Defining a Multiple-Contour Availability

     

You can create a contoured availability that contains several different unit values over time. Closed-end availability is when the first row is a date in the Available From field and/or the last row is a date in the Available To field. This specifies that prior to the date in the first row's Available From date and after the date in the last row's Available To date, the resource is not available (the Max Units value is 0%).

graphics/06inf07.jpg

graphics/one_icon.jpg Double-click on the resource you want to define.

graphics/two_icon.jpg If the first row's Available From date contains a date, the resource will have a Max Units value of 0% any time prior to that date, making it unavailable for work on the project. If this field contains the value NA, the resource is available for the Units value on this row up until the Available To date.

graphics/three_icon.jpg Make sure that there are no breaks between the Available To date on one row and the Available From date on the next row. If a break occurs, the resource will not be available (0%) during the time between the dates.

graphics/four_icon.jpg If the last row's Available To date contains a date value, the resource will not be available (0%) for any dates after this date. If you want the resource to be available at the Units value on this row for all dates after the Available From date, type NA in the Available To date field.

This example has the resource available at 0% for all dates prior to 7/1/2004. It then has him available at 25% from 7/1/2004 to 7/30/2004. Between 7/31/2004 and 8/31/2004, he is available at 50%. Then between 9/1/2004 and 9/30/2004, he is available at 100%. Finally, after 9/30/2004, he is available at 0%.



Show Me. Microsoft Office Project 2003
Show Me Microsoft Office Project 2003
ISBN: 0789730693
EAN: 2147483647
Year: 2003
Pages: 204

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net