To update a baseline, page 289
1 On the Tools menu, point to Tracking, and then click Set Baseline.
2 In the Set Baseline dialog box, select the baseline you want to update.
3 Under For, click either Entire project or Selected tasks.
To enter task-level or assignment-level actual work values, page 291
1 On the View menu, click Task Usage.
2 On the View menu, point to Table: Usage, and then click Work.
3 Enter the actual work values you want for a task or assignment in the Actual column.
To enter daily (or other time period’s) actual work values per task or assignment, page 298
1 On the View menu, click Task Usage.
2 Scroll the timescale to the time period for which you want to record actual work.
3 On the Format menu, point to Details, and click Actual Work.
4 In the timescale grid, enter the task or assignment value you want in the Act. Work field.
To reschedule uncompleted work, page 304
1 On the Tools menu, point to Tracking, and then click Update Project.
2 Click Reschedule uncompleted work to start after, and in the Date box, type or click the date you want.