13 Tracking Progress on Tasks and Assignments


13 Tracking Progress on Tasks and Assignments

To update a baseline, page 289

1 On the Tools menu, point to Tracking, and then click Set Baseline.

2 In the Set Baseline dialog box, select the baseline you want to update.

3 Under For, click either Entire project or Selected tasks.

To enter task-level or assignment-level actual work values, page 291

1 On the View menu, click Task Usage.

2 On the View menu, point to Table: Usage, and then click Work.

3 Enter the actual work values you want for a task or assignment in the Actual column.

To enter daily (or other time period’s) actual work values per task or assignment, page 298

1 On the View menu, click Task Usage.

2 Scroll the timescale to the time period for which you want to record actual work.

3 On the Format menu, point to Details, and click Actual Work.

4 In the timescale grid, enter the task or assignment value you want in the Act. Work field.

To reschedule uncompleted work, page 304

1 On the Tools menu, point to Tracking, and then click Update Project.

2 Click Reschedule uncompleted work to start after, and in the Date box, type or click the date you want.




Microsoft Office Project 2007 Step by Step
MicrosoftВ® Office Project 2007 Step by Step (Step By Step (Microsoft))
ISBN: 0735623058
EAN: 2147483647
Year: 2004
Pages: 247

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net