Lesson 9.4. Updating Task Completion PercentageFigure 9-6. The Update Tasks dialog box.Figure 9-7. The updated task in the Gantt chart.The quickest way to track the progress of an individual task is by recording its completion percentage. For example, it's easier to say that a mark is half done than to say that 25 of the 50 scheduled work hours have been completed. Tracking task progress allows Project to recalculate your schedule. Let's practice updating task progress by its completion percentage.
|