Range filter, 227
Ratio of cost variance to Budgeted cost of work schedule (CV%), 395
Ratio of the schedule variance (SV%), 393
Recording macros, 373–376
Recurring task, 164–167, 198
Relationship Diagram, 248
Relationships, 48, 98.
See also Dependencies;
and entries for individual relationships
Remaining cost, 210, 318
Reporting project status
examining resource costs, 322–324
examining task costs, 317–322
identifying slipped tasks, 310–317
key to properly communicating status, 309–310
reporting cost variance with spotlight view, 325–328
See also Progress
Reports
defined, 112, 254
exploring, 24–27
formatting and printing, 112–118
formatting and printing plan, 97–118
in global template, 368
printing, 254–257
See also Gantt Chart view;
and entries for specific reports
Reports dialog box, 24, 112
Rescheduling incomplete work, 302–305
Resource allocations
evaluating, 192
examining, overtime, 191–199
leveling overallocated resources, 203–209
Resource Allocation view, 193, 199–203
Resource calendar, 70–73
Resource cost information, 69.
See also Cost resources
Resource costs, 317, 322–324.
See also Task costs;
Variance
Resource details, 279
Resource Graph command, 199
Resource Graph view, 199
Resource Information dialog box, 65, 173–175, 177
Resource leveling, 203–209
Resource Leveling dialog box, 205
Resource Management toolbar, 199
Resource manager, 322
Resource Name field, 64, 167
Resource names, enter, 64
Resource note, 52
Resource overallocations
leveling, 203–209
manually resolving, 199–203
Resource pay rates, entering, 68–69
Resource pool
benefits of, 405
creating, 404–410
creating dedicated, 410
defined, 404
linking new project plans to, 420–422
opening sharer plan and updating, 422–425
updating all plans’ working times in, 417–419
updating resource’s information in, 413–416
viewing assignment details in, 410–412
working with sharer plans and, 419
Resource(s), 332
adjusting working time for individual, 70–73
aspects of, 59
assigning, to task, 83–90
assigning, to tasks, 77–94
defined, 59
documenting, 74
entering multiple pay rates for, 172–174
handling actual from, 457–459
leveling overallocated, 203–209
setting up, 59–74, 176–177
staffing enterprise project with, 443–449
See also Pay rate;
and entries for specific resources
Resource Sheet view, 18–19, 25, 70, 219–220
Resource Substitution Wizard, 443–444
Resource Summary sheet, 27
Resource Usage view
and assignment notes, 183
defined, 19
display Cost Rate Table field, 185, 297
Resource Allocation view, 193–194
timephased grid, 301, 338
work values in timescaled grid, 198
Resource variance, troubleshooting, problems, 337–342
Risks, 464–488, 472
Roll Up Baseline, 289