To edit resource assignments’ work values, page 338
1 On the View menu, click Resource Usage.
2 In the Work column, edit the values you want.
To replace one resource with another, page 340
1 On the View menu, click Task Usage.
2 In the Task Name column, select the task for which you want to replace the resource.
3 On the Standard toolbar, click the Assign Resources button.
4 In the Assign Resources dialog box, in the Resource Name column, click the name of the resource you want to replace, and then click Replace.
5 In the Replace Resource dialog box, click the name of the replacement resource, and click OK.
To filter for critical tasks, page 343
On the Project menu, point to Filtered For: All Tasks, and then click Critical.
To enter overtime work values in the Task Form, page 343
1 On the View menu, click Gantt Chart.
2 In the Task Name column, select the task you want.
3 On the Window menu, click Split.
4 Click anywhere in the Task Form. On the Format menu, point to Details, and then click Resource Work.
5 In the Ovt. Work column for the resource to which you want to assign overtime work, enter the number of hours of overtime work you want and then click OK.