Once a course of action has been developed for a risk event, the strategy must be implemented. A good strategy includes risk triggers to alert the project team of impending risk events. Although the project manager has the ultimate responsibility for the risk plan, she may designate a team member to monitor risk events likely to occur in their technical areas. Monitoring risks involves more than observing whether the anticipated risks occur; it involves determining if the strategies to respond to the risks are adequate or whether other actions are required, which is a function of the next step—tracking risk response.
|