Lesson 5.1. Overlapping TasksFigure 5-1. The Predecessors tab in the Task Information dialog box.Figure 5-2. Overlapped tasks with lead timeOverlapping linked tasks means that you want the successor task to begin before the predecessor task ends. Therefore, you give the successor task lead time. Lead time can be entered as a duration or as a task completion percentage.
|