Formatting a Gantt Chart View


You can directly format specific items (a milestone, for example) in a Gantt chart view or use the Gantt Chart Wizard (on the Format menu) to change the look of a Gantt Chart view in limited ways. If you completed Chapter 5, “Formatting and Printing Your Plan,” you worked with the Gantt Chart Wizard. In this section, you will customize specific items, such as Gantt bars and gridlines, in ways that the Gantt Chart Wizard cannot.

Tip 

Remember that several views are Gantt chart views, even though only one view is specifically called the Gantt Chart view. Other Gantt chart views include the Detail Gantt, Leveling Gantt, Multiple Baselines Gantt, and Tracking Gantt. Gantt chart view generally refers to a type of presentation that shows Gantt bars organized along a timescale.

In addition to changing the formatting of objects that appear by default in a Gantt chart view (such as a task’s Gantt bar), you can add or remove objects. For example, it may be useful to compare baseline, interim, and actual plans in a single view. Doing so helps you evaluate the schedule adjustments you have made.

In this exercise, you display the current schedule along with the baseline and the interim plan. (The baseline and the interim plan were previously set in the project plan.) You begin by customizing a copy of the Tracking Gantt chart view.

Be Sure To start Microsoft Office Project 2007 if it’s not already running.

Important 

If you are running Project Professional, you may need to make a one-time adjustment to use the Computer account and to work offline. This ensures that the practice files you work with in this chapter do not affect your Project Server data. For more information, see “Starting Project Professional” on page 11.

Open Parnell Film 16a from the \Documents\Microsoft Press\Project 2007 SBS\Chapter 16 Advanced Formatting folder. You can also access the practice files for this book by clicking Start, All Programs, Microsoft Press, Project 2007 Step by Step and then selecting the chapter folder of the file you want to open.

1. On the File menu, click Save As.

The Save As dialog box appears.

2. In the File name box, type Parnell Film 16, and then click Save.

3. On the View menu, click More Views.

The More Views dialog box appears.

4. On the Views list, click Tracking Gantt, and click the Copy button.

The View Definition dialog box appears.

image from book

5. In the Name box, type Interim Tracking Gantt, and click OK.

The new view is listed in the More Views dialog box.

6. Click the Apply button.

Project displays the new view, which at this point is identical to the Tracking Gantt view. Next, you will customize this new view so that your original Tracking Gantt view will not be altered. You will add the interim plan bars to the view.

7. On the Format menu, click Bar Styles.

The Bar Styles dialog box appears.

Tip 

You can also display this dialog box by double-clicking the background of the chart portion of a Gantt chart view or by right-clicking in the background and selecting Bar Styles in the shortcut menu.

8. Scroll down the list of the bar styles, and in the Name column, click Baseline Split.

9. Click the Insert Row button.

Project inserts a row for a new bar style in the table. Project draws Gantt bars in the order in which they are listed in the Bar Styles dialog box. Inserting a new bar style above the Baseline Split will help ensure that it won’t be obscured by another type of Gantt bar.

10. In the new cell in the Name column, type Interim.

Interim is the name you’ll give to the new task bar that will appear on the chart portion of the view.

Tip 

The names of most task bars will appear in the legend of printed Gantt chart views. If you do not want a task bar name to appear in the legend, type an asterisk (*) at the beginning of the task bar name. For example, if you wanted to prevent Interim from appearing in the legend, you would enter its name here as *Interim. In the Bar Styles dialog box, you can see that the Rolled Up task bar name (among others) is prefaced with an asterisk, so it does not appear in the legend of a printed Gantt chart view.

11. In the same row, click the cell under the Show For Tasks column heading, and then click Normal on the drop-down list.

The Show ForTasks value indicates the type of task the bar will represent (such as a normal task, a summary task, or a milestone) or the status of the task (such as critical or in progress).

Tip 

This is a fairly complex dialog box in Project, but it is extensively documented in online Help. To see Help for this dialog box, click the Help button.

12. Click the cell under the From column heading, and click Start1 on the drop-down list.

13. Click the cell under the To column heading, and then click Finish1 on the drop-down list.

The From and To values represent the start and end points for the bar.

image from book

The Start1 and Finish1 items are the fields in which the first interim plan values were previously set for you in the project plan. The current start date and finish date of each task in the project were saved to these fields when the interim plan was set. If you completed Chapter 13, “Tracking Progress on Tasks and Assignments,” you have already been introduced to interim plans.

You have now instructed Project to display the first interim plan’s start and finish dates as bars. Next, you will specify what these bars should look like.

14. Click the cell under the Row column heading, and click 2 on the drop-down list.

This causes Project to display multiple rows of Gantt bars for each task in the view. Next, focus your attention on the lower half of the Bar Styles dialog box.

15. In the Shape box under the Middle label, click the half-height bar, the third option from the top of the list.

Troubleshooting 

The Bar Styles dialog box is one of several dialog boxes in Project that contains tabs (and is referred to as a tabbed dialog box). If you don’t see the Shape box mentioned in the previous step, verify that the Bars tab is active and not the Text tab.

16. In the Pattern box under the Middle label, click the solid bar, the second option from the top of the list.

17. In the Color box, click Green.

image from book

Because this custom view focuses on the interim plan, next you’ll format the interim bars to include their start and finish dates.

18. In the Bar Styles dialog box, click the Text tab.

19. In the Left box, click Start1 on the drop-down list.

Tip 

You can type a letter in a field name list to go directly to fields that begin with that letter. For example, you can type S to go to the items that begin with S.

20. In the Right box, click Finish1 on the drop-down list.

Selecting these values will cause the Start1 and Finish1 dates to appear on either side of the bar.

image from book

21. Click OK to close the Bar Styles dialog box.

Project displays the interim bars on the Interim Tracking Gantt view. Next, you will get a better look at the Gantt bars.

22. In the Task Name column, click the name of task 6, Select locations.

23. On the Standard toolbar, click the Scroll To Task button. image from book

Project scrolls the view to display the Gantt bars for task 6 and its adjacent tasks.

image from book

Here you can see that the completed task 6 (shown as a solid blue bar at the top of the task row) corresponds exactly to its interim plan bar (the green bar at the bottom of the task row) and that both were scheduled later than the baseline (the patterned gray bar in the middle of the task row). This occurred because, after the baseline was set, changes to the schedule were made that pushed out the scheduled start date of the task. Then the interim plan was saved.

To conclude this exercise, you’ll display horizontal gridlines on the chart portion of the Interim Tracking Gantt view to better distinguish the rows of Gantt bars per task.

24. On the Format menu, click Gridlines.

The Gridlines dialog box appears.

25. In the Line to change box, make sure that Gantt Rows is selected. Then, in the Type box, click the long dashed line, the last option on the list.

image from book

26. Click OK to close the Gridlines dialog box.

Project draws gridlines between task rows in the chart.

image from book

Displaying gridlines like this is a great idea when you print multiple Gantt bars for each task.

Project supports several additional Gantt Chart formatting features than those we’ve worked with in this section. If you wish to explore other formatting options, look at these commands on the Format menu:

  • Timescale-for setting time increments, such as weeks and days, and how non-working time is displayed.

  • Text Styles-for formatting text associated with a specific task type, such as summary task text.

  • Layout-for formatting link lines and Gantt bar visual effects.




Microsoft Office Project 2007 Step by Step
MicrosoftВ® Office Project 2007 Step by Step (Step By Step (Microsoft))
ISBN: 0735623058
EAN: 2147483647
Year: 2004
Pages: 247

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net