Monthly assessment schedule

  • Work breakdown structure (WBS)

  • Program Evaluation and Review Technique (PERT)

after

  • Basili Data Collection Method

  • Objectives Matrix (OMAX)

  • Action plan

  • Major Program Status

  • Events log

end sidebar

Notes and key points

  • Legend: Various symbols are used. For this example:

    click to expand

  • Optional: To identify activity completed

    click to expand

Step-by-step procedure

  • STEP 1 The team facilitator records all necessary activities of a project on a flip chart. Activities were identified by team participants who represent or have knowledge of the work that needs to be completed.

  • STEP 2 A basic Gantt chart is drawn on a whiteboard with a list of activities ordered by sequence of completion. See example Typical Research Project Activities and Time Frames.

  • STEP 3 The team estimates the time required for each activity. On that basis, an activity completion date (due date) is associated with every listed activity and recorded. Horizontal bars are drawn to represent time duration and the begin/end dates for each activity, as shown in the example.

  • STEP 4 Lastly, ownership (responsibility) is determined or assigned for the completion of each activity.

  • STEP 5 The team checks activities, sequence and duration, makes final revisions, and dates the chart. Once the chart is finalized, it is given to the project manager.

Example of tool application

click to expand




Six Sigma Tool Navigator(c) The Master Guide for Teams
Six Sigma Tool Navigator: The Master Guide for Teams
ISBN: 1563272954
EAN: 2147483647
Year: 2005
Pages: 326

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net