Project Management


Maturity Level 2

Requirements Management

The purpose of Requirements Management is to manage the requirements of the project's products and product components , and to identify inconsistencies between those requirements and the project's plans and work products.

Specific Practices by Specific Goal:

SG1

Manage Requirements

Requirements are managed and inconsistencies with project plans and work products are identified.

SP1.1

Obtain an Understanding of Requirements

Develop an understanding with the requirements providers on the meaning of the requirements.

SP1.2

Obtain Commitment to Requirements

Obtain commitment to the requirements from the project participants .

SP1.3

Manage Requirements Changes

Manage changes to the requirements as they evolve during the project.

SP1.4

Maintain Bidirectional Traceability of Requirements

Maintain bidirectional traceability among the requirements and the project plans and work products.

SP1.5

Identify Inconsistencies between Project Work and Requirements

Identify inconsistencies between the project plans and work products and the requirements.

Project Planning

The purpose of Project Planning is to establish and maintain plans that define project activities.

Specific Practices by Specific Goal:

SG1

Establish Estimates

Estimates of project planning parameters are established and maintained .

SP1.1

Estimate the Scope of the Project

Establish a top-level work breakdown structure (WBS) to estimate the scope of the project.

SP1.2

Establish Estimates of Work Product and Task Attributes

Establish and maintain estimates of the attributes of the work products and tasks .

SP1.3

Define Project Life Cycle

Define the project life-cycle phases upon which to scope the planning effort.

SP1.4

Determine Estimates of Effort and Cost

Estimate the project effort and cost for the work products and tasks based on estimation rationale.

SG2

Develop a Project Plan

A project plan is established and maintained as the basis for managing the project.

SP2.1

Establish the Budget and Schedule

Establish and maintain the project's budget and schedule.

SP2.2

Identify Project Risks

Identify and analyze project risks.

SP2.3

Plan for Data Management

Plan for the management of project data.

SP2.4

Plan for Project Resources

Plan for necessary resources to perform the project.

SP2.5

Plan for Needed Knowledge and Skills

Plan for knowledge and skills needed to perform the project.

SP2.6

Plan Stakeholder Involvement

Plan the involvement of identified stakeholders.

SP2.7

Establish the Project Plan

Establish and maintain the overall project plan content.

SG3

Obtain Commitment to the Plan

Commitments to the project plan are established and maintained.

SP3.1

Review Plans that Affect the Project

Review all plans that affect the project to understand project commitments.

SP3.2

Reconcile Work and Resource Levels

Reconcile the project plan to reflect available and estimated resources.

SP3.3

Obtain Plan Commitment

Obtain commitment from relevant stakeholders responsible for performing and supporting plan execution.

Project Monitoring and Control

The purpose of Project Monitoring and Control is to provide an understanding of the project's progress so that appropriate corrective actions can be taken when the project's performance deviates significantly from the plan.

Specific Practices by Specific Goal:

SG1

Monitor Project against Plan

Actual performance and progress of the project are monitored against the project plan.

SP1.1

Monitor Project Planning Parameters

Monitor the actual values of the project planning parameters against the project plan.

SP1.2

Monitor Commitments

Monitor commitments against those identified in the project plan.

SP1.3

Monitor Project Risks

Monitor risks against those identified in the project plan.

SP1.4

Monitor Data Management

Monitor the management of project data against the project plan.

SP1.5

Monitor Stakeholder Involvement

Monitor stakeholder involvement against the project plan.

SP1.6

Conduct Progress Reviews

Periodically review the project's progress, performance, and issues.

SP1.7

Conduct Milestone Reviews

Review the accomplishments and results of the project at selected project milestones.

SG2

Manage Corrective Action to Closure

Corrective actions are managed to closure when the project's performance or results deviate significantly from the plan.

SP2.1

Analyze Issues

Collect and analyze the issues and determine the corrective actions necessary to address the issues.

SP2.2

Take Corrective Action

Take corrective action on identified issues.

SP2.3

Manage Corrective Action

Manage corrective actions to closure.

Supplier Agreement Management

The purpose of Supplier Agreement Management is to manage the acquisition of products from suppliers for which there exists a formal agreement.

Specific Practices by Specific Goal:

SG1

Establish Supplier Agreements

Agreements with the suppliers are established and maintained.

SP1.1

Determine Acquisition Type

Determine the type of acquisition for each product or product component to be acquired .

SP1.2

Select Suppliers

Select suppliers based on an evaluation of their ability to meet the specified requirements and established criteria.

SP1.3

Establish Supplier Agreements

Establish and maintain formal agreements with the supplier.

SG2

Satisfy Supplier Agreements

Agreements with the suppliers are satisfied by both the project and the supplier.

SP2.1

Review COTS Products

Review candidate COTS products to ensure they satisfy the specified requirements that are covered under a supplier agreement.

SP2.2

Execute the Supplier Agreement

Perform activities with the supplier as specified in the supplier agreement.

SP2.3

Accept the Acquired Product

Ensure that the supplier agreement is satisfied before accepting the acquired product.

SP2.4

Transition Products

Transition the acquired products from the supplier to the project.

Measurement and Analysis

The purpose of Measurement and Analysis is to develop and sustain a measurement capability that is used to support management information needs.

Specific Practices by Specific Goal:

SG1

Align Measurement and Analysis Activities

Measurement objectives and activities are aligned with identified information needs and objectives.

SP1.1

Establish Measurement Objectives

Establish and maintain measurement objectives that are derived from identified information needs and objectives.

SP1.2

Specify Measures

Specify measures to address the measurement objectives.

SP1.3

Specify Data Collection and Storage Procedures

Specify how measurement data will be obtained and stored.

SP1.4

Specify Analysis Procedures

Specify how measurement data will be analyzed and reported .

SG2

Provide Measurement Results

Measurement results that address identified information needs and objectives are provided.

SP2.1

Collect Measurement Data

Obtain specified measurement data.

SP2.2

Analyze Measurement Data

Analyze and interpret measurement data.

SP2.3

Store Data and Results

Manage and store measurement data, measurement specifications, and analysis results.

SP2.4

Communicate Results

Report results of measurement and analysis activities to all relevant stakeholders.

Process and Product Quality Assurance

The purpose of Process and Product Quality Assurance is to provide staff and management with objective insight into processes and associated work products.

Specific Practices by Specific Goal:

SG1

Objectively Evaluate Processes and Work Products

Adherence of the performed process and associated work products and services to applicable process descriptions, standards, and procedures is objectively evaluated.

SP1.1

Objectively Evaluate Processes

Objectively evaluate the designated performed processes against the applicable process descriptions, standards, and procedures.

SP1.2

Objectively Evaluate Work Products and Services

Objectively evaluate the designated work products and services against the applicable process descriptions, standards, and procedures.

SG2

Provide Objective Insight

Noncompliance issues are objectively tracked and communicated, and resolution is ensured.

SP2.1

Communicate and Ensure Resolution of Noncompliance Issues

Communicate quality issues and ensure resolution of non-compliance issues with the staff and managers.

SP2.2

Establish Records

Establish and maintain records of the quality assurance activities.

Configuration Management

The purpose of Configuration Management is to establish and maintain the integrity of work products using configuration identification, configuration control, configuration status accounting, and configuration audits .

Specific Practices by Specific Goal:

SG1

Establish Baselines

Baselines of identified work products are established.

SP1.1

Identify Configuration Items

Identify the configuration items, components, and related work products that will be placed under configuration management.

SP1.2

Establish a Configuration Management System

Establish and maintain a configuration management and change management system for controlling work products.

SP1.3

Create or Release Baselines

Create or release baselines for internal use and for delivery to the customer.

SG2

Track and Control Changes

Changes to the work products under configuration management are tracked and controlled.

 

SP2.1

Track Change Requests

Track change requests for the configuration items.

SP2.2

Control Configuration Items

Control changes to the configuration items.

SG3

Establish Integrity

Integrity of baselines is established and maintained.

SP3.1

Establish Configuration Management Records

Establish and maintain records describing configuration items.

SP3.2

Perform Configuration Audits

Perform configuration audits to maintain integrity of the configuration baselines.

Requirements Development

The purpose of Requirements Development is to produce and analyze customer, product, and product-component requirements.

Specific Practices by Specific Goal:

SG1

Develop Customer Requirements

Stakeholder needs, expectations, constraints, and interfaces are collected and translated into customer requirements.

SP1.1

Elicit Needs

Elicit stakeholder needs, expectations, constraints, and interfaces for all phases of the product life cycle.

 

The following specific practice appears in the continuous representation as SP1.1-1, but is subsumed in the staged representation by SP1.1, Elicit Needs. The specific practice is presented here in gray only as informative material.

 

SP1.1-1

Collect Stakeholder Needs

Identify and collect stakeholder needs, expectations, constraints, and interfaces for all phases of the product life cycle.

 

SP1.2

Develop the Customer Requirements

Transform stakeholder needs, expectations, constraints, and interfaces into customer requirements.

SG2

Develop Product Requirements

Customer requirements are refined and elaborated to develop product and product-component requirements.

SP2.1

Establish Product and Product-Component Requirements

Establish and maintain product and product-component requirements, which are based on the customer requirements.

SP2.2

Allocate Product-Component Requirements

Allocate the requirements for each product component.

SP2.3

Identify Interface Requirements

Identify interface requirements.

SG3

Analyze and Validate Requirements

The requirements are analyzed and validated , and a definition of required functionality is developed.

SP3.1

Establish Operational Concepts and Scenarios

Establish and maintain operational concepts and associated scenarios.

SP3.2

Establish a Definition of Required Functionality

Establish and maintain a definition of required functionality.

SP3.3

Analyze Requirements

Analyze requirements to ensure that they are necessary and sufficient.

SP3.4

Analyze Requirements to Achieve Balance

Analyze requirements to balance stakeholder needs and constraints.

SP3.5

Validate Requirements with Comprehensive Methods

Validate requirements to ensure the resulting product will perform as intended in the user 's environment using multiple techniques as appropriate.

 

The following specific practice appears in the continuous representation as SP3.5-1, but is subsumed in the staged representation by SP3.5, Validate Requirements with Comprehensive Methods. The specific practice is presented here in gray only as informative material.

 

SP3.5-1

Validate Requirements

Validate requirements to ensure the resulting product will perform appropriately in its intended-use environment.

Technical Solution

The purpose of Technical Solution is to design, develop, and implement solutions to requirements. Solutions, designs, and implementations encompass products, product components, and product-related life-cycle processes either singly or in combinations, as appropriate.

Specific Practices by Specific Goal:

SG1

Select Product-Component Solutions

Product or product-component solutions are selected from alternative solutions.

SP1.1

Develop Detailed Alternative Solutions and Selection Criteria

Develop detailed alternative solutions and selection criteria.

 

The following specific practice appears in the continuous representation as SP1.1-1, but is subsumed in the staged representation by SP1.1, Develop Detailed Alternative Solutions and Selection Criteria. The specific practice is presented here in gray only as informative material.

 

SP1.1-1

Develop Alternative Solutions and Selection Criteria

Develop alternative solutions and selection criteria.

 

SP1.2

Evolve Operational Concepts and Scenarios

Evolve the operational concept, scenarios, and environments to describe the conditions, operating modes, and operating states specific to each product component.

SP1.3

Select Product-Component Solutions

Select the product-component solutions that best satisfy the criteria established.

SG2

Develop the Design

Product or product-component designs are developed.

SP2.1

Design the Product or Product Component

Develop a design for the product or product component.

SP2.2

Establish a Technical Data Package

Establish and maintain a technical data package.

SP2.3

Design Interfaces Using Criteria

Design comprehensive product-component interfaces in terms of established and maintained criteria.

 

The following specific practice appears in the continuous representation as SP2.3-1, but is subsumed in the staged representation by SP2.3, Design Interfaces Using Criteria. The specific practice is presented here in gray only as informative material.

 

SP2.3-1

Establish Interface Descriptions

Establish and maintain the solution for product-component interfaces.

 

SP2.4

Perform Make, Buy, or Reuse Analyses

Evaluate whether the product components should be developed, purchased, or reused based on established criteria.

SG3

Implement the Product Design

Product components and associated support documentation are implemented from their designs.

SP3.1

Implement the Design

Implement the designs of the product components.

SP3.2

Develop Product Support Documentation

Develop and maintain the end-use documentation.

Product Integration

The purpose of Product Integration is to assemble the product from the product components, ensure that the product, as integrated, functions properly, and deliver the product.

Specific Practices by Specific Goal:

SG1

Prepare for Product Integration

Preparation for product integration is conducted .

SP1.1

Determine Integration Sequence

Determine the product-component integration sequence.

SP1.2

Establish the Product Integration Environment

Establish and maintain the environment needed to support the integration of the product components.

SP1.3

Establish Product Integration Procedures and Criteria

Establish and maintain procedures and criteria for integration of the product components.

SG2

Ensure Interface Compatibility

The product-component interfaces, both internal and external, are compatible.

SP2.1

Review Interface Descriptions for Completeness

Review interface descriptions for coverage and completeness.

SP2.2

Manage Interfaces

Manage internal and external interface definitions, designs, and changes for products and product components.

SG3

Assemble Product Components and Deliver the Product

Verified product components are assembled and the integrated, verified , and validated product is delivered.

SP3.1

Confirm Readiness of Product Components for Integration

Confirm, prior to assembly, that each product component required to assemble the product has been properly identified, functions according to its description, and that the product-component interfaces comply with the interface descriptions.

SP3.2

Assemble Product Components

Assemble product components according to the product integration sequence and available procedures.

SP3.3

Evaluate Assembled Product Components

Evaluate assembled product components for interface compatibility.

SP3.4

Package and Deliver the Product or Product Component

Package the assembled product or product component and deliver it to the appropriate customer.

Verification

The purpose of Verification is to ensure that selected work products meet their specified requirements.

Specific Practices by Specific Goal:

SG1

Prepare for Verification

Preparation for verification is conducted.

SP1.1

Select Work Products for Verification

Select the work products to be verified and the verification methods that will be used for each.

 

SP1.2

Establish the Verification Environment

Establish and maintain the environment needed to support verification.

SP1.3

Establish Verification Procedures and Criteria

Establish and maintain verification procedures and criteria for the selected work products.

SG2

Perform Peer Reviews

Peer reviews are performed on selected work products.

SP2.1

Prepare for Peer Reviews

Prepare for peer reviews of selected work products.

SP2.2

Conduct Peer Reviews

Conduct peer reviews on selected work products and identify issues resulting from the peer review.

SP2.3

Analyze Peer Review Data

Analyze data about preparation, conduct, and results of the peer reviews.

SG3

Verify Selected Work Products

Selected work products are verified against their specified requirements.

SP3.1

Perform Verification

Perform verification on the selected work products.

SP3.2

Analyze Verification Results and Identify Corrective Action

Analyze the results of all verification activities and identify corrective action.

Validation

The purpose of Validation is to demonstrate that a product or product component fulfills its intended use when placed in its intended environment.

Specific Practices by Specific Goal:

SG1

Prepare for Validation

Preparation for validation is conducted.

SP1.1

Select Products for Validation

Select products and product components to be validated and the validation methods that will be used for each.

 

SP1.2

Establish the Validation Environment

Establish and maintain the environment needed to support validation.

SP1.3

Establish Validation Procedures and Criteria

Establish and maintain procedures and criteria for validation.

SG2

Validate Product or Product Components

The product or product components are validated to ensure that they are suitable for use in their intended operating environment.

SP2.1

Perform Validation

Perform validation on the selected products and product components.

SP2.2

Analyze Validation Results

Analyze the results of the validation activities and identify issues.

Organizational Process Focus

The purpose of Organizational Process Focus is to plan and implement organizational process improvement based on a thorough understanding of the current strengths and weaknesses of the organization's processes and process assets.

Specific Practices by Specific Goal:

SG1

Determine Process-Improvement Opportunities

Strengths, weaknesses, and improvement opportunities for the organization's processes are identified periodically and as needed.

SP1.1

Establish Organizational Process Needs

Establish and maintain the description of the process needs and objectives for the organization.

SP1.2

Appraise the Organization's Processes

Appraise the processes of the organization periodically and as needed to maintain an understanding of their strengths and weaknesses.

SP1.3

Identify the Organization's Process Improvements

Identify improvements to the organization's processes and process assets.

SG2

Plan and Implement Process-Improvement Activities

Improvements are planned and implemented, organizational process assets are deployed, and process-related experiences are incorporated into the organizational process assets.

SP2.1

Establish Process Action Plans

Establish and maintain process action plans to address improvements to the organization's processes and process assets.

SP2.2

Implement Process Action Plans

Implement process action plans across the organization.

SP2.3

Deploy Organizational Process Assets

Deploy organizational process assets across the organization.

SP2.4

Incorporate Process-Related Experiences into the Organizational Process Assets

Incorporate process-related work products, measures, and improvement information derived from planning and performing the process into the organizational process assets.

Organizational Process Definition

The purpose of Organizational Process Definition is to establish and maintain a usable set of organizational process assets.

Specific Practices by Specific Goal:

SG1

Establish Organizational Process Assets

A set of organizational process assets is established and maintained.

SP1.1

Establish Standard Processes

Establish and maintain the organization's set of standard processes.

SP1.2

Establish Life-Cycle Model Descriptions

Establish and maintain descriptions of the life-cycle models approved for use in the organization.

SP1.3

Establish Tailoring Criteria and Guidelines

Establish and maintain the tailoring criteria and guidelines for the organization's set of standard processes.

SP1.4

Establish the Organization's Measurement Repository

Establish and maintain the organization's measurement repository.

 

SP1.5

Establish the Organization's Process Asset Library

Establish and maintain the organization's process asset library.

Organizational Training

The purpose of Organizational Training is to develop the skills and knowledge of people so they can perform their roles effectively and efficiently .

Specific Practices by Specific Goal:

SG1

Establish an Organizational Training Capability

A training capability that supports the organization's management and technical roles is established and maintained.

SP1.1

Establish the Strategic Training Needs

Establish and maintain the strategic training needs of the organization.

SP1.2

Determine Which Training Needs Are the Responsibility of the Organization

Determine which training needs are the responsibility of the organization and which will be left to the individual project or support group .

SP1.3

Establish an Organizational Training Tactical Plan

Establish and maintain an organizational training tactical plan.

SP1.4

Establish Training Capability

Establish and maintain training capability to address organizational training needs.

SG2

Provide Necessary Training

Training necessary for individuals to perform their roles effectively is provided.

SP2.1

Deliver Training

Deliver the training following the organizational training tactical plan.

SP2.2

Establish Training Records

Establish and maintain records of the organizational training.

SP2.3

Assess Training Effectiveness

Assess the effectiveness of the organization's training program.

Integrated Project Management for IPPD

The purpose of Integrated Project Management is to establish and manage the project and the involvement of the relevant stakeholders according to an integrated and defined process that is tailored from the organization's set of standard processes.

For Integrated Product and Process Development, Integrated Project Management also covers the establishment of a shared vision for the project and a team structure for integrated teams that will carry out the objectives of the project.

Specific Practices by Specific Goal:

SG1

Use the Project's Defined Process

The project is conducted using a defined process that is tailored from the organization's set of standard processes.

SP1.1

Establish the Project's Defined Process

Establish and maintain the project's defined process.

SP1.2

Use Organizational Process Assets for Planning Project Activities

Use the organizational process assets and measurement repository for estimating and planning the project's activities.

SP1.3

Integrate Plans

Integrate the project plan and the other plans that affect the project to describe the project's defined process.

SP1.4

Manage the Project Using the Integrated Plans

Manage the project using the project plan, the other plans that affect the project, and the project's defined process.

SP1.5

Contribute to the Organizational Process Assets

Contribute work products, measures, and documented experiences to the organizational process assets.

SG2

Coordinate and Collaborate with Relevant Stakeholders

Coordination and collaboration of the project with relevant stakeholders is conducted.

SP2.1

Manage Stakeholder Involvement

Manage the involvement of the relevant stakeholders in the project.

SP2.2

Manage Dependencies

Participate with relevant stakeholders to identify, negotiate, and track critical dependencies.

SP2.3

Resolve Coordination Issues

Resolve issues with relevant stakeholders.

SG3

Use the Project's Shared Vision for IPPD

The project is conducted using the project's shared vision.

SP3.1

Define Project's Shared-Vision Context

Identify expectations, constraints, interfaces, and operational conditions applicable to the project's shared vision.

SP3.2

Establish the Project's Shared Vision

Establish and maintain a shared vision for the project.

SG4

Organize Integrated Teams for IPPD

The integrated teams needed to execute the project are identified, defined, structured, and tasked.

SP4.1

Determine Integrated Team Structure for the Project

Determine the integrated team structure that will best meet the project objectives and constraints.

SP4.2

Develop a Preliminary Distribution of Requirements to Integrated Teams

Develop a preliminary distribution of requirements, responsibilities, authorities, tasks, and interfaces to teams in the selected integrated team structure.

SP4.3

Establish Integrated Teams

Establish and maintain teams in the integrated team structure.

Risk Management

The purpose of Risk Management is to identify potential problems before they occur, so that risk-handling activities may be planned and invoked as needed across the life of the product or project to mitigate adverse impacts on achieving objectives.

Specific Practices by Specific Goal:

SG1

Prepare for Risk Management

Preparation for risk management is conducted.

SP1.1

Determine Risk Sources and Categories

Determine risk sources and categories.

SP1.2

Define Risk Parameters

Define the parameters used to analyze and categorize risks, and the parameters used to control the risk management effort.

SP1.3

Establish a Risk Management Strategy

Establish and maintain the strategy to be used for risk management.

SG2

Identify and Analyze Risks

Risks are identified and analyzed to determine their relative importance.

SP2.1

Identify Risks

Identify and document the risks.

SP2.2

Evaluate, Categorize, and Prioritize Risks

Evaluate and categorize each identified risk using the defined risk categories and parameters, and determine its relative priority.

SG3

Mitigate Risks

Risks are handled and mitigated, where appropriate, to reduce adverse impacts on achieving objectives.

SP3.1

Develop Risk Mitigation Plans

Develop a risk mitigation plan for the most important risks to the project, as defined by the risk management strategy.

SP3.2

Implement Risk Mitigation Plans

Monitor the status of each risk periodically and implement the risk mitigation plan as appropriate.

Integrated Teaming

The purpose of Integrated Teaming is to form and sustain an integrated team for the development of work products.

Specific Practices by Specific Goal:

SG1

Establish Team Composition

A team composition that provides the knowledge and skills required to deliver the team's product is established and maintained.

SP1.1

Identify Team Tasks

Identify and define the team's specific internal tasks to generate the team's expected output.

SP1.2

Identify Needed Knowledge and Skills

Identify the knowledge, skills, and functional expertise needed to perform team tasks.

SP1.3

Assign Appropriate Team Members

Assign the appropriate personnel to be team members based on required knowledge and skills.

SG2

Govern Team Operation

Operation of the integrated team is governed according to established principles.

SP2.1

Establish a Shared Vision

Establish and maintain a shared vision for the integrated team that is aligned with any overarching or higher-level vision.

SP2.2

Establish a Team Charter

Establish and maintain a team charter based on the integrated team's shared vision and overall team objectives.

SP2.3

Define Roles and Responsibilities

Clearly define and maintain each team member's roles and responsibilities.

SP2.4

Establish Operating Procedures

Establish and maintain integrated team operating procedures.

SP2.5

Collaborate among Interfacing Teams

Establish and maintain collaboration among interfacing teams.

Integrated Supplier Management

The purpose of Integrated Supplier Management is to proactively identify sources of products that may be used to satisfy the project's requirements and to manage selected suppliers while maintaining a cooperative project-supplier relationship.

Specific Practices by Specific Goal:

SG1

Analyze and Select Sources of Products

Potential sources of products that best fit the needs of the project are identified, analyzed, and selected.

SP1.1

Analyze Potential Sources of Products

Identify and analyze potential sources of products that can be used to satisfy the project's requirements.

SP1.2

Evaluate and Determine Sources of Products

Use a formal evaluation process to determine which sources of custom-made and off-the-shelf products to use.

SG2

Coordinate Work with Suppliers

Work is coordinated with suppliers to ensure the supplier agreement is executed appropriately.

 

SP2.1

Monitor Selected Supplier Processes

Monitor and analyze selected processes used by the supplier.

SP2.2

Evaluate Selected Supplier Work Products

For custom-made products, evaluate selected supplier work products.

SP2.3

Revise the Supplier Agreement or Relationship

Revise the supplier agreement or relationship, as appropriate, to reflect changes in conditions.

Decision Analysis and Resolution

The purpose of Decision Analysis and Resolution is to analyze possible decisions using a formal evaluation process that evaluates identified alternatives against established criteria.

Specific Practices by Specific Goal:

SG1

Evaluate Alternatives

Decisions are based on an evaluation of alternatives using established criteria.

SP1.1

Establish Guidelines for Decision Analysis

Establish and maintain guidelines to determine which issues are subject to a formal evaluation process.

SP1.2

Establish Evaluation Criteria

Establish and maintain the criteria for evaluating alternatives, and the relative ranking of these criteria.

SP1.3

Identify Alternative Solutions

Identify alternative solutions to address issues.

SP1.4

Select Evaluation Methods

Select the evaluation methods.

SP1.5

Evaluate Alternatives

Evaluate alternative solutions using the established criteria and methods.

SP1.6

Select Solutions

Select solutions from the alternatives based on the evaluation criteria.

Organizational Environment for Integration

The purpose of Organizational Environment for Integration is to provide an Integrated Product and Process Development (IPPD) infrastructure and manage people for integration.

Specific Practices by Specific Goal:

SG1

Provide IPPD Infrastructure

An infrastructure that maximizes the productivity of people and affects the collaboration necessary for integration is provided.

SP1.1

Establish the Organization's Shared Vision

Establish and maintain a shared vision for the organization.

SP1.2

Establish an Integrated Work Environment

Establish and maintain an integrated work environment that supports IPPD by enabling collaboration and concurrent development.

SP1.3

Identify IPPD-Unique Skill Requirements

Identify the unique skills needed to support the IPPD environment.

SG2

Manage People for Integration

People are managed to nurture the integrative and collaborative behaviors of an IPPD environment.

SP2.1

Establish Leadership Mechanisms

Establish and maintain leadership mechanisms to enable timely collaboration.

SP2.2

Establish Incentives for Integration

Establish and maintain incentives for adopting and demonstrating integrative and collaborative behaviors at all levels of the organization.

SP2.3

Establish Mechanisms to Balance Team and Home Organization Responsibilities

Establish and maintain organizational guidelines to balance team and home organization responsibilities.




Interpreting the CMMI(c) A Process Improvement Approach
Interpreting the CMMI (R): A Process Improvement Approach, Second Edition
ISBN: 142006052X
EAN: 2147483647
Year: 2005
Pages: 205

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net