Changing Project Scope


In the course of checking and adjusting your project plan, you might need to cut scope. For example, you might need to cut tasks you perceive as optional to meet the finish date. To bring project costs in line with your allotted budget, you might cut tasks associated with increased quality or quantity that you think you can live without. Or maybe you need to cut an entire phase or deliverable in order to alleviate resource overallocation .

Note  

Your task list is likely based on the scope statement that all the stakeholders, including customers, originally approved. If you need to cut scope, you might have to go back and obtain stakeholder approval for these changes.

To delete a task, simply click its row heading and press the Delete key. You can also delete a summary task that represents an entire phase or group of related tasks. To delete a summary task, click its row heading and press the Delete key. A message appears and warns you that deleting the summary task will delete all of its subtasks as well. Click OK to confirm that you want to do this.




Microsoft Office Project 2003 Inside Out
Microsoft Office Project 2003 Inside Out
ISBN: 0735619581
EAN: 2147483647
Year: 2003
Pages: 268

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net