I


import/export map

A set of specifications for importing specific data to or from Project fields. Project includes several built-in maps, which you can use as they are or modify. Import and export maps are sometimes referred to as data maps.

inflexible constraint

A constraint type that forces a task to begin or end on a certain date. Must Start On (MSO) and Must Finish On (MFO) are both inflexible constraints.

inserted project

A Project plan that is inserted into another Project plan, called a consolidated plan. An inserted project is also known as a subproject.

interim plan

A task’s start and finish values, saved for later comparison. Each Project plan can have, at most, 10 interim plans.




Microsoft Office Project 2007 Step by Step
MicrosoftВ® Office Project 2007 Step by Step (Step By Step (Microsoft))
ISBN: 0735623058
EAN: 2147483647
Year: 2004
Pages: 247