Deployment and Implementation


Deployment of Griffith University's WLAN solution was undertaken on a phased basis. This approach allowed the university's IT staff to validate the architecture from a technical and security basis, introduce the services on an incremental basis, ensure that support staff were among the first to familiarize themselves with and benefit from the solution, and finally avoid the "big bang" approach for service introduction.

Careful site surveys were undertaken and cabling was laid before each access point was installed. Finally, each Smart Zone was tested before being launched as a production service.

Deployment Phases

Phase One of the deployment concentrated on IT areas, cafes, outdoor locations, libraries, and learning centers. The areas selected for Phase One were partly defined by the end users (see "Lessons Learned and Recommendations" later) through proactive user surveys and requirements definitions.

Note

Learning centers are "computer labs on steroids," according to Scott. They are specialized areas set aside for student study, research, and educational activity. Griffith University learning centers typically house 90 desktop PCs in a large open area, with additional breakout rooms and group study rooms available to students. Highly used and very popular, the learning centers provide the students with a dedicated space within the university environment to concentrate on their academic activities. They were a logical prime location for early deployment.


Phase Two of the deployment added all seminar rooms and 80 percent of "bookable" teaching areas (excluding the main lecture halls and laboratories). All staff meeting rooms and common rooms were also included. This phase was only undertaken after the successful completion of Phase One; in other words, the Network and Communications Services team addressed any problems that were identified during Phase One before proceeding with more widespread deployment. Phase Two saw the extension of WLAN coverage into teaching areas and greatly increased the "footprint" of the solution, with more than 150 additional access points deployed.

Phase Three of Griffith University's deployment addressed the lecture halls and scientific laboratories. Only recently completed (late 2005), this phase adds to the coverage and extends the service into practically all teaching areas. Nearly all outside areas where staff and students congregate are now covered.

A planned fourth phase will be undertaken in. This phase will address dead spots identified by end users and the Network and Communications Services team, in addition to remaining areas that were originally deemed low priority. Phase Four will bring the university closer to ubiquitous coverage.

Site Survey

It pays to plan for capacity because as more and more students purchase laptops, providing enough capacity will be critical.

David Renaud, Wireless Network Support Engineer

An independent vendor was appointed to undertake the site surveys and the installation and configuration of the access points. The vendor was given detailed instructions and a template from which to work. These instructions included the stipulation that a signal strength of at least 50 percent (when measured by the Cisco Airnet Client Utility) was required at all locations within the Smart Zone. This requirement was achieved by taking four signal strength measurements at the extreme edges of the Smart Zone. Where coverage problems occurred, external high-gain antennas were used.

Figure 12-3 shows the location of access point naasn003ap01 in a project room. The four black circles mark the locations where Griffith IT staff measured signal strength to ensure that it met the 50 percent benchmark.

Figure 12-3. Validating Signal Strength

Reprinted with permission of Griffith University


Some general guidelines have been adopted over the course of the deployment phases. These guidelines, based upon environmental factors and the nature of university buildings, offer further direction during the site survey process:

  • For buildings that have internal concrete walls, there is one access point per room.

  • For buildings that have internal Gyprock (plasterboard) walls, there is one access point per two to three rooms. However, this is largely determined by the capacity (in terms of potential users) of the rooms, as detailed earlier. If more than 15 concurrent users are expected, more access points are used.

For soundproof rooms and laboratories, access points are mounted inside an AV cabinet or in an area where the signal will pass through a glass window into such a room.

Cabling

During Phase Three, it was decided that two cables per access point would be installed. Originally, this provision was to allow for an extra access point to be installed in the future, should demand increase. However, university IT staff discovered that they could use the second cable for console access, providing out of band (OOB) management capabilities. This capability has proven to be of great assistance to the IT staff, not the least because of the extended nature of the university's wireless network, which is spread over five campus locations. Two cables per access point now forms part of the Office of Facilities Management (OFM) building standard.

Access Point Configuration

The site survey vendor configured the access points, working from a template and detailed work instructions, which expedited the deployment and avoided university staff resourcing problems.

Testing

Upon physical installation of the access points by the site survey vendor, the access points were configured and tested. During each deployment phase and before the service was launched in each area, the WLAN was tested again by IT staff, and coverage maps were generated. Only after service availability was validated were the areas added to the web portal and the WLAN made available to users in that locality.




The Business Case for Enterprise-Class Wireless Lans
The Business Case for Enterprise-Class Wireless LANs
ISBN: 1587201259
EAN: 2147483647
Year: 2004
Pages: 163

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net