1. | A project schedule is comprised of which of the following? Choose all that apply:
|
|
2. | What two things can a project manager do to reduce the amount of time required to complete a task?
|
|
3. | Which of the following will add time to a project schedule?
|
|
4. | Of the following, what are two drawbacks of a Gantt chart?
|
|
5. | What is a Project Network Diagram?
|
|
6. | Of the following, which one is not a true statement about network diagrams?
|
|
7. | All of the following statements about slack are incorrect except for which one?
|
|
8. | What is the Precedence Diagramming Method (PDM)?
|
|
9. | What law states that work will expand to fill the amount of time allotted to it?
|
|
10. | You are the project manager of a web server and web site upgrade. You have assigned Mark the task of creating the web pages and Janice the task of developing the web pages. Mark and Janice can work on their assigned tasks concurrently. What type of relationship do these tasks have?
|
|
11. | Phil is the project manager of a network upgrade. All of the client workstations are to be replaced , and this task has been assigned to Steve, Harry, and Beth. Once the physical workstations are in place, Sam will release an automated script to deploy an operating system to each of the new workstations. What type of relationship best describes these two tasks?
|
|
12. | When a project manager begins to create the network diagram, what type of relationship between all of the tasks would reduce any risk in the original plan?
|
|
13. | Why should a project manager avoid assigning specific dates to tasks when at all possible during the creation of the network diagram?
|
|
14. | Elizabeth is the project manager for the development of a new database and a web application that will access the database. Originally, the creation of the database and a portion of the application development was scheduled to happen concurrently. Elizabeth felt, however, that the application development phase should not start until most of the database was created. What type of constraint is this?
|
|
15. | Why must lag times be scheduled between tasks in a Project Network Diagram?
|
|
Answers
1. | A, B, D. A project schedule is the compilation of all of the tasks to be completed within a project and the assignment of resources, and should reflect the entries of the WBS. If you are using Microsoft Project, then you can streamline your efforts, as Microsoft Project will allow you to create the network diagram and work toward the WBS. |
2. | A, B. By partitioning a task into smaller work units, a project manager can allow the work units to overlap. A project manager can also add more resources, particularly team members , to a task to reduce the amount of time it takes to complete the task. Moving the task into or out of the critical path isn t really an option. |
3. | A. Lag time is waiting time. If a project manager adds lag time, the project schedule will expand. |
4. | B, C. Gantt charts do not display task details like a network diagram does. Gantt charts also do not reflect the short path to project completion. A network diagram is more powerful than a Gantt chart because it allows tasks to be moved and adjusted to participate in schedule compression. |
5. | C. A network diagram is a fluid mapping of the entire project, not just one phase. A network diagram is not an extension of the Gantt chart or the WBS. |
6. | D. Network diagrams do not allow for detailed time management. They do allow for some time planning, but usually only down to days or weeks ” not hours and minutes. Network diagrams do allow for contingency plans, detailed planning, and implementation tracking. |
7. | D. Slack is the amount of time an activity s completion can be delayed without delaying the project end date. |
8. | B. PDM, Precedence Diagramming Method, focuses on the activities required within a project rather than the start and end of activities. |
9. | C. When project team members and project managers add time to their time estimates they ll likely succumb to Parkinson s Law: work expands to fill the time allotted to it. |
10. | B. These tasks can use SS dependency, which means start to start. The FS dependency is the most common, which means finish to start. The FF means the tasks must be finish to finish and the last dependency is start to finish. |
11. | A. FS. Because the tasks involving the replacement of workstations must be completed before the script can run, the dependency used is FS, or finish to start. |
12. | A. FS. To reduce practically all risk in the network diagram, all tasks can begin with FS relationships. This means that no task would begin until its predecessor had been completed. Once the diagram has been created, tasks can be rearranged to represent other relationships. |
13. | D. Tasks assigned to dates do not consider successor and predecessor tasks. This becomes a huge problem when upstream tasks are delayed by several days; the task assigned to a specific date does not change to reflect the changes of the tasks upstream. Whenever possible, do not assign tasks to a specific date. Examples include when a particular resource is available or a consultant is scheduled to be present. |
14. | A. Because Elizabeth had a gut feeling that the tasks should be changed to FS, it s a discretionary constraint. If the decision had been made on prior experience, it would have been an experience constraint. If the task needed to be delayed because of a resource, it would have been a resource constraint. An organization constraint is typically enforced when another project within the organization is delaying the success of the current project. |
15. | D. Lag times allow other events to be completed before successor tasks can begin. For example, a dependent task is to mail a survey to all of the network users. Before the successor task, analyzing the user surveys, can happen, there must be time allotted for the users to respond to the survey. It s not an actual task, but it still requires times within the diagram. |