|
|
The process of reducing the number of sequential activities and replacing them with parallel activities.
The actual or estimated date of an activityís completion.
The absolute quantity of a material resource to be used to complete an assignment.
A set cost for a task that remains constant regardless of the taskís duration.
A calendar date that cannot be moved or changed during the schedule.
A task in which the duration is a fixed value, regardless of any changes to the work or resources.
A task in which the assigned units are a fixed value, regardless of any changes to the duration or resources.
The amount of time that an activity can slip past its duration without delaying the rest of the project.
See network diagram.
The excess time available before the start of the following activity, assuming both activities start on their early start date.
A type of chart, created by Henry Gantt, that presents the sequence and time required for a projectís activities; typically viewed as horizontal bars against a time scale.
In Project Professional, a placeholder resource used to specify the skill a resource needs in order to be assigned to a specific task.
A one-sentence declaration of what one intends to accomplish.
To combine or arrange tasks or resources according to specific criteria.
A graphic display of resource usage over a period of time.
An activity that can be forced to start on its earliest feasible date, even if that means overloading a resource.
That stage of the project cycle where products and services are field tested and measured.
A finish date for an activity that is dictated by external constraints.
A start date for an activity that is dictated by external constraints.
An activity that has been started but not yet completed.
Resources expended that are not directly identified to any specific project, product, or service.
The process of bringing disparate people, activities, business units, and other items together to perform more effectively.
A set of start and finish dates that you save at certain stages of your project.
An activity with neither predecessors nor successors.
|
|